FA301618B0005 SOW APPENDIX B2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| COSA_Item_520_Hydromulching.pdf | ||
| FA301618B0005_0004.pdf | ||
| Site_Visit_Q-A40-41.pdf | ||
| Site_Visit_Q-A_38-39.pdf | ||
| Amendment_0003.pdf | ||
| Site_Visit_Sign-In.pdf | ||
| Site_Visit_Q-A.docx | DOCX document | |
| FA301618B0005_01.pdf | ||
| FA301618B0005_02.pdf | ||
| FA301618B0005_SOW_Appendix_B1.pdf | ||
| FA301618B0005_SOW_Appendix_B3.pdf | ||
| FA301618B0005_SOW_Appendix_C.pdf | ||
| FA301618B0005_Attachment_4_Wage_Determination.pdf | ||
| FA301618B0005_Attachment_6_Unescorted_Access_Request.pdf | ||
| FA301618B0005_Attachment_3_Project_Map.pdf | ||
| FA301618B0005.docx.pdf | ||
| FA301618B0005_SOW_Appendix_A.pdf | ||
| FA301618B0005_Attachment_5_Construction_Cost_Estimate_Breakdown.xls | XLS spreadsheet | |
| FA301618B0005_Attachment_1_Statement_of_Work.pdf | ||
| FA301618B0005_Attachment_SOW_Apendix_D.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of San Antonio Standard Specifications for Construction 66 while not rolling or when changing directions. In addition, vibratory rollers shall not be allowed in the vibrating mode on mats with a plan depth of less than I-Yi inches, unless approved by the Engineer.
The motion of the rollers shall be slow enough to avoid other than usual initial displacement of the mixture. If any displacement occurs, it shall be corrected to the satisfaction of the Inspector. Ensure pavement is fully compacted before allowing rollers to stand on the pavement.
(1) Ordinary Compaction Control. One three-wheel roller, one pneumatic-tire roller, and one tandem roller shall be furnished for each compaction operation except as provided below or approved by the Engineer. The use of a tandem roller may be waived by the Engineer when the surface is already adequately smooth and further steel-wheel rolling is shown to be ineffective. With approval of the Engineer, the Contractor may substitute a vibratory roller for the three wheel roller and/or the tandem roller. Use of at least one pneumatic-tire roller is required unless approved by the Engineer. Additional or heavier rollers shall be furnished if required by the Engineer.
Rolling patterns shall be established by the Contractor to achieve the maximum compaction. The selected rolling pattern shall be followed unless changes in the mixture or placement conditions occur which affect compaction. When changes in the mixture or placement conditions occur, a new rolling pattern shall be established.
(2) Density Compaction Control. Place and compact asphaltic concrete materials in accordance with the method specified in Section 205.4.H, "Quality Control and Acceptance."
5. Compaction Cessation Temperature. Regardless of the method required for in-place compaction control, all rolling for compaction shall be completed before the mixture temperature drops below l 75°F.
6. Opening to Traffic. Allow the compacted pavement to cool to l 60°F or lower before opening to traffic unless otherwise directed. When directed, sprinkle the finished mat with water or limewater to expedite opening the roadway to traffic.
If the surface ravels, flushes, ruts or deteriorates in any manner prior to final acceptance of the work, it will be the Contractor's responsibility to correct this condition at their expense, to the satisfaction of the Inspector and in conformance with the requirements of this specification.
H. Quality Control and Acceptance. Control and acceptance of hot mixed asphaltic concrete pavement shall be followed as specified herein or as directed on the plans. The contractor shall conduct production and placement operations in accordance with the method specified.
All testing will be conducted in accordance with the testing methods shown in Table 10.
