Project No. WA NPS OLYM 2016(1) Project SPRUCE RAILROAD TRAIL SEGMENT A

# General Technical Question Answer Date

1 x

Section 107.10 (d) (9)‐ States to not perform construction activities during night time hours (2 hours before sunset to 2 hours after sunrise)‐ So October 1st‐ sunrise is 7:14 am so work can’t start until 9:14am and sunset is 6:50 pm‐ so you have to stop at 4:50pm, and it only gets shorter‐ is this a park requirement or an environmental requirement? The last two projects this was dropped?

Your interpretation is correct. There are contract requirements driven by both environmental and Park Service concerns.

An amendment will be issued to reduce the restriction in the fall months. I am unaware of the SCR’s requirements from past jobs.

6/27/17

2 x

Item #20220‐1000 removal of Individual trees‐ are these for trees inside or outside the marked clearing limits? So are all trees inside the clearing limits part of the Clearing item? The last two phases have been different‐ one included them and one did not.

Is the trail staked at all?

The individual trees called out for payment are inside of the clearing limits and meet the criteria as defined in 201.04 (e). No the trail is not staked.

6/27/17

3 x

So trees under 12” are not counted in the item?

Under measurement section 202.09 in the FP‐14 book any tree over 6 Inches is measured, just clarifying. Also does this include the trees already cut?

Trees under 12” DBH will not be measured for payment under Section 202. An Amendment will be issued clarifying the requirements of Section 201 and 202 and cut trees.

6/27/17

4 x

The trees with blue ribbons are they the ones that get removed with rootwads? Can the rootwads and logs be hauled to the ONP Pit at Sol Duc instead of the Elwha?

FHWA did not place the blue ribbons, and do not know what they indicate. An amendment will be written for logs to be hauled to Sol Duc.

6/27/17

Check General or Technical

5 x

Who is responsible for maintaining Camp David road where it turns gravel?

Camp David Road is currently maintained by the NPS. Refer to Section 107. – LEGAL

RELATIONS AND RESPONSIBILITY TO THE

PUBLIC

6/27/17

6 x The bridge on Camp David Road‐ is there any restrictions on it?

The Bridge on the Camp David road is Posted with restrictions.

6/27/17

7 x Minor crushed aggregate‐ #30202‐2000 can 1 ¼” CSBC or does it have to be 1” minus?

Furnish crushed aggregate conforming to Subsection 703.06. Maximum size is 1 inch. 6/28/2017

8 x 15301‐0000 can the QCM perform tests onsite or does it have to be someone else?

Yes, the QCM may perform the testing.

6/28/2017