Form_2519_-_Welding_ _Safety_Checklist.doc
DOC document 35 KB Posted
- Attached to
- Construct Addition to Corrosion Control Facility Bldg 180 Federal contract opportunity
- Solicitation number
- F3QCCL6062A003
About this file
Welding and Safety
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_2_of_2.pdf | ||
| FA8501-16-R-0013-0003.pdf | ||
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_1_of_2.pdf | ||
| Amendment_2_130401.pdf | ||
| RFI_Questions_and_Answers_Bldg_180_.docx | DOCX document | |
| Amendment_for_Bldg_180.pdf | ||
| RFI_Questions_and_Answers_for_Bldg_180__3.docx | DOCX document | |
| RFI_Questions_and_Answers_Bldg_180__2.docx | DOCX document | |
| UHHZ130401_Contractors_Site_Visit_Attendees.pdf | ||
| RFI's_and_Answers_for_Bldg_180.docx | DOCX document | |
| Special_Warranty_Requirements.doc | DOC document | |
| Master_Utility_Outage.pdf | ||
| Specifications_Vol._1_of_2.pdf | ||
| Specifications_Vol._2_of_2.pdf | ||
| App_C_UHHZ_130401.pdf | ||
| 11-Mar-2016_Wage_Determination.pdf | ||
| Govt._Project_Time_Estimate_Sheet.xlsx | XLSX spreadsheet | |
| FA8501-16-R-0013.pdf | ||
| Half_Size_Drawings.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ALL PURPOSE CHECKLIST
PAGE 1 of 1 PAGES
| UHHZ 130401 Addition/Alterations to Aircraft Corrosion Control Facility, Building #180 |
| OPR |
DATE
WELDING & CUTTING SAFETY
References: a. AFISC/SE Msg 192000Z Dec 85, ALSAFECOM 001/1985 Welding & Cutting Safety
b. AFLC/ISC Msg 201830Z 0001/1985 Welding & Cutting Safety
c. 78 CEG/CEF Ltr 27 Jan 86, ALSFECOM 001/1985 Welding & Cutting Safety Message
ENGINEERING
1. Has the project been reviewed to insure that the cutting, welding or brazing required or allowed in the project is necessary for technical or economical reasons in lieu of a safe method?
YES
NA ____
Signatures:
2. Are specific required precautions that are over and above those required by the General Requirements (Section 1A) and by the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1) adequately covered in the design documents? YES
NA _____
3. Are requirements for welder testing or certification specified in the project documents? YES
NA _____
4. Have all Safety, Health and Fire comments been satisfactorily addressed? Have they signed the project drawings when required?
YES _____
NA _________
CONSTRUCTION MANAGEMENT
5. Have specified and general precautions for cutting and welding safety been covered at the preconstruction conference?
YES
NA _________
6. Is the contractor's welder properly certified and knowledgeable of the materials and facility hazards involved in his work?
YES
NA __________
7. For any change in the contract that involves cutting or welding, has it been coordinated with the project engineer and all necessary Safety, Health of Fire agencies?
8. Was fire prevention inspection performed by the welding permit issuing authority (CEF) at the job site? Is all required protective equipment in place?
ON-SITE SUPERVISOR
9. Are you, the on-site Air Force and/or contractor supervisor, fully aware of fire safety prevention requirements? If the on-site supervisor is a replacement or was not in attendance at the preconstruction conference, has he been briefed on fire prevention and safety requirements prior to welding or cutting?
YES