June 2008 Item 205 Hot Mix Asphaltic Concrete Pavement
City of San Antonio Standard Specifications for Construction 67
June 2008
Table 10 A ccep·a e ro uc 10n an t bl P d f d Pl acemen es ml!: e 0 S tT f M th d
Description Test Method Gradation including % passing the #200 sieve Tex-200-F or Tex-236-F Laboratory-molded density
VMA
Tex-207-F Laboratorv-molded bulk specific gravity In-Place air voids Segregation ( density profile) Tex-207-F, Part V Longitudinal ioint density Tex-207-F, Part VII Moisture content Tex-212-F, Part JI Theoretical maximum specific (Rice) gravity Tex-227-F Asphalt content Tex-236-F Hamburg Wheel test Tex-242-F Thermal profile Tex-244-F Asphalt binder sampling and testing 1 Tex-500-C Boil test1 Tex-530-C I. The Engineer may waive the sampling and testing requirements at their discretion.
1. Production Sampling and Testing. For a given project, sample asphaltic concrete materials at the production facility every 500 tons for each mixture type supplied or as directed by the Engineer. Unless otherwise shown on the plans, a production facility that supplies the same mixture to multiple City projects on the same day will not be required to sample and test at the required frequency for every project. A single test report may be used on two or more projects to represent the quality of the mixture for that day's production.
During production, do not exceed the operational tolerances in Table 7. Stop production if testing indicates tolerances are exceeded on:
• 3 consecutive tests on any individual sieve,
• 4 consecutive tests on any of the sieves, or
• 2 consecutive tests on asphalt content.
Suspend production and shipment of mixture if the asphalt content deviates from the current JMF by more than 0.5% for any test.
Begin production only when test results or other information indicate, to the satisfaction of the Engineer, that the next mixture produced will be within Table 7 tolerances.
The Contractor shall perform a Hamburg Wheel test at the direction of the Engineer at any time during production, including when the boil test indicates a change in quality from the materials submitted for the initial JMF. If the production sample fails the Hamburg Wheel test criteria in Table 6, suspend production until further Hamburg Wheel tests meet the specified values. The Engineer may require up to the entire sublot of any mixture failing the Hamburg Wheel test to be removed and replaced at the Contractor's expense.
If the Hamburg Wheel test results in a "remove and replace" condition, the Contractor may request that the Engineer confirm the results by retesting the failing material. An Independent laboratory retained by the Engineer will perform the Hamburg Wheel tests
Item 205 Hot Mix Asphaltic Concrete Pavement
City of San Antonio Standard Specifications for Construction 68 and determine the final disposition of the material in question based on the initial test results.
2. Placement Sampling and Testing.
a. In-Place Density. For every 500 tons of compacted asphaltic material or as directed by the Engineer, test the in place density. The in place density shall be in the range of 92.0% to 97.0% of the maximum density. Do not increase the asphalt content of the mixture to increase pavement density.
Unless otherwise shown on the plans, obtain 2 roadway specimens at each location selected by the Engineer for in-place density determination. Unless otherwise determined, the Engineer will witness the coring operation and measurement of the core thickness. Unless otherwise approved, obtain the cores within 1 working day after placement is completed. Obtain two 6 inch diameter cores side-by-side from within 1 foot of the location provided by the Engineer. For Type C, D and F mixtures, 4 inch diameter cores are allowed. Mark the cores for identification.
Visually inspect each core and verify that the current paving layer is bonded to the underlying layer. If an adequate bond does not exist between the current and underlying layer, take corrective action to insure that an adequate bond will be achieved during subsequent placement operations.
Immediately after obtaining the cores, dry the core holes and tack the sides and bottom. Fill the hole with the same type of mixture and properly compact the mixture. Repair core holes with other methods when approved.
If the core heights exceed the minimum untrimmed values listed in Table 8, trim the cores within 1 working day following placement operations unless otherwise approved. If the core height before trimming is less than the minimum untrimmed value shown in Table 8, decide whether or not to include the pair of cores in the density determination for that sublot. If the cores are to be included in density determination, trim the cores. If the cores will not be included in density determination, store untrimmed cores for the Engineer.
The Engineer will measure density in accordance with Tex-207-F and Tex-227-F.
