ECEP Cooling Tower Basin Improvements - Contract Specifications Summary

This is an Exhibit B specifications document for Solicitation No. ITB-C007159, titled "ECEP Cooling Tower Basin Improvements," issued by the Central Florida Tourism Oversight District (CFTOD) on September 18, 2026. The project encompasses mechanical and electrical improvements to the EPCOT Energy Plant (EEP) cooling tower system, including installation of sluice gates at three basin openings, a 24-inch chilled water return bypass pipe with butterfly valves, replacement of pneumatic actuators with electric actuators on cooling tower inlet valves for towers 1-3, replacement of tower 4 inlet components, installation of isolation butterfly valves in the main condenser water header, solenoid valves for chemical treatment discharge, and associated control modifications. The project requires a minimum dedicated staff including a part-time project manager, full-time general superintendent, and part-time field project engineer. Normal work hours are 7:00 AM to 4:00 PM Monday through Friday, with work requiring lane closures potentially scheduled between 11:00 PM and 7:00 AM Sunday through Thursday. The contractor must apply for dewatering permits during pre-construction, comply with FDOT traffic control standards, maintain traffic control plans, and coordinate extensively with the owner's representative and separate contractors.

The contractor bears responsibility for all permitting costs, traffic control device maintenance, utility coordination, site cleanliness, and material disposal, with violators subject to daily penalties of $500 for unauthorized haul routes. A Schedule of Values must be submitted before payment approval, incorporating cost codes and funding source splits provided by CFTOD. The contractor must maintain comprehensive project records, submit critical path method schedules within 28 days of notice to proceed, and comply with contract milestones and milestone definitions. All work must meet local, state, and federal codes, including the EPCOT Building Code, with the contractor assuming all additional costs related to accepted substitutions and coordination with owner-furnished items. The contract requires web-based document processing through CFTOD's centralized file sharing system for all project submissions, including submittals, RFIs, field reports, and pay applications.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT B

LIST OF DRAWINGS &

REVISION STATUS

SOLICITATION NO.:

ITB-C007159

SOLICITATION TITLE: ECEP Cooling Tower Basin Improvements

DOCUMENT TITLE:

LIST OF DRAWINGS & REVISION STATUS

IMPORTANT NOTICE

This Exhibit is incorporated into and made part of the solicitation documents. Bidders/Proposers shall review all information and shall consider the requirements of this Exhibit when preparing and submitting their response.

12424 Research Parkway, Suite 200

Orlando, FL 32826

FL CA #29588

www.mckimcreed.com

EPCOT ENERGY PLANT (EEP)

COOLING TOWER BASIN IMPROVEMENTS

PROJECT MANUAL

Issued For Bid Documents

September 18, 2026

CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT

FILE NAME – 00 00 00 TITLE PAGE

C006553 EPCOT ENERGY PLANT (EEP) COOLING TOWER BASIN

IMPROVEMENTS

ISSUED FOR BID – 09/18/2026

SECTION 00 00 00

TITLE PAGE

SECTION 00 00 00

TITLE PAGE

C006553

EPCOT ENERGY PLANT (EEP)

COOLING TOWER BASIN IMPROVEMENTS

MECHANICAL / ELECTRICAL ENGINEERING CONSULTANT (PRIME)

McKim & Creed, Inc.

12424 Research Parkway, Suite 200

Orlando, FL 32826

FL CA #29588

Project Manager & Senior Mechanical Engineer: Michael R. Hartley, PE, CxA, EMP mhartley@mckimcreed.com

(407) 496-2082

FILE NAME – 00 88 50.00 LIST OF DRAWINGS AND SPECIFICATIONS

ISSUED FOR BID 09/18/2026

SECTION 00 88 50.00

LIST OF DRAWINGS AND SPECIFICATIONS

The following list of Drawing and Specifications, all prepared as noted, shall form a part of the Project Manual.

Project Manual

Entitled: EPCOT Energy Plant (EEP) Cooling Tower Basin Improvements

Dated: 08/28/2026

DRAWINGS

The following list of Drawings/materials are applicable to the foregoing

LIST OF DRAWINGS / MATERIALS:

DRAWING

NO.

DRAWING TITLE ISSUE

DATE

EOR

COVER MAP & GENERAL NOTES

V100 COVER & PROJECT LOCATION 09/18/2026 MICHAEL R. HARTLEY

V101 LIST OF DRAWINGS AND REVISION STATUS 09/18/2026 MICHAEL R. HARTLEY

MECHANICAL

M001 MECHANICAL NOTES, LEGENDS AND ABBREVIATIONS 09/18/2026 MICHAEL R. HARTLEY

M101 CHILLER BUILDING PARTIAL MECHANICAL PLAN 09/18/2026 MICHAEL R. HARTLEY

M301 CHILLER BUILDING MECHANICAL SECTIONS 09/18/2026 MICHAEL R. HARTLEY

M401 MECHANICAL SPECIFICATIONS 09/18/2026 MICHAEL R. HARTLEY

M402 MECHANICAL CONTROL DIAGRAMS AND DETAILS 09/18/2026 MICHAEL R. HARTLEY

M601 CHILLER BUILDING MECHANICAL PIPING SCHEMATIC 09/18/2026 MICHAEL R. HARTLEY

ELECTRICAL

E001 ELECTRICAL NOTES, LEGENDS AND ABBREVIATIONS 09/18/2026 DAN COX

E101 ELECTRICAL FLOOR PLAN 09/18/2026 DAN COX

E102 ELECTRICAL ROOM ENLARGED PLAN, PARTIAL RISER

DIAGRAM, & PANEL SCHEDULE

09/18/2026 DAN COX

STRUCTURAL

S001 STRUCTURAL GENERAL NOTES, PARTIAL PLANS &

SECTIONS

09/18/2026 NATHAN E. MARROW

S101 PARTIAL PLAN AND DETAILS 09/18/2026 NATHAN E. MARROW

SPECIFICATIONS

The following list of Specifications is applicable to the foregoing. Any Supplemental Specifications that only pertain to this specific Project and are not part of the Owner’s Standards Specifications will have an

(S) designation following the section title in the table below.

