About this file
This is an Evaluation Criteria document for RFP No. DR141705 issued by Metro for the procurement of cooling and propulsion fans. The contract requires the proposer to supply 220 APS (Auxiliary Power System) cooling fans and 1,630 propulsion cooling fans over a five-year performance period. The delivery schedule mandates a minimum shipment of 36 APS fans and 288 propulsion cooling fans every six months, or an equivalent schedule subject to Metro's approval. All proposed fans must include a one-year product warranty for both APS and propulsion cooling fans as detailed in the Scope of Work.
Proposers must meet all five technical requirements to be considered for award; failure to satisfy any requirement will result in the proposal being deemed technically unacceptable and the price proposal returned unopened or electronically unread. Critical administrative requirements include notification to the Project Manager of any production delays no later than 30 days prior to the scheduled ship date in writing, as well as provision of reasonable updates on shipping timelines. Additionally, proposers must notify the Project Manager in writing 48 hours prior to shipment delivery, providing the quantity of fans being shipped, tracking or BOL number, freight carrier name, and estimated time of arrival.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EVALUATION CRITERIA DOCUMENTATION
RFP NO. DR141705
APS AND PROPULSION COOLING FANS
Each Proposer is required to meet or exceed the requirements below to be considered for award.
If the proposer fails to meet any one of the requirements, the proposal will be deemed technically unacceptable and will not be considered for award. Proposals that are deemed technically unacceptable will have the price proposal returned unopened or electronically unread.
NO. CATEGORY TECHNICAL / NON-TECHNICAL CRITERIA PASS FAIL
1.
QUANTITY /
FANS
The Proposer must provide 220 APS and 1,630 Propulsion cooling fans over a 5-year period as per Scope of Work (Exhibit A).
2. WARRANTY
The Proposer must hold a one-year product warrant for both APS and Propulsion cooling fans as outline in the Scope of Work listed (Exhibit A).
3.
DELIVERY
SCHEDULE
Upon award, the Proposer must be able to ship a minimum of 36 APS and 288 Propulsion Cooling Fans every six months as per the delivery schedule listed in Scope of Work (Exhibit A) or provide an equivalent delivery schedule subject to Metro’s approval.
4.
PRODUCTION
DELAYS
The Proposer must advise Project Manager (PM) of any production delays no later than 30 days prior to ship date in writing. Proposer shall also provide reasonable updates on shipping timelines to the Project Manager (PM) in writing.
5.
SHIPMENT
NOTIFICATION
The Proposer must notify the Project Manager in wiring 48-hours prior to shipment delivery to obtain the number of fans being shipped, tracking number or BOL number, freight carrier name and estimated time of arrival (ETA).
RFP DR141705
File details come from the government source that posted it. Updated .