Before drying to a constant weight, cores may be predried using a vacuum device, or by other methods approved by the Engineer, to remove excess moisture. The Engineer will use the average density of the 2 cores to calculate the in-place density at the selected location.
If the in-place density in the compacted mixture is below 92% or greater than 97%, change the production and placement operations to bring the in-place density within requirements. The Engineer may suspend production until the in-place density is brought to the required level, and may require a test section as described below, before proceeding.
At the onset of production, or after production and placement operations have been altered to bring the in-place density into conformance, construct a test section of 1 lane-width and at most 0.2 miles in length to demonstrate that compaction to between 92.0% and 97.0% in-place density can be obtained. Continue this procedure until a test section with the correct density can be produced. The Engineer will allow only 2
City of San Antonio Standard Specifications for Construction 69 test sections per day. When a test section producing satisfactory in-place air void content is placed, resume full production.
(1) Shoulders and Ramps. Shoulders and ramps are subject to in-place density testing, unless otherwise shown on the plans.
(2) Miscellaneous Areas. Miscellaneous areas include areas that are not generally subject to primary traffic, such as driveways, mailbox turnouts, crossovers, gores, spot level-up areas, and other similar areas. Miscellaneous areas also include level-ups and thin overlays if the layer thickness designated on the plans is less than the compacted lift thickness shown in Table 8.
Miscellaneous areas will not be included in the in place density testing. Compact areas that are not subject to in-place air void determination in accordance with ordinary compaction control.
b. Segregation (Density Profile). If shown on the plans, test for segregation using density profiles in accordance with Tex-207-F, Part V. Provide the Engineer with the results of the density profiles as they are completed. Areas defined as "Miscellaneous Areas," are not subject to density profile testing.
If density profiles are required by the plans, perform a density profile every time the screed stops, on areas that are identified by either the Contractor or the Engineer as having thermal segregation, and on any visibly segregated areas. If the screed does not stop, and there are no visibly segregated areas or areas that are identified as having thermal segregation, perform a minimum of 1 profile per 500 tons of compacted material or as directed by the Engineer.
Reduce the test frequency to a minimum of 1 profile per 2,000 tons of compacted material, or as directed by the Engineer, if 4 consecutive profiles are within established tolerances. Continue testing at this frequency unless a profile fails, at which point resume testing at a minimum frequency of 1 per 500 tons or as directed by the Engineer. The Engineer may further reduce the testing frequency based on a consistent pattern of satisfactory results.
Unless otherwise shown on the plans, the density profile is considered failing if it exceeds the tolerances in Table 11. No production or placement bonus will be paid for any sublot that contains a failing density profile. The Engineer may make as many independent density profile verifications as deemed necessary. The Engineer's density profile results will be used when available.
Investigate density profile failures and take corrective actions during production and placement to eliminate the segregation. Suspend production if 2 consecutive density profiles fail, unless otherwise approved. Resume production after the Engineer approves changes to production or placement methods.
City of San Antonio Standard Specifications for Construction 70
Table 11 Se re ation Densit Profile Acee tance Criteria
Maximum Allowable Maximum Allowable Mixture Type Density Range Density Range
(Hi hest to Lowest) (Avera e to Lowest)
T e F 6.0 cf 3.0 cf
c. Longitudinal Joint Density.
(1) Informational Tests. While establishing the rolling pattern, perform joint density evaluations and verify that the joint density is no more than 3.0 pounds per cubic foot below the density taken at or near the center of the mat. Adjust the rolling pattern if needed to achieve the desired joint density. Perform additional joint density evaluations at least once per sublot unless otherwise directed.
(2) Record Tests. If shown on the plans, for each 500 tons of compacted material or as directed by the Engineer, perform a joint density evaluation at each pavement edge that is or will become a longitudinal joint. Determine the joint density in accordance with Tex-207-F, Part VII. Record the joint density information and submit results to the Engineer. The evaluation is considered failing if the joint density is more than 3.0 pounds per cubic foot below the density taken at the core random sample location and the correlated joint density is less than 90.0%. The Engineer may make independent joint density verifications at the random sample locations. The Engineer's joint density test results will be used when available.