LIST OF SPECIFICATIONS

DIVISION 01 – GENERAL REQUIREMENTS

01 10 00.00 SUMMARY OF WORK

01 14 00.00 COORDINATION WITH OWNER’S OPERATIONS

01 25 00.00 PRODUCT SUBSTITUTIONS

01 29 73.00 SCHEDULE OF VALUES

01 31 13.00 PROJECT COORDINATION

01 31 13.10.00 CONTRACT TIME, SEQUENCING, AND TIMING OF WORK

01 31 19.00 PROGRESS MEETINGS

01 31 26.00 ELECTRONIC DOCUMENT PROCESSING SERVICE

01 32 13.00 SCHEDULE OF WORK

01 32 16.00 CONSTRUCTION SCHEDULE

01 33 00.00 SUBMITTAL PROCEDURES

01 33 23.00 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01 35 23.00 CFTOD PROJECT SPECIFIC SAFETY PLAN REQUIREMENTS

01 41 00.00 REGULATORY REQUIREMENTS

01 42 00.00 REFERENCES

01 44 00.00 QUALITY ASSURANCE AND QUALITY CONTROL

01 45 23.00 TESTING AND INSPECTION SERVICES

01 50 00.00 TEMPORARY CONSTRUCTION FACILITIES

01 61 00.00 PRODUCT REQUIREMENTS AND OPTION

01 64 00.00 OWNER FURNISHED PRODUCTS

01 66 00.00 PRODUCT HANDLING AND PROTECTION

01 70 00.00 PROJECT CLOSEOUT

01 73 00.00 EXECUTION

01 73 29.00 CUTTING AND PATCHING

01 74 00.00 CLEANING

01 75 00.00 STARTING AND ADJUSTING

01 78 23.00 OPERATION AND MAINTENANCE DATA

01 78 43.00 SPARE PARTS AND EXTRA MATERIAL

01 79 00.00 DEMONSTRATION AND TESTING

01 91 13.00 GENERAL COMMISSIONING REQUIREMENTS

DIVISIONS 02 THROUGH 22 (NOT USED)

DIVISION 23 – MECHANICAL

23 00 10 COMMON MECHANICAL REQUIREMENTS

23 05 10 BASIC MATERIALS AND METHODS FOR HVAC SYSTEMS

23 05 23.03 VALVES

23 05 29.03 HANGERS AND SUPPORTS

23 09 00.03 INSTRUMENTATION

23 21 13.03 PIPING

23 21 14.03 PIPING SPECIALTIES

DIVISIONS 24 THROUGH 25 (NOT USED)

DIVISION 26 – ELECTRICAL

26 00 01 ELECTRICAL GENERAL PROVISIONS

26 01 26.09 ELECTRICAL TESTING

26 05 19.09 CONDUCTORS AND CABLE

26 05 29.09 HANGERS AND SUPPORTS

26 05 33.09 RACEWAY AND BOXES

26 05 53.09 ELECTRICAL IDENTIFICATION

26 05 83.09 WIRING CONNECTIONS

26 20 00.09 LOW-VOLTAGE ELECTRICAL DISTRIBUTION

DIVISIONS 27 THROUGH 33 (NOT USED)

END OF SECTION

Division 01 General Requirements

FILE NAME – 01 11 00.00 SUMMARY OF WORK

SECTION 01 11 00.00

SUMMARY OF WORK

PART 1 – WORK COVERED BY CONTRACT DOCUMENTS

1.01 GENERAL

A. The Scope of Work for the EPCOT ENERGY PLANT (EEP) COOLING TOWER BASIN IMPROVEMENTS is described by the Project Manual entitled EPCOT ENERGY PLANT (EEP) COOLING TOWER BASIN IMPROVEMENTS. Specific elements of the Scope of Work are generally summarized below but this Summary of the Work is not intended to be complete descriptions of the Work. Any quantities or measurements, if included in the summaries, are approximate and are not to be used in estimating the Work.

B. It is the intent of the Owner that the Contractor will perform all of the Work of any kind and nature shown on the Drawings and/or described in the Specifications or other Contract Documents, which is within the Contractor's Scope of Work, unless specifically excluded or indicated as Owner-furnished and/or installed. Any Work not specifically indicated on the Drawings and/or described in the Specifications or other Contract Documents, but is required to fulfill the intent of a "complete job" for the Contractor's Scope of Work, will be considered included in the Contract. Work must meet all requirements of the local, state and federal codes and standards.

1.02 GENERAL SUMMARY

A. The Scope of Work for the EPCOT ENERGY PLANT (EEP) COOLING TOWER BASIN IMPROVEMENTS includes, but is not limited to, the following:

1. Provide sluice gates at (3) existing basin openings between cooling tower cells 3 and 4.

2. Provide a 24" CWR bypass pipe between the north side header to the south side header.

Provide butterfly valves at the connection to the existing north header and at the connection to the existing south header.

3. Replace the pneumatic actuators with electric actuators on the existing cooling tower inlet valves for cooling towers 1, 2, and 3.

4. Replace the butterfly valve and pneumatic actuator with an electric actuator at the tower inlet for cooling tower 4.

5. Provide isolation butterfly valves in the main condenser water header between the takeoffs for CT-1 and CT-2, between the takeoffs for CT-2 and CT-3 and between the takeoffs for CT-3 and CT-4.

6. Provide solenoid valves at the chemical treatment discharge pipes for each cooling tower basin.

7. Provide control modifications for operation of the sluice gates, tower isolation valves, header isolation valves and chemical treatment discharge valves.

1.03 DETAILED SCOPE OF WORK

A. Mobilization and General Conditions:

1. The Contractor shall provide a minimum dedicated staff for the duration of the Contract Time including but not limited to the following staff positions:

a. Part time dedicated project manager.

b. Full time dedicated general superintendent.

c. Part time field project engineer.

