RFI_Questions_and_Answers_Bldg_180__2.docx
DOCX document 14 KB Posted
- Attached to
- Construct Addition to Corrosion Control Facility Bldg 180 Federal contract opportunity
- Solicitation number
- F3QCCL6062A003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_1_of_2.pdf | ||
| Revised_17_Jun_2016_-_Specifications_130401_-_Volume_2_of_2.pdf | ||
| FA8501-16-R-0013-0003.pdf | ||
| Amendment_2_130401.pdf | ||
| RFI_Questions_and_Answers_Bldg_180_.docx | DOCX document | |
| Amendment_for_Bldg_180.pdf | ||
| RFI_Questions_and_Answers_for_Bldg_180__3.docx | DOCX document | |
| UHHZ130401_Contractors_Site_Visit_Attendees.pdf | ||
| RFI's_and_Answers_for_Bldg_180.docx | DOCX document | |
| Master_Utility_Outage.pdf | ||
| Specifications_Vol._1_of_2.pdf | ||
| Specifications_Vol._2_of_2.pdf | ||
| Form_2519_-_Welding_ _Safety_Checklist.doc | DOC document | |
| Special_Warranty_Requirements.doc | DOC document | |
| App_C_UHHZ_130401.pdf | ||
| 11-Mar-2016_Wage_Determination.pdf | ||
| Govt._Project_Time_Estimate_Sheet.xlsx | XLSX spreadsheet | |
| FA8501-16-R-0013.pdf | ||
| Half_Size_Drawings.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Questions and Answers
Question 1:
1. E-303 drawing show 3 rooms on the Mezzanine, Do they require Notification devices in these rooms? Rooms 201, 202, 203
2. Do the Temp Trailers discussed at the site visit require a Fire Alarm System in them?
3. Is a remote annunciator required by the LOC at the front entrance?
4. E-304 drawing shows only 1 flow and tamper switch; there are 2 other wet sprinkler riser in this room. Does the other riser need to be monitored?
5. Does the Steam Cleaning Room 118 require explosion proof fittings or do the devices need to be weatherproof?
6. Do the paint booths need any devices inside of them? If so do they need to be explosion proof?
7. Are outside speakers required at all entrances?
8. Is a pull station required in the Mech. Room?
Answer 1: 1. E-303 drawing show 3 rooms on the Mezzanine, Do they require
Notification devices in these rooms? Rooms 201, 202, 203
GOVT RESPONSE: NO
2. Do the Temp Trailers discussed at the site visit require a Fire
Alarm System in them?
3. Is a remote annunciator required by the LOC at the front entrance?
GOVT RESONSE: YES
4. E-304 drawing shows only 1 flow and tamper switch; there are 2 other wet sprinkler riser in this room. Does the other riser need to be monitored?
GOVT RESPONSE: YES, See drawing FP001 Existing Riser Diagram.
5. Does the Steam Cleaning Room 118 require explosion proof fittings or do the devices need to be weatherproof?
GOVT RESPONSE: Request that it be weatherproof.
6. Do the paint booths need any devices inside of them? If so do they need to be explosion proof?
7. Are outside speakers required at all entrances?
8. Is a pull station required in the Mech. Room?
GOVT RESPONSE: YES (if Mech. Room is Rm#114).
Question 2
1. Please provide a copy of the prior asbestos and lead paint survey
GOVT RESPONSE: See Appendix B titled "HAZARDOUS MATERIALS REPORT" at the back of specification volume 2 of 2. There are no other previous reports on record.
2. Please provide asbuilt drawings for all previous construction work.
GOVT RESPONSE: CE has record PDF drawings for original B180. They are posted under "0. Initial Documents", in two folders (B180 As-Built Drawings, and B180 Old Drawings) on CE's "Z" drive and project folder. It is the Contracting Officer's discretion as whether to provide these drawings to the bidders or not.
3. Will all of the area to be demolished be made available to the GC upon NTP?
GOVT RESPONSE: CE is waiting for answer from CMXG organization. Will provide a final response soon.
4. Regarding the antennae on the north face of the building. Provide clarification as to whether service needs to be maintained during construction.
GOVT RESPONSE: CE is waiting for answer from CMXG organization. Will provide a final response soon.
5. Plans call for GWB ceilings in the shower areas. Would the government entertain other materials more appropriate for that environment.
GOVT RESPONSE: Moisture resistant gypsum board should be used in areas subject to moisture or dampness.
6. Several of our major mechanical and electrical subcontractors have requested that the bid date be extended at least 1-2 weeks.
GOVT RESPONSE: It is the Contracting Officer's discretion as whether to extend the bid due date or not.
Question 3.
On previous renovation projects at RAFB when there is an existing Federal
Signal "Big Voice" panel currently in use is has been acceptable to modify and reuse it instead of the additional expense to replace it. Will this be allowed for this project?
GOVT RESPONSE: It really depend on the existing Federal Signal “Big Voice” unit. There are some that could be modified/reuse, and there are some that could not be modify and require purchasing /installing a new unit.
Question 4.
Can any additional site visits be taken by subcontractors?
Answer: The government does not intend to have another site visit.
Question 5.
Half size drawings were issued on FBO. Can a full-size set of drawings be issued to help ensure accuracy of take-off estimates?
Answer:
I have just one "Office Copy" of full size drawings provided by the AE.
Half size drawings should be sufficient, though a strain on the eyes. Any contractors' estimator who cares to come by my office, may sit down with this copy to make his takeoff. AutoCAD drawings of specific sheet(s) can be made available as well, although we don't normally provide these to bidders.