Exhibit_D_-_Trench_Safety_Act.pdf
PDF 555 KB Posted
- Attached to
- Wastewater Pump Station R & R
- Solicitation number
- CC-7100-26/HSM (A)
- Issued by
- Seminole County, Florida
About this file
This document is Exhibit D of the Trench Safety Act compliance requirement for a Wastewater Pump Station Repair and Refurbishment project issued by the Seminole County Board of County Commissioners in Florida. The exhibit establishes mandatory compliance procedures for bidders undertaking trench work on utility facility projects. Bidders are required to specify all costs associated with Trench Safety Act compliance as part of their overall bid submissions, though these costs are not itemized as separate line items. Bidders must reference applicable Trench Safety Standards that will govern construction activities and provide written assurance of compliance with all relevant safety requirements during project execution.
The pricing structure requires bidders to incorporate trench safety costs into their total project pricing without segregating them as distinct pay items. Bidders must complete a trench safety summary table identifying units of quantity, unit measures, and extended costs, then sign and date the exhibit as certification of their understanding and commitment to compliance. This exhibit applies only to projects involving trench work and is mandatory under Florida Statutes Sections 553.60-553.64 for any contractor performing excavation or trenching activities on the wastewater pump station projects.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
00110 – Trench Safety Act (Rev 082020)
TRENCH SAFETY ACT (if applicable for this project)
SECTIONS 553.60-553.64, FLORIDA STATUTES
NOTICE TO BIDDERS:
In order to comply with the Trench Safety Act, the Bidder is required to specify the costs of compliance. These costs are not a separate pay item. The Bidder must also reference the Trench Safety Standards which will be in effect during construction, and assure in writing that the Bidder will comply with the applicable Trench Safety Standards.
TRENCH SAFETY UNITS OF QUANTITY UNIT EXTENDED
MEASURE MEASURE COST COST
TOTAL $__________
Representative Name Bidder Name
Representative Signature Date
EXHIBIT D
File details come from the government source that posted it. Updated .