B. Permitting:

1. The Contractor shall apply for a dewatering permit during the pre-construction phase. The

Contractor shall prepare and submit the Notice of Intent (NOI) to the Central Florida Tourism Oversight District (CFTOD) prior to submitting it to the Florida Department of Environmental Protection (FDEP) during the pre-construction phase. In addition, the Contractor shall apply for any and all permits that are required by CFTOD Building and Safety during the pre-construction period.

2. Work must meet all requirements of the local, state and federal codes and standards as well as the most recent version of the EPCOT Building Code with the most current supplement thereof in effect at the time of the effective Contract date.

3. The Contractor shall obtain and provide all required permits.

C. Maintenance of Traffic (MOT)/Temporary Traffic Control (TTC):

1. The Contractor shall follow the Traffic Control Plans (TCPs) if provided for the Project.

Contractor is required to adhere to Florida Department of Transportation (FDOT) Standard Plans (Standard Design Index) 102-600 series and associated indexes for items not detailed in the TCPs. Contractor is required to submit for approval proposed MOT details when certain activities (i.e., structure component deliveries, excavations adjacent to traffic, overhead installations, etc.) require detailed operations to control traffic flow. The Contractor shall conduct their work to interfere as little as possible with public travel, whether vehicular or pedestrian. Whenever it is necessary to cross, obstruct, or close roads, driveways, and walks, whether public or private, the Contractor shall, at their own expense, provide and maintain suitable and safe bridges, detours, or other temporary expedients for the accommodation of public and private travel, and shall give reasonable notice to Owners of driveways before interfering with them. Such maintenance of traffic will not be required when the Contractor has obtained permission from the Owner and tenant of the property, or from the authority having jurisdiction over the property involved, to obstruct traffic at the designated point. The Contractor shall include all such activities within their bid and expect to attend regular MOT Coordination meetings to discuss proposed operations. Should the Contractor request to deviate from the TCPs or request an alternate/additional detour or subphase, the Contractor shall hire a professional engineer licensed to do business in the State of Florida to provide signed and sealed MOT individual plans prior to applying for the required permits from CFTOD Planning & Engineering. The MOT plans shall be in compliance with the Manual for Uniform Traffic Control Devices and applicable FDOT Standards. The Contractor shall maintain their traffic control devices for the entire duration of the Project until the Owner or Owner’s Representative certifies that the Punch List is complete.

2. The Contractor shall provide a FDOT MOT certified traffic control crew to provide continuous maintenance of all traffic control systems at its expense, whenever traffic conditions warrant such control and whenever directed to provide such maintenance or adjustments by the Owner or Owner’s Representative. This requirement shall also apply to all events requiring a vehicle to back up on a lane maintained for traffic or any other situation considered by the Owner or Owner’s Representative to be dangerous.

3. The Contractor shall provide a qualified traffic control crew at its expense to inspect all traffic control systems in the presence of the Owner or Owner’s Representative at the beginning and end of each work shift for a minimum of one hour after the start of the shift and a minimum of one hour before the end of the shift. The Contractor’s crew shall make immediate corrections or adjustments to the MOT systems as required to conform them to the approved MOT plans or as directed by the Owner or Owner’s Representative.

4. All MOT devices shall be like-new. They shall be freshly painted and free of scratches, dents, dirt, and debris, and stains. The Contractor shall replace any MOT device that becomes damaged with a new device.

5. The Contractor shall construct and remove all temporary pavement as indicated within the Drawings or otherwise deemed as necessary by the Owner’s Representative.

6. The Contractor shall provide an MOT plan that has been signed and sealed by a Professional Engineer licensed in the State of Florida. Plans will be reviewed and approved by Owner, Owner’s Representative, and affected Stakeholders.

D. Lay Down Yard/Employee Parking Construction:

1. The designated lay down yard and employee parking area is anticipated to be in the vicinity of the Job Site. The Contractor shall contain all trade parking, inclusive of the Contractor itself, to designated Contractor parking areas. Staging and construction laydown area is very limited within Job Site limits. A designated lay down yard and employee privately operated vehicle (POV) parking area is anticipated to be located at a nearby location yet to be determined.

Contractor is responsible for maintaining cleanliness of their assigned/approved area(s). No POV shall be parked within Job Site limits.

2. Contractor employees shall be transported from assigned parking areas to the Job Site by means provided by Contractor.

E. (deleted)

F. (deleted)

G. (deleted)

H. (deleted)

I. Utilities:

1. The Contractor is to coordinate all utility construction efforts with the Owner’s Representative.

Owner’s Representative requires coordination for inspections of Owner’s new and existing utilities. Owner’s Representative will also require 72-hour notice and planning when working around existing utilities. Other utility Owners may include, but are not limited to, Walt Disney World (WDW) owned utilities, Smart City Telecom (data and communications fiber optic and wire), CFTOD (traffic fiber optic), WDW Telecom (Disney fiber optic), Spectrum, Duke, Summit Broadband, TECO, & AT&T.

2. The Contractor shall identify and protect all existing utilities within the limits of the Work.

3. Except as otherwise explicitly indicated on Drawings or called for in the Specifications, do not cut, alter, remove or otherwise disturb any existing improvement or construction or disturb any existing utilities without the approval of the Owner’s Representative.

4. The Contractor shall immediately restore to service and repair any damage caused by it to any existing utilities which are not scheduled for removal, discontinuance or abandonment, or which have not been released by the Owner and jurisdictional agencies for removal, discontinuance or abandonment, even if so scheduled.

5. Temporary Supports for existing utilities: The Contractor shall provide all necessary temporary supports required to protect any and all existing utilities prior to commencing Work. Any damage to existing in-service utilities during construction will be repaired at the Contractor’s expense. Temporary supports shall be reviewed by Owner’s Representative or the appropriate utility company prior to installation by the Contractor.

