EXHIBIT 2 - SCHEDULE OF QUANTITIES AND PRICES.xlsx
XLSX spreadsheet 17 KB Posted
- Attached to
- High-Rise Fire Safety Program and Training
- Solicitation number
- PS143477
- Issued by
- California
About this file
EXHIBIT 2 - SCHEDULE OF QUANTITIES AND PRICES
This is a pricing schedule for RFP PS143477, a High Rise Fire Safety Program and Training contract. The contract encompasses a seven-year period consisting of five base years plus two one-year renewal options. Proposers must provide fully burdened unit rates for all seven years to enable cost evaluation. The scope of work includes required services consisting of online certification programs for Fire Safety Directors (35 participants) and Floor Wardens (100 participants), and Rule of Five evacuation drills conducted six times annually involving five floors over two days with after-action reports. Additional as-needed services include full building evacuation drills (one occurrence), development and delivery of training materials (12 instances), phone consultations (12 instances), and Fire and Life Safety Plan certification for University System of Georgia (USG) buildings and child care centers (one occurrence).
Proposers must submit unit pricing in column C for each line item across all seven contract years. The estimated quantities provided in column D are specified for proposal evaluation purposes only and are not representative of actual quantities required during contract performance. Annual subtotals on the pricing schedule must correspond with totals on individual Form 60 submissions. The Grand Total across all seven years will be used to determine the lowest-priced proposal for award consideration. The contract structure allows the procuring entity flexibility to exercise one or both one-year renewal options following the initial five-year base term.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| EXHIBIT 2 - SCHEDULE OF QUANTITIES AND PRICES |
| RFP PS143477 HIGH RISE FIRE SAFETY PROGRAM AND TRAINING |
Proposer is required to provide their fully burdened unit rates (colum C) for the five (5) base years and the two (2) one-year options in order to calculate the total cost. The Grand Total will be used for the evaluation of proposals to determine the lowest priced propsoal. The subtotals for each year on this sheet must match the total on the individual Form 60s.
Note: The estimated quantities (column D) listed in the scenario is not representative of the actual quantities that may be required for contract performance. They are for proposal evaluation purposes only.
| UNIT PRICING FOR BASE CONRACT YEAR 1 | |
| (A) | |
| Item | (B) |
| Description | (C) |
| Fully Burdened Unit Rate | (D) |
| Estimated Quantity | (E) |
Total
| Required Services | ||||
| 1 | Online Certification Program | |||
| a. Fire Safety Director | $ - 0 | 35 | $ - 0 | |
| b. Floor Warden | $ - 0 | 100 | $ - 0 | |
| 2 | Rule of Five evacuation drills (6 drills; each drill involves 5 floors; over two days; after-action report) | $ - 0 | 6 | $ - 0 |
| Subtotal of Required Services | $ - 0 | |||
| As Needed Services | ||||
| 3 | Full building evacuation drill | $ - 0 | 1 | $ - 0 |
| 4 | Develop training material and provide training. | $ - 0 | 12 | $ - 0 |
| 5 | Phone consultation. | $ - 0 | 12 | $ - 0 |
| 6 | Certify Fire and Life Safety Plan for USG building & Child Care Center | $ - 0 | 1 | $ - 0 |
| Subtotal of As Needed Services | $ - 0 | |||
| Year 1 Grand Total | $ - 0 | |||
| BIDDER/PROPOSER: ___________________ |
| UNIT PRICING FOR BASE CONRACT YEAR 2 | |
| (A) | |
| Item | (B) |
| Description | (C) |
| Fully Burdened Unit Rate | (D) |
| Estimated Quantity | (E) |
Total
| Required Services | ||||
| 1 | Online Certification Program | |||
| a. Fire Safety Director | $ - 0 | 35 | $ - 0 | |
| b. Floor Warden | $ - 0 | 100 | $ - 0 | |
| 2 | Rule of Five evacuation drills (6 drills; each drill involves 5 floors; over two days; after-action report) | $ - 0 | 6 | $ - 0 |
| Subtotal of Required Services | $ - 0 | |||
| As Needed Services | ||||
| 3 | Full building evacuation drill | $ - 0 | 1 | $ - 0 |
| 4 | Develop training material and provide training. | $ - 0 | 12 | $ - 0 |
| 5 | Phone consultation. | $ - 0 | 12 | $ - 0 |
| 6 | Certify Fire and Life Safety Plan for USG building & Child Care Center | $ - 0 | 1 | $ - 0 |
| Subtotal of As Needed Services | $ - 0 | |||
| Year 2 Grand Total | $ - 0 |
| BIDDER/PROPOSER: ___________________ | ||
| UNIT PRICING FOR BASE CONRACT YEAR 3 | ||
| (A) | ||
| Item | (B) | |
| Description | (C) | |
| Fully Burdened Unit Rate | (D) | |
| Estimated Quantity | (E) |
Total
| Required Services | ||||
| 1 | Online Certification Program | |||
| a. Fire Safety Director | $ - 0 | 35 | $ - 0 | |
