Sol_F17PS00539_Amd_000006.pdf
PDF 105 KB Posted
- Attached to
- Construct an Equipment/Storage Building at Hagerman NFH - Hagerman, ID Federal contract opportunity
- Solicitation number
- F17PS00539
About this file
F17PS00539
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_F17PS00539_Amd_000008.pdf | ||
| B09_F17PS00539-000008.pdf | ||
| Sol_F17PS00539_Amd_000007.pdf | ||
| B09_Amendment_000006_Q&A.docx | DOCX document | |
| Sol_F17PS00539_Amd_000005.pdf | ||
| A06_Report_(Asbestos_Survey_of_'The_Barn').pdf | ||
| A06_Report_(Lead_and_PCBs_Paint_Survey_of_'The_Barn').pdf | ||
| Sol_F17PS00539_Amd_000004.pdf | ||
| A06_Report_(Asbestos_Survey_of_former_Admin_Building).pdf | ||
| A06_Report_(Lead_and_PCBs_Paint_Survey_of_the_former_Admin_Building).pdf | ||
| Sol_F17PS00539_Amd_000003.pdf | ||
| Sol_F17PS00539_Amd_000002.pdf | ||
| Sol_F17PS00539_Amd_000001.pdf | ||
| A06_Specifications.pdf | ||
| A06_Drawings.pdf | ||
| Sol_F17PS00539.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
F17PS00539
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
F01
PORTLAND OR 97232-4181
911 NE 11TH AVENUE
EASTSIDE FEDERAL COMPLEX
FWS, DIVISION OF CONTRACTING AND GE
F01
PORTLAND OR 97232-4181
911 NE 11TH AVENUE
EASTSIDE FEDERAL COMPLEX
FWS, DIVISION OF CONTRACTING AND GE
07/26/2017000006
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/26/2017
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Purpose of this amendment is to revise Paragraph L.2 and provide answers to questions form prospective bidders. As a result of this amendment, the bid due date / time is extended from July 27, 2017 at 2:00 PM (PDT) to August 03, 2017 at 2:00 PM (PDT).
POC for this action is Michael Stearns at 503-736-4469.
Legacy Doc #: FWS
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Michael Stearns
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation No. F17PS00539 Construct Equipment/Storage Building
United States Fish and Wildlife Service
Hagerman National Fish Hatchery (NFH) – Hagerman, ID
Amendment 000006 July 26, 2017
Amendment 000006 is being issued to modify the solicitation as stated below. Bidders are responsible for having read and considered these modification in preparation of their bids.
01) Section L, Paragraph L.2, Subparagraph c.iii.1. – Change ‘Wendy Duval’ to ‘Michael Stearns.’
Solicitation No. F17PS00539 Construct Equipment/Storage Building
United States Fish and Wildlife Service
Hagerman National Fish Hatchery (NFH) – Hagerman, ID
Amendment 000006 July 26, 2017
The following are answers to questions submitted by prospective offerors. Offerors shall consider the answers in preparation of their bid.
Question 01: Refer to Specification Sections 03 30 00 and 13 44 00 and Drawing Sheets S-001 thru S-004 – Please note that this question was the second, duplicated Question 21 as part of Amendment 000004. The answer provided under Amendment 000004 was not applicable; therefore, the answer is provided as part of this amendment.
The concrete design does not appear to be adequate for the building uplift and the curb on top of the slab is inefficient. Can alternate, engineered designs be proposed that meet the apparent design criteria?
Answer 01: The curb is not a structural component of the concrete slab; it is intended to assist in rodent control and water intrusion.
The footings are currently sized for a building that has not been fully-designed and are based on preliminary calculations. Once the building submittal from the selected contractor has been approved through the submittal approval process, the foundation design will be revisited to determine if modifications are needed. As required by Specification Section 13 34 19, the final foundation load calculations are required from the actual building manufacturer in order to verify the footing sizes and provide a final design and footing size.
Question 02: No reference indicated
What is the R-value in Bay 7 for the walls and the ceiling?
Answer 02: Refer to Drawing Sheet G-001, Energy Code Summary in sheet notes.
Question 03: No reference indicated
Are you requiring the ridge vent to be continuous or can each bay have a 10’ vent?