6. The Contractor shall strictly adhere to utility notice and excavation permit provisions specified below in subsection NOTIFICATION TO UTILITY COMPANIES AND EXCAVATION PERMIT.

The Owner’s Representative Utility Locate Office will locate primary utility services. It will not locate secondary services. Secondary services include roadway lighting systems, irrigation systems, and electrical power systems for the existing lift station. All such services shall be maintained and/or relocated without interruption to existing services. The Contractor shall hire a private utility locate service to identify and locate all secondary utilities within the limits of the Work

7. Locating services provided by the Owner’s Representative Utility Locate Office, Sunshine 811 and by any private secondary locating technician are confined to surface markings and flagging only. The Contractor shall hand dig and/or soft dig as required to determine the depths of all utilities. All such hand digging and soft digging shall be included in the Contract amount.

a. Hand dig is defined as any excavation using hand shovels to break up soil or earth for removal.

1) Shovels must be made with non-conductive handles to protect the operator from the potential for electrical shocks resulting from contact with energized lines.

b. Soft Dig is defined as any excavation using tools or equipment that utilize air or water pressure as the direct means to break up soil or earth for removal by vacuum excavation

8. Any temporary or permanent utility (potable water, reclaimed water, sanitary water, gas, chilled water, etc.) connections to existing facilities will require advanced coordination between Contractor, Owner, Owner’s Representative, and affected Stakeholders in all cases.

9. The Contractor is strictly prohibited from adjusting, closing, or opening any mechanical valves on Owner’s or other utility systems. Utilization/adjustment of valves for any reason requires advanced coordination between Contractor, Owner, utility Owner, and Owner’s Representative in all cases. The utility Owner(s) must be present to supervise/perform any and all valve operations.

J. Construction:

1. The Contractor shall construct all areas as shown on the Drawings.

K. (deleted)

L. (deleted)

M. (deleted)

N. (deleted)

O. (deleted)

P. Sod:

1. Contractor shall replace all sod, with like kind, if damaged by its operations.

Q. (deleted)

PART 2 – GENERAL INSTRUCTIONS & STANDARDS FOR THE CONSTRUCTION WORK

2.01 GENERAL REQUIREMENTS

A. The Contractor shall provide all services and necessary items of expense, including but not limited to, labor, material, trucking, transportation, equipment, hoisting, scaffolding, power, supervision, appliances, layout and all other services and items of expense required for the complete performance of all Work in accordance with the Contract Documents.

B. Schedule

1. The Contractor shall submit their overall and monthly progress Critical Path Method (CPM) schedule submittals to the Owner’s Representative.

C. Proposed Staffing Plan

1. Contractor shall submit with its Bid Proposal a staffing plan which clearly illustrates the key elements of the organizational structure proposed to accomplish the management, field work, and administrative services required. The Contractor shall identify the key person to be placed in responsible charge of the Work. The Project Manager and key personnel within each discipline shall be identified and past experience of each, as it relates to this Project, shall be discussed. Other items to be included in the discussion of the staffing plan are:

a. Work force capabilities of the firm.

b. Work force commitment for the Project.

c. Key staff resumes.

d. Note: The Contractor is required to have a certified inspector onsite for SWPPP and MOT at all times.

2.02 JOB SITE ACCESS / USE OF JOB SITE

A. Access to the Job Site shall come from Owner’s Representative. A haul route will have to be provided by the Contractor for CFTOD Planning and Engineering review and approval. The Contractor shall utilize lined trucks to haul muck or saturated soils off site (if required) and shall utilize only those hauling routes prescribed or approved by the Owner for hauling to and from the site. For each and every occurrence that the Contractor or its Subcontractor(s) utilizes a haul route that is not prescribed by, or otherwise expressly approved by, the Owner, the Owner shall deduct from the Contract Sum, the sum of $500.00 a day.

B. Vehicular traffic to the Job Site is limited to vehicles required to deliver labor and materials. On-site parking for vehicles shall be limited to those areas designated by the Owner’s Representative and shall be limited to company work vehicles actively working on site. Vehicles not actively supporting Job Site operations are not permitted to remain on site. The designated lay down yard and employee parking area is anticipated to be in the vicinity of the Job Site. When it is designated, the Contractor shall create an engineered plan for review by the Owner that demonstrates how it will safely access the Job Site and storage areas and how it will egress from the Job Site and storage area.

C. The Contractor is responsible for the routing of all construction personnel and traffic required in the performance of the Work and shall ensure compliance with any special instructions pertaining to such routing as established by the Owner.

D. Lunch and break areas are confined to the immediate Job Site area, within the limits of construction.

Tradesmen shall be prohibited from patronizing the restaurants in the adjacent development.

E. The Contractor shall confine its use of the Job Site to those activities directly relating to the performance of the Work. No other use of the Job Site will be permitted without the express written approval of the Owner or Owner’s Representative.

F. The Contractor shall provide all necessary flagmen, barricades, and MOT devices necessary for safe and proper traffic control. The Contractor is advised that it is responsible for all construction personnel and traffic routing logistics required in the performance of its Work.

G. The Contractor shall provide all necessary temporary water retention basins, turbidity control, and silt fence, etc., for construction site water run-off control. The Contractor is advised that should any of the adjoining ponds, lakes, wetlands, or canals become contaminated due to the Contractor’s actions or inactions, the cost to flocculate, clean, or restore by any other means, these ponds, lakes, wetlands, or canals shall be paid for by the Contractor. Any fines and / or penalties assessed for contamination of these water bodies, due to the Contractor’s actions or inactions, shall be paid for by the Contractor.

2.03 COORDINATION

A. The Contractor shall coordinate with the Owner’s Representative to allow for all materials testing.

B. The Contractor shall coordinate its Work with the Owner’s Representative and with the Owner’s Separate Contractors. The Contractor shall sequence its Work, as required by the Owner’s Representative, with the work of the Owner’s Separate Contractors at no additional cost to the Owner.