| b. Floor Warden | $ - 0 | 100 | $ - 0 | |
| 2 | Rule of Five evacuation drills (6 drills; each drill involves 5 floors; over two days; after-action report) | $ - 0 | 6 | $ - 0 |
| Subtotal of Required Services | $ - 0 | |||
| As Needed Services | ||||
| 3 | Full building evacuation drill | $ - 0 | 1 | $ - 0 |
| 4 | Develop training material and provide training. | $ - 0 | 12 | $ - 0 |
| 5 | Phone consultation. | $ - 0 | 12 | $ - 0 |
| 6 | Certify Fire and Life Safety Plan for USG building & Child Care Center | $ - 0 | 1 | $ - 0 |
| Subtotal of As Needed Services | $ - 0 | |||
| Year 3 Grand Total | $ - 0 |
BIDDER/PROPOSER: ___________________
| UNIT PRICING FOR BASE CONRACT YEAR 4 | |
| (A) | |
| Item | (B) |
| Description | (C) |
| Fully Burdened Unit Rate | (D) |
| Estimated Quantity | (E) |
Total
| Required Services | ||||
| 1 | Online Certification Program | |||
| a. Fire Safety Director | $ - 0 | 35 | $ - 0 | |
| b. Floor Warden | $ - 0 | 100 | $ - 0 | |
| 2 | Rule of Five evacuation drills (6 drills; each drill involves 5 floors; over two days; after-action report) | $ - 0 | 6 | $ - 0 |
| Subtotal of Required Services | $ - 0 | |||
| As Needed Services | ||||
| 3 | Full building evacuation drill | $ - 0 | 1 | $ - 0 |
| 4 | Develop training material and provide training. | $ - 0 | 12 | $ - 0 |
| 5 | Phone consultation. | $ - 0 | 12 | $ - 0 |
| 6 | Certify Fire and Life Safety Plan for USG building & Child Care Center | $ - 0 | 1 | $ - 0 |
| Subtotal of As Needed Services | $ - 0 | |||
| Year 4 Grand Total | $ - 0 | |||
| BIDDER/PROPOSER: ___________________ |
| UNIT PRICING FOR BASE CONRACT YEAR 5 | |
| (A) | |
| Item | (B) |
| Description | (C) |
| Fully Burdened Unit Rate | (D) |
| Estimated Quantity | (E) |
Total
| Required Services | |||||
| 1 | Online Certification Program | ||||
| a. Fire Safety Director | $ - 0 | 35 | $ - 0 | ||
| b. Floor Warden | $ - 0 | 100 | $ - 0 | ||
| 2 | Rule of Five evacuation drills (6 drills; each drill involves 5 floors; over two days; after-action report) | $ - 0 | 6 | $ - 0 | |
| Subtotal of Required Services | $ - 0 | ||||
| As Needed Services | |||||
| 3 | Full building evacuation drill | $ - 0 | 1 | $ - 0 | |
| 4 | Develop training material and provide training. | $ - 0 | 12 | $ - 0 | |
| 5 | Phone consultation. | $ - 0 | 12 | $ - 0 | |
| 6 | Certify Fire and Life Safety Plan for USG building & Child Care Center | $ - 0 | 1 | $ - 0 | |
| Subtotal of As Needed Services | $ - 0 | ||||
| Year 5 Grand Total | $ - 0 | ||||
| BIDDER/PROPOSER: ___________________ | |||||
| UNIT PRICING FOR BASE CONRACT OPTION 1 YEAR 6 | |||||
| (A) | |||||
| Item | (B) | ||||
| Description | (C) | ||||
| Fully Burdened Unit Rate | (D) | ||||
| Estimated Quantity | (E) |
Total
| Required Services | ||||
| 1 | Online Certification Program | |||
| a. Fire Safety Director | $ - 0 | 35 | $ - 0 | |
| b. Floor Warden | $ - 0 | 100 | $ - 0 | |
| 2 | Rule of Five evacuation drills (6 drills; each drill involves 5 floors; over two days; after-action report) | $ - 0 | 6 | $ - 0 |
| Subtotal of Required Services | $ - 0 | |||
| As Needed Services | ||||
| 3 | Full building evacuation drill | $ - 0 | 1 | $ - 0 |
| 4 | Develop training material and provide training. | $ - 0 | 12 | $ - 0 |
| 5 | Phone consultation. | $ - 0 | 12 | $ - 0 |
| 6 | Certify Fire and Life Safety Plan for USG building & Child Care Center | $ - 0 | 1 | $ - 0 |
| Subtotal of As Needed Services | $ - 0 | |||
| Year 6 Grand Total | $ - 0 | |||
| BIDDER/PROPOSER: ___________________ |
| UNIT PRICING FOR BASE CONRACT OPTION 2 YEAR 7 | |
| (A) | |
| Item | (B) |
| Description | (C) |
| Fully Burdened Unit Rate | (D) |
| Estimated Quantity | (E) |
Total
| Required Services | ||||
| 1 | Online Certification Program | |||
| a. Fire Safety Director | $ - 0 | 35 | $ - 0 | |
| b. Floor Warden | $ - 0 | 100 | $ - 0 | |
| 2 | Rule of Five evacuation drills (6 drills; each drill involves 5 floors; over two days; after-action report) | $ - 0 | 6 | $ - 0 |
| Subtotal of Required Services | $ - 0 | |||
| As Needed Services | ||||
| 3 | Full building evacuation drill | $ - 0 | 1 | $ - 0 |
| 4 | Develop training material and provide training. | $ - 0 | 12 | $ - 0 |
| 5 | Phone consultation. | $ - 0 | 12 | $ - 0 |
| 6 | Certify Fire and Life Safety Plan for USG building & Child Care Center | $ - 0 | 1 | $ - 0 |
| Subtotal of As Needed Services | $ - 0 | |||
| Year 7 Grand Total | $ - 0 | |||
| SUMMARY OF PRICING | ||||
| TOTAL FOR BASE YEARS 1-5 | $ - 0 | |||
| TOTAL FOR FIRST 1-YEAR OPTIONS (YEAR 6) | $ - 0 | |||
| TOTAL FOR SECOND 1-YEAR OPTIONS (YEAR 7) | $ - 0 | |||
| GRAND TOTAL (7 YEARS) | $ - 0 |
File details come from the government source that posted it. Updated .