Answer 03: Ridge vent shall be continuous over Bays 1 thru 6 only. Bay 7 should not have a ridge vent, as the Heat Recovery Unit will provide ventilation of that bay only.
Question 04: No reference indicated
What is the weight and required location of the Heat Recovery unit?
Answer 04: Approximate total unit weight is 844 lbs. Unit shall be located in Bay 7, suspended from the building framing. Drawing Sheet G-001 and Section 3or Drawing Sheet G-002 show the Heat Recovery Unit just west of grid line 2, with the roof intake hood for the unit visible above the roof. The unit’s exact location within Bay 7 shall be selected by the contractor based upon convenient support points.
Question 05: Refer to Specification Section 13 34 19, Paragraph 1.9.A.
Specification section calls for a 5-year manufacturer’s warranty for system and components. None of the MBMA Manufacturers that responded offer such a blanket warranty. What is the intent of this article?
Answer 05: Provide a warranty against rust, corrosion, and weathertightness.
Question 06: Refer to Specification Section 13 34 19, Paragraphs 1.9.B. and 2.3.A.
Specification section calls for a 5-year warranty for … coverage for rust and corrosion and weather tightness of the building. Paragraph 2.3.A. calls out for a screw down roof based on the purlin spacing and rib height. There is not a screw down that provides an extended coverage for weather tightness according to the responses received. Only a standing seam roof provides this weather tightness coverage and it has coverage of only 24” vs. the specified minimum 36”. What is the intent of the design, to have an extended leak warranty for the roof or to meet the letter of the specification?
Answer 06: Provide the extended leak warranty with a standing seam roof.
Question 07: Refer to Specification Section 13 34 19, Paragraphs 2.3.A. and 2.6.B.
Specification section Paragraph 2.3.A. states the building is to be Energy Star Compliant. Per Paragraph 2.3.A., the specified screw down roof will not come close to meeting the energy code requirements, only a standing seem roof has the ability to meet the thermal transfer values in application. What is the intent of the design, to meet the energy code for the finished bays or to have the most cost-effective building?
Answer 07: Provide a standing seam roof.
Question 08: Refer to Specification Section 13 34 19, Paragraph 2.6.H.
Specification calls for continuous ridge type ventilator. How many 10’ sections are required?
Answer 08: Nine (9), 10-foot sections will cover Bays 1 thru 6.
Question 09: No reference indicated
Are continuous ridge type ventilator required for Bays 6 and 7?
Answer 09: Continuous ridge type ventilator is only required for Bay 6.
Question 10: No reference indicated
Are the alternate Bays 1-5 overhead door openings to be priced with removable girts or as a framed opening to be added in the future?
Answer 10: Door openings shall be priced as framed openings.
Question 11: No reference indicated
The specifications call for the project to meet Idaho Energy Code. As shown in the drawings and specifications, the building does not meet these requirements. Is this building to be built to Idaho Energy Code?
Answer 11: No. The building does not need to meet the Idaho Energy Code.
Question 12: No reference indicated
The specification for Bay 7 call R5 thermal blocks above continuous roll insulation on purlins beneath roofing. Can you confirm this is correct?
Answer 12: That is correct.
Question 13: Refer to Drawing Sheet S-003
The plans call for 8” Metal Stud Framing to be provided by the PEMB Manufacturer. Our manufacturer will not supply these. Can these be supplied by others?
Answer 13: Other subcontractors may supply metal stud framing. They need to provide all the same design, submittal, and installation capabilities as would have been provided by sourcing with the PEMB package. All parts of the stud wall including sizes, bracing, and connections need to be designed. The subcontractor shall provide design through their own resources.
Question 14: Refer to Drawing Sheets S-003 and S-004
Can you verify the width of the Metal Stud Framing? Drawing Sheet S-003 calls for 8” and the detail on Drawing Sheet S-004 calls for 7-1/2”. Which is correct?
Answer 14: Curb width shall match the stud width (i.e. 8 inches).
Question 15: No reference indicated
Our PEMP Manufacturer will only give a 5-year weathertight warranty for the standing seam metal roofs. Will a standing seam roof be allowed?
Answer 15: A standing seam roof is acceptable.
Question 16: No reference indicated
Does the Government have a list of General Contractors bidding?
Answer 16: No. The only information hinting or anyone interested in submitting a bid can be found on the redacted, site visit sign-in sheet which can be found under Amendment 000003.