C. Contractor is required to coordinate its efforts with the Owner’s Representative for service connections for on-going development adjacent to this Project, at no additional cost to the Owner.

D. The Contractor is required to coordinate with the delivery of any and all Owner Furnish, Owner or Contractor installed items.

E. The Contractor shall coordinate with the Owner’s Representative for site access/control for the District Fire Department.

F. The Owner, or appointed delegate, reserves the right to access any part of the Job Site, at any time, for the purpose of observation, or to install other work, either with its own forces of with other Contractors.

2.04 WORKER CONDUCT AND CLOTHING

A. The Contractor is responsible at all times for the proper conduct of its personnel and that of its Subcontractors and suppliers. The Contractor shall restrict its personnel to the Job Site and immediate vicinity thereof and shall endeavor to prevent discordant relationships between its personnel and that of any adjacent property Owner or resident.

B. The Contractor shall enforce strict discipline and good order among employees and other workers related to the performance of the Work. Under no circumstances will behavior offensive to building occupants or the general public be tolerated, and Contractor shall immediately remove and further ban from the Job Site any persons failing to comply with this standard.

C. The Contractor shall ensure its personnel are properly dressed with OSHA approved clothing and safety gear, including but not limited to, hard hats, work shoes, shirts and long pants, as appropriate for the performance of the Work. Shorts, sleeveless shirts (tank tops) or clothing bearing offensive marks or wording are not permitted to be worn on the Job Site. The Owner’s Representative shall solely determine whether any such clothing is or is not permissible.

2.05 (DELETED)

2.06 TESTING AND INSPECTION

A. Refer to Specification Section 01 45 23.00 – TESTING AND INSPECTION SERVICES, contained in the Project Manual, for Specifications governing soils and materials testing and inspection. The Owner or Owner’s Representative reserves the right to re-test and approve or disapprove the results of any testing and inspections.

2.07 (DELETED)

2.08 TEMPORARY FENCING

A. Geogrid Fencing and Silt Barriers:

1. When required by the Contract Documents, geogrid fencing and silt barriers shall be provided and maintained along the boundaries of all designated tree preservation and protected wetland areas. The Contractor shall not disturb the trees or vegetation within such areas unless directed otherwise by the Owner's Representative.

2. Geogrid fencing shall be provided and maintained along jurisdictional wetland buffers excluding those wetlands (if any) to be removed under this Contract. Silt barriers shall be provided and maintained along areas designated on Drawings.

3. The Contractor shall inspect all geogrid fences and silt barriers daily and shall immediately make necessary repairs to any damaged or improperly functioning geogrid fences and/or silt barriers.

2.09 PERMITS AND PERMIT FEES

A. All Permits required for any part of the Contractor’s Work (except those permits obtained directly by the Owner, as further enumerated below) shall be procured and paid for by the Contractor. This shall apply also to those permits required to be obtained by the Contractor in the name of the Owner or its Owner’s Representative for the Owner’s or Owner’s Representative’s own temporary construction office facilities, if any. The costs for the required permits (except those permits obtained directly by the Owner or the Owner’s Representative) are included in the Contract Sum. Before applying for any permit, the Contractor shall present a draft application to the Owner’s Representative for review.

B. The Contractor shall apply for a dewatering permit during the pre-construction phase. The Contractor shall prepare and submit the NOI to the Owner prior to submitting it to the FDEP during the pre-construction phase. In addition, the Contractor shall apply for any and all permits that are required by CFTOD Building and Safety during the pre-construction period.

C. The Contractor shall submit to the Owner’s Representative a copy of all permits required to be obtained by this Contractor, which are required for the performance of this Work.

2.10 JOB SITE CLEANLINESS, CONSTRUCTION OPERATIONS UPON AND AFFECTING THE USE OF

THE JOB SITE

A. Refer to Specification Section 01 74 00.00 – CLEANING, contained in the Project Manual, for Specifications governing cleaning and Job Site cleanliness.

B. The Contractor shall cause no dirt or debris to be deposited on any public or private roadways and must clean up same in an expeditious manner if such dirt or debris occurs due to this Contractor's operation. If the Contractor fails to perform, clean-up will be performed by others and all costs for same will be deducted from monies due or owing the Contractor.

C. The Contractor shall clean the tires of all vehicles as they exit the Job Site and enter onto the public roadway or private driveways. The Contractor shall provide rotary power broom equipment on site for daily sweeping as needed and as requested by the Owner’s Representative.

D. The Contractor shall use "whisperized" construction equipment. Noise levels shall be within those levels acceptable by the authorities having jurisdiction.

E. Material deliveries shall generally be made during normal working hours. Where special deliveries must be made at other times Contractor shall request approval of same. If such request is approved, the Contractor shall arrange for the proper labor force to receive and unload materials promptly.

F. The Contractor shall be responsible to consolidate and secure all equipment and materials at the Job Site. The Owner will not provide any security for material and equipment stored on site for Contractors working at the Job Site.

G. On site storage of fuel will not be permitted without prior written approval of the Owner and approval from all appropriate local, state, and federal agencies having jurisdiction.

H. Any and all damage to property resulting directly or indirectly by the Contractor's operations, or those of its Subcontractors, shall be repaired or replaced by the Contractor at no additional cost to the Owner and to the satisfaction of Owner's Representative.

I. Daily clean-up of the construction areas will be strictly enforced. Excess materials or accumulation of debris shall not encumber the site.

J. If, in the judgment of the Owner’s Representative, the construction area is deemed to be unclean and/or encumbered by the accumulation of excess materials; and, in the event the Contractor fails to correct the situation, the Owner reserves the right to take any action it deems necessary to correct the situation and shall back charge the Contractor for the full cost of the corrective action.

K. The Contractor shall provide a final clean prior to turnover.

L. All construction activities that may have any effect on any adjacent landowner’s operating systems or facilities must first have the final approval of the Owner’s Representative before they are initiated.

The activity description, schedule, time, duration, and areas affected must be submitted to the Owner or Owner’s Representative at least 72 hours in advance to obtain this approval.