Investigate joint density failures and take corrective actions during production and placement to improve the joint density. Suspend production if 2 consecutive evaluations fail unless otherwise approved. Resume production after the Engineer approves changes to production or placement methods.
d. Recovered Asphalt DSR. The Engineer may take production samples or cores from suspect areas of the project to determine recovered asphalt properties. Asphalt binders with an aging ratio greater than 3.5 do not meet the requirements for recovered asphalt properties and may be deemed defective when tested and evaluated by the Engineer. The aging ratio is the dynamic shear rheometer (DSR) value of the extracted binder divided by the DSR value of the original unaged binder (including RAP binder). DSR values are obtained according to AASHTO T 315 at the specified high temperature performance grade of the asphalt. The binder from RAP will be included proportionally as part of the original unaged binder. The Engineer may require removal and replacement of the defective material at the Contractor's expense. The asphalt binder will be recovered for testing from production samples or cores using Tex-211-F.
e. Irregularities. Immediately take corrective action if surface irregularities, including but not limited to segregation, rutting, raveling, flushing, fat spots, mat slippage, color, texture, roller marks, tears, gouges, streaks, or uncoated aggregate particles, are detected.
The Engineer may allow placement to continue for at most I day of production while taking appropriate action. If the problem still exists after that day, suspend paving until the problem is corrected to the satisfaction of the Engineer.
City of San Antonio Standard Specifications for Construction 71
At the expense of the Contractor and to the satisfaction of the Engineer, remove and replace any mixture that does not bond to the existing pavement or that has other surface irregularities identified above.
3. Individual Loads of Hot Mix. The Engineer can reject individual truckloads of hot mix.
When a load of hot mix is rejected for reasons other than temperature, the Contractor may request that the rejected load be tested. Make this request within 4 hr. of rejection. The Engineer will sample and test the mixture. If test results are within the operational tolerances shown in Table 7, payment will be made for the load. If test results are not within operational tolerances, no payment will be made for the load and the Engineer may require removal.
4. Ride Quality. When required by the plans, measure ride quality in accordance with TxDOT Standard Specification Item 585, "Ride Quality for Pavement Surfaces." Surface Test Type A or B as well as Pay Schedule 1, 2, or 3 shall also be indicated on the plans.
205.5. MEASUREMENT: Hot Mix Asphaltic Concrete Pavement shall be measured by square yard, complete in place, for the thickness specified on the plans. Limits of payment will be from face of curb to face of curb. Pavement area shall not exceed the limits shown on the plans without written authorization.
205.6. PAYMENT: The work performed and materials furnished, as described by this item and measured as provided herein, shall be paid for at the contract unit bid price per square yard specified on the plans of "Hot Mix Asphaltic Concrete Pavement," which price shall be full compensation for furnishing and placing all materials, and for all labor, tools, equipment, and incidentals necessary to complete the work. The prime coat and tack coat, when required, shall be paid under the provisions of Item Nos. 202 and 203, respectively.
Trial batches will not be paid for unless they are incorporated into pavement work approved by the Engineer.
Pay adjustment for ride quality, when required on the plans, will be determined in accordance with TxDOT Standard Specification Item 585, "Ride Quality for Pavement Surfaces."
205.7. BID ITEM:
Item 205.1 - Hot Mix Asphaltic Pavement Type A - per square yard _inches pavement thickness
Item 205.2 - Hot Mix Asphaltic Pavement Type B - per square yard _inches pavement thickness
Item 205.3 - Hot Mix Asphaltic Pavement Type C - per square yard _inches pavement thickness
Item 205.4 - Hot Mix Asphaltic Pavement Type D - per square yard _inches pavement thickness
Item 205.5 - Hot Mix Asphaltic Pavement Type F - per square yard _inches pavement thickness
June 2008 Item 205 Hot Mix Asphaltic Concrete Pavement
City of San Antonio Standard Specifications for Construction 90
ITEM
208 SALVAGING, HAULING & STOCKPILING RECLAIMABLE
ASPHALTIC PAVEMENT
208.1. DESCRIPTION: Salvage, by milling existing asphalt concrete pavement or asphalt-stabilized base, haul, and stockpile existing asphalt material.
