DAS_SOW_NAWCTSD_ORLANDO_r2.docx
DOCX document 15 KB Posted
- Attached to
- Cellular Signal Distributed Antenna System Federal contract opportunity
- Solicitation number
- N6134020R0083
About this file
This combined synopsis/solicitation requests quotes for a cellular signal distributed antenna system project at Naval Air Warfare Center Training Systems Division in Orlando, Florida. The Navy seeks to install an active fiber distributed antenna system to provide reliable cellular coverage within a 263,000 square foot, three-floor building by September 1, 2020. The system must support approximately 1,800 users and all major carriers across multiple frequency bands. The solicitation includes line items for demolition of the existing system, installation of the new system, and optional annual maintenance. Quotes are due by April 13, 2020 and the Navy will award a firm-fixed price contract to the responsible offeror providing the lowest price technically acceptable solution meeting requirements.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAWCTSD ORLANDO
Cellular Signal Distributed Antenna System 12211 Science Drive Orlando, FL 32826
OBJECTIVE
NAWCTSD Orlando is seeking to install Active Fiber DAS to upgrade and remove the current cellular antenna system in order to provide reliable coverage within the DeFlorez building located at 12211 Science Drive, Orlando, FL 32826.
The building’s current system consists of the following:
1. Dual-Band Bi-Directional Amplifier- NOT FUNCTIONING
2. 6 Each In-Line Booster for PCS (1900 MHz) and CEL (800 MHz) coverage area
3. Dual Band Line Amp Kit
4. 1 Panel Donor Antenna PCS (1900 MHZ)
5. 1 Yagi Donor Antenna CEL (800Mhz)
6. 1 Non Penetrating Antenna Mast
7. 36 Indoor Omni Directional Distribution Antennas
8. Assorted couplers, power dividers, jumpers, coaxial cable, plenum coaxial cable, and connectors
Requirements
1. Active Fiber DAS able to support approximately 1800 users in a three floor building approximately 263K square feet.
2. No device is to be added within 10 feet of restricted areas identified in floor plan attachments.
3. Support cellular signal coverage for all major carriers (AT&T, T-Mobile, Sprint, Verizon).
4. Support multiple frequencies 2G, 3G, 4G/LTE, 5G, VHF bands used by each carrier.
5. Installation, parts, materials will be provided by the vendor.
6. Cost should include all associated fees with system design, system components along with specifications, commissioning of the system, warranty plans, service level agreements, carrier agreements, licensing, project management, labor, and lifecycle.
7. Cost to decommission and remove old system and infrastructure as a separate itemized price.
8. Must be FCC compliant and adhere to all relevant cellular signal laws and regulations.
9. Adhere to all local, state and federal codes for the installation of any equipment.
10. Work must be completed and invoiced prior to September 1, 2020.