M. Work activities that affect the environment of guest operations (noise, visual intrusion, safety, odor, dust and dirt, etc.) may be restricted to other than normal operating hours.

N. Cranes and draglines shall be boomed down at the end of each workday and during periods of inactivity during the workday.

O. Any maintenance to construction equipment on-site, which may be considered by the Owner’s Representative to have the potential to contaminate the existing earth, will not be permitted.

P. Maintenance and dust abatement of all areas of Work provided by the Contractor shall be performed in a manner acceptable to the Owner.

Q. The Contractor will be responsible for safely barricading open excavations that may present hazards.

R. The Contractor shall hire Mid Florida Materials to provide rubbish removal, reuse container rental/removal or other services related to the disposal of waste material from the Job Site (Tel:

407.886.5879). Contact a minimum of 24 hr. in advance of waste pick-up. No other firm, entity or agency is authorized to provide solid waste service within the District unless permitted in writing by the Owner. Such services include Class I, Class III and Construction and Demolition Debris service.

Any firm, entity or agency found to be providing such service within the District without written permission from the Owner or Owner’s Representative shall be required to remove any solid waste containers associated with this service within 48 hours of notification. Failure to do so will result in the impoundment of said containers by the Owner. Release of said impounded containers to the Owner will require payment of a storage fee of $100/container each day.

S. The Contractor shall legally dispose of all excess soils generated by the Work.

T. On-site security is the responsibility of Contractor. Ahere to the security requirements established by the Owner and adjacent landowners. Coordination and all questions with regard to security shall be directed to the Owner’s Representative.

2.11 EXISTING AND ADJACENT ROADWAYS AND UTILITIES

A. The Contractor will maintain access to roadways at all times. The Contractor shall create no open cuts or other obstacles on roadways or walkways without explicit approval of the Owner’s Representative. Authorized cuts must be bridged to permit vehicular and pedestrian traffic to continue without delay or hindrances. Any Work that must be performed which may result in delays to public traffic or re-routing of traffic must be coordinated with the Owner’s Representative.

B. Wherever possible, the Contractor shall arrange Work so there will be no service interruptions of any existing systems. Whenever service interruptions are necessary, the Contractor shall secure the advance approval of the Owner’s Representative and jurisdictional agencies as to the time and date such interruptions will be permitted. The Contractor shall return all services back into operation as soon as possible, including working on an overtime basis, if deemed necessary by the Owner’s Representative, at no additional cost to the Owner.

C. All existing conditions adjacent to the immediate Job Site that are disturbed due to Contractor’s activities must be restored by the Contractor to pre-construction conditions.

D. The Contractor shall restore all existing grade, existing sod, and existing irrigation it disturbs.

Restore all affected areas to existing conditions or better.

E. CFTOD, WDW and other Utility Owners all have existing infrastructure within the Project limits. The Contractor shall preserve and protect all such infrastructure during the performance of its Work. The Contactor shall sequence its Work in cooperation with the utility companies and as required to work around the existing infrastructure without damaging it until it is relocated. Once relocated, the Contractor shall preserve and protect the relocated infrastructure throughout the remaining duration of the Work. Contact information is provided on the Drawings.

2.12 TEMPORARY FACILITIES

A. The Contractor shall provide generators for temporary construction power. If the required electrical load exceeds duration and load levels that make it impractical to service, then utility power will be provided. If utility power is required, it shall be the responsibility of the Contractor to submit a Utility Services Request (USR) with the required details (Web: https://www.oversightdistrict.org/utilities/).

B. The Contractor shall provide temporary portable toilets for use by its tradesmen and shall be located out of view from the traveling public at locations approved by the Owner’s Representative.

2.13 NOTIFICATION TO UTILITY COMPANIES AND EXCAVATION PERMIT

A. Utility Locate Tickets:

1. In accordance with Florida “Underground Damage Prevention and Safety Act” (Chapter 556, Florida Statutes) as administered by Sunshine 811 of Florida. Any entity or individual responsible for any project involving excavating, grading, penetration, or disturbance of the earth’s surface, inclusive of jack and boring, pile-driving, directional drilling, trenching and pipe bursting, within the District shall not commence such Work until that entity/individual has submitted a Locate Ticket request to Sunshine 811 and received clearance from the affected utilities. Refer to http://www.sunshine811.com/

2. There are two types of utility locate requests:

a. Standard Locate requests:

1) Used when no portion of the excavation will be underwater.

2) Must be submitted between 7:00 AM and 4:00 PM, Monday through Friday, excluding weekends and holidays.

3) Request must be submitted a minimum of two (2) full business days before excavation. If the excavation site is in an area that is underwater, the request must be submitted ten (10) full business days before excavation. Two (2) full business days represents a time period of 48 hours, not including the day the locate ticket is requested, weekends or holidays. Day one begins at 12:00 AM the day AFTER the locate ticket is requested.

b. Submit request to Sunshine 811 Notification system.

1) Call 811 or enter the request via the internet at 32Thttp://www.sunshine811.com/

2) Write down the Sunshine 811 Locate Ticket number

c. Contact the Reedy Creek Energy Services (RCES) Utility Locate Office via email at WDW.RCES.Utility.Locates@disney.com 32T or at (407) 824-5992 to locate the existing utilities in the area.

1) Provide the Sunshine 811 Locate Ticket number.

2) Mark up the supplied map to show the limits of the excavation that will occur within the following thirty (30) days.

d. Emergency Locate requests:

1) An emergency is defined by Chapter 556.109, Florida Statutes as any condition constituting a clear and present danger to life or property; a situation caused by the escape of any substance transported by means of an underground facility; any interruption of vital public service or communication caused by any break or defect in a member’s underground facility; or any impairment of public roads or utilities that requires immediate repair, as determined by FDOT or another affected political subdivision.