208.2. EQUIPMENT: The Engineer may require demonstration of the equipment's capabilities.
A. Milling (Planing) Machine. Use milling (planning) machines that:
1. have a minimum 6 foot cutting width except for work areas less than 6 feet wide;
2. are self-propelled with sufficient power, traction, and stability to maintain an accurate depth of cut and slope;
3. can cut in 1 continuous operation:
a. 4 inches of asphalt concrete pavement,
b. 1 inch of concrete pavement,
c. or a combination of 2 inches of asphalt concrete pavement and Y:z inch of concrete pavement;
4. use dual longitudinal controls capable of operating on both sides automatically from any longitudinal grade reference, which includes string line, ski, mobile string line, or matching shoe;
5. use transverse controls with an automatic system to control cross slope at a given rate;
6. use integral loading and reclaiming devices to allow cutting, removal, and discharge of the material into a truck in one operation; and
7. include devices to control dust created by the cutting action.
B. Manual System. Use a manual system that can achieve a uniform depth of cut, flush to all inlets, valve covers, manholes, and other appurtenances within the paved area. Use of a manual system is allowed for areas restricted to self-propelled access and for detail pavement removal.
C. Sweeper. Unless otherwise approved, use a street sweeper to remove cuttings and debris from the planed or textured pavement. Equip the sweeper with a water tank, dust control spray assembly, both a pick-up and a gutter broom, and a debris hopper.
208.3. CONSTRUCTION: Remove dirt, raised pavement markings, and other debris, as directed.
Unless otherwise shown on the plans, ensure that 95% of the reclaimed material passes a 2 inch sieve. Do not contaminate asphalt material during its removal, transportation, or storage. Repair pavement to remain that is damaged by the removal operations. Work performed under this item shall be prosecuted in such a manner as to cause minimum inconvenience to traffic or to the owners of adjacent property.
June 2008 Item 208 Salvaging, Hauling & Stockpiling Reclaimable Asphaltic Pavement
City of San Antonio Standard Specifications for Construction 91
A. Grade Reference. When required, place grade reference points at maximum intervals of 50 feet. Use the control points to set the grade reference. Support the grade reference so the maximum deflection does not exceed 1 /16 inch between supports.
B. Milling (Planing). Vary the speed of the machine to leave a grid or other pattern type with discontinuous longitudinal reach. Remove the pavement surface for the length, depth, and width shown on the typical section and to the established line and grades. Remove pavement to vertical lines adjacent to curbs, gutters, inlets, manholes, or other obstructions. Do not damage appurtenances or underlying pavement.
Provide a milled (planed) surface that has a uniform textured appearance and riding surface.
Surface should be free from gouges, continuous longitudinal grooves, ridges, oil film, and other imperfections of workmanship. Leave a uniform surface of concrete pavement free of asphalt materials when removing an asphalt concrete pavement overlay .
When an overlay on the milled (planed) pavement is not required, provide a minimum texture depth of not less than 0.05 inch. Stop milling (planing) operations when surface texture depth is not sufficient.
When located within 4 inches of steep curbs, water valves, draw grates, bridge joints, etc., asphaltic concrete that cannot be removed by the milling (planing) machine shall be removed by a manual system conforming to 208.2.B. "Manual System" or other methods acceptable to the Engineer.
When milling (planing) over a bridge deck, the milling depth shall not exceed 3/16 inch into the original deck surface of the bridge. Do not damage armor joints, sealed expansion joints, and other appurtenances.
Provide a pavement surface that, after milling (planing), has a smooth riding quality and is true to the established line, grade, and cross section. Provide a pavement surface that does not vary more than Ys inch in 10 feet. Evaluate this criterion with a 10 foot straightedge placed parallel to the centerline of the roadway