2) Work-scheduling problems are not considered an emergency.

e. If prior to 7:00 AM or after 4:00 PM on weekdays, or anytime on weekends or holidays, call the RCES Control Room Emergency Number at 407.824.4185. Provide the nature of the emergency and exact location.

f. Call Sunshine 811.

g. Provide the Sunshine 811 Locate Ticket number to the RCES Control Room.

h. Approved excavators can request emergency tickets using Internet Ticket Entry (ITE).

Excavators not approved for ITE emergency ticket entry must request emergency tickets by calling 811.

B. Have the area subject to the request marked on the ground using the “white line” method recommended by Sunshine 811. If the area is a sensitive “on-stage” area where marking is not desired, meet the locators at the site and define the actual extent of the area to be located. Follow the Low Impact Marking Guidelines defined in Chapter 556.114, Florida Statutes.

C. DO NOT BEGIN EXCAVATION until you have:

1. Received and reviewed the Utility Locate Office Locate Ticket and notes for utility presence, conflicts, or special conditions.

2. Received notification from Sunshine 811 that all public utility locators (CFTOD, Smart City, TECO/Peoples Gas, Duke Energy, etc.) have responded to the locate request. This is automatically sent to you if you provide an e-mail address during the Locate Ticket request process. Or, you can access them manually by calling 811, 800.432.4770 or using the internet at the web address noted above.

D. NOTE: RCES Utility Locate Office is ONLY RESPONSIBLE for locating the utilities owned by CFTOD and for notifying specific WDW organizations that have underground facilities within CFTOD (WDW Irrigation, WDW Telecom, and WDW Video Technology). Owner’s Representative Utility Locate Office is not responsible for location of “secondary” facilities – those lines (electric, water, sewer, etc.) that are on the customer side of the meter or any other similar lines on the customer’s property. The Locate Ticket you will get from Owner’s Representative Utility Locate Office will specifically indicate that the excavator must also contact the property Owner / customer to obtain information on those secondary lines. The customer may require that the excavator locate such lines.

E. During Excavation:

1. Protect exposed underground facilities.

2. Keep the locator marks visible throughout the excavation period or request a reissue of the locate.

3. STOP EXCAVATION if an underground facility is contacted (even if there is no noticeable damage) or if you expose any warning tape or red concrete and contact the facility Owner directly.

4. Understand tolerance zones. Locate marks show the approximate location of underground facilities. The lines can actually be located anywhere within the tolerance zone. Proceed cautiously when digging within 24 inches on either side of the locate marks when using any mechanized equipment within the tolerance zone, supervision is necessary.

5. Keep a copy of the Owner’s Representative Utility Locate Office Locate Ticket and the Sunshine 811 Positive Response at the specific area of Work.

6. Issuance of a utility locate ticket does not relieve the excavator of the responsibility of exercising due caution for unknown or miss-allocated underground utilities.

a. The Utility Locate Ticket shall not be construed as a building permit.

b. When a utility requests an area to be “HAND-DUG” it means HAND DIG ONLY.

c. Hand dig is defined as any excavation using hand shovels to break up soil or earth for removal.

1) Shovels must be made with non-conductive handles to protect the operator from the potential for electrical shocks resulting from contact with energized lines.

7. The Owner or Owner’s Representative reserves the right to stop excavation at any time for the following reasons:

a. The Utility Locate Ticket is not present at the Job Site.

b. The excavation is not in compliance with Owner’s rules and regulations.

c. The excavation is endangering personnel, equipment, or existing utilities.

d. No restitution will be made for Work stoppage for violations of the above-mentioned causes.

2.14 SAFETY REQUIREMENTS

A. The Contractor shall submit a certificate to show proof of inspection of all hoisting machinery, including serial number, date of certification, and expiration date, prior to its use. The certificate shall be displayed on the subject equipment signed by a competent person or by a government or private agency recognized by the Department of Labor. The Contractor shall maintain records and dates of the results of inspections for each hoisting machine and piece of equipment.

B. Contractor shall provide a Project Specific Safety Plan (PSSP) and obtain approval by the Owner or Owner’s Representative prior to commencing Work.

C. Contractor shall provide a Severe Weather Preparedness plan and obtain approval prior to commencing Work. The Severe Weather Preparedness plan will follow the guidelines of CFTOD’s most recent version of the “Required Storm Preparation Procedures”. The costs incurred as a result of the implementation of this plan on this Contract will be the responsibility of the Contractor.

D. Contractor is required to start all meetings or briefings with a “Safety minute or thought of the day”.

PART 3 – SPECIAL INSTRUCTIONS

3.01 WORK HOURS

A. Normal work hours shall be between 7:00 AM and 4:00 PM Monday through Friday. All Work requiring a temporary lane closure may need to be performed between 11:00 PM and 7:00 AM Sunday through Thursday.

B. Contractor shall obtain approval from the Owner’s Representative at least 72 hours prior to scheduling any Work to be performed during hours other than the normal (7:00 AM to 4:00 PM) work hours or on Saturdays, Sundays, or legal holidays.

C. The Contractor shall pay for the cost of all standby trades or premiums for Work on Saturdays, Sundays, and Holidays when the schedule or Job Site conditions require such Work.

3.02 RESTRICTIONS GOVERNING CERTAIN CONSTRUCTION OR DEMOLITION ACTIVITIES

A. Work Restrictions

1. Owner’s Representative places moratoriums restricting Work near critical utilities during the following Holiday periods:

a. Christmas through New Years

b. Easter/Spring Break

c. Memorial Day

d. July 4th

e. Labor Day

f. Thanksgiving

2. Work activities during these time periods shall be approved through the Owner’s Representative. Time periods and durations of such may differ depending on what day the Holidays actually fall on.

B. Direction drill, drilled shaft, jack and bore spoils

1. Spoils from auger operations, drilling, and jacking operations are to be disposed of properly offsite at no additional cost to the Owner.

2. All fluids (slurry) generated by directional drill/auger operations must be legally disposed of outside of the CFTOD and outside of the Walt Disney World Resort. The CFTOD Composting Facility no longer accepts drilling fluids.

C. Miscellaneous

1. (deleted)

3.03 MATERIAL AND EQUIPMENT STORAGE LIMITATIONS

A. Limited storage space will be available at the Job Site and on-site storage will be subject to approval of the Owner’s Representative. All stored material must be neatly organized and stacked, subject to advance approval by the Owner’s Representative. The Contractor shall create an engineered plan for review by the Owner that demonstrates how it will safely access the Job Site and storage areas and how it will egress from the Job Site and storage areas.

B. The Contractor shall supply materials to the Job Site on a just in time delivery strategy in order to minimize storage of materials on site.

C. The Contractor shall relocate stored materials or equipment at its expense when directed by the Owner’s Representative.

D. The Contractor shall cooperate and coordinate with the Owner’s Representative and all other Separate Contractors regarding the placement and storage of materials and equipment in order not to encumber the areas prior to and during the performance of the Work.

E. The Contractor shall be solely responsible for the securing and safekeeping of all of its on-site materials, tools and equipment. If the Contractor is to leave any materials on site after work hours, it shall be secured in a conex, or a fenced in area at the Contractor’s expense.

F. The Contractor shall use “whisperized” construction equipment. The Contractor shall be prepared to schedule Work of extreme noise levels at times established by the Owner’s Representative.

G. Material deliveries shall be made during normal working hours unless otherwise arranged with the Owner’s Representative. Where special deliveries must be made at other times, the Contractor shall arrange for labor forces to receive and unload as promptly as possible.

H. The Contractor shall not store fuel on site.

PART 4 – ATTACHMENTS

4.01 SUPPLEMENTAL INFORMATION

A. See Specification Section 00 88 50.00 - LIST OF DRAWINGS AND SPECIFICATIONS.

PART 5 – CLARIFICATIONS

5.01 The Work hereunder is not subject to, nor governed by, union and/or trade agreements.

FILE NAME – 01 14 00.00 COORDINATION WITH OWNER’S OPERATIONS

SECTION 01 14 00.00

COORDINATION WITH OWNER’S OPERATIONS

PART 1 – GENERAL

1.01 SUMMARY

A. Section includes:

1. Requirements for coordinating with Owner’s operations during the Work and included requirements for tie-ins and shutdowns necessary to complete the Work without impact on Owner’s operations except as allowed in this Section.

1. Contractor shall provide labor, materials, tools, equipment and incidentals shown, specified and required to coordinate with Owner’s operations during the Work.

B. General Requirements:

1. Except for shutdowns specified in this Section, perform the Work such that Owner’s facility remains in continuous satisfactory operation during the Project. Schedule and conduct the Work such that the Work does not: impede Owner’s production or processes, create potential hazards to operating equipment and personnel, reduce the quality of the facility’s products or effluent, or cause odors or other nuisances.

2. Work not specifically covered in this Section or in referenced Sections may, in general, be completed at any time during regular working hours in accordance with the General Conditions and Supplementary Conditions, subject to the requirements in this Section.

3. Contractor has the option of providing additional temporary facilities that can eliminate or mitigate a constraint without additional cost to Owner, provided such additional temporary facilities: do not present hazards to the public, personnel, structures, and equipment; that such additional temporary facilities do not adversely affect Owner’s ability to comply with Laws and Regulations, permits, and operating requirements; that such temporary facilities do not generate or foster the generation of odors and other nuisances; and that requirements of the Contract Documents are fulfilled.

4. Coordinate shutdowns with the Owner and Owner’s Representative. When possible, combine multiple tie-ins into a single shutdown to minimize impacts on Owner’s operations and processes.

5. Do not shut off or disconnect existing operating systems, unless accepted by Engineer in writing. Operation of existing equipment will be by the Owner’s Representative unless otherwise specified or indicated. Where necessary for the Work, Contractor shall seal or bulkhead Owner-operated gates and valves to prevent leakage that may affect the Work, Owner’s operations, or both. Provide temporary watertight plugs, bulkheads, and line stops as required. After completing the Work, remove seals, plugs, bulkhead, and line stops to satisfaction of Engineer.

C. Continuous Treatment Provision:

1. Federal regulations prohibit bypassing of untreated or partially treated wastewater or sewage during construction Work.

2. Contractor shall provide labor, equipment, materials, and incidentals to provide continuous treatment to the level prior to construction Work.

3. Contractor shall be responsible for providing temporary pumping facilities, systems, piping, valve, appurtenances, equipment, materials, and temporary utilities necessary to complete the Work without treatment bypassing.

1.02 REFERENCES

A. Definitions: A “shutdown” is when a portion of the normal operation of Owner’s facility, whether equipment, systems, piping, or conduit, has to be temporarily suspended or taken out of service to perform the Work.

1.03 ADMINISTRATIVE REQUIREMENTS

A. Coordination:

1. Review installation procedures under other Specification Sections and coordinate Work that must be performed with or before the Work specified in this Section.

2. Notify other Contractors in advance of Work requiring coordination with Owner’s operations, to provide other Contractors sufficient time for work included in their contracts that must be installed with or before Work specified in this Section.

3. When possible, combine multiple tie-ins into a single shutdown to minimize impacts on Owner’s operations and processes.

B. Pre-Shutdown Meetings: Contractor shall schedule and conduct meeting with Owner’s Representative and Engineer prior to scheduling shutdown

C. Sequencing:

1. Perform the Work in the specified sequence. Certain phases or stages of the Work may require working 24-hour days or working during hours outside of regular work hours. Work may be accelerated from a later stage to an earlier stage if Owner’s operations are not adversely affected by proposed sequence change, with Engineer’s acceptance. Stages specified in this Section are sequential in performance of the Work.

D. Scheduling:

1. Work that may interrupt normal operations shall be accomplished at times convenient to Owner.

2. Furnish at the Site, in close proximity to the shutdown and tie-in work areas, tools, equipment, spare parts and materials, both temporary and permanent, necessary to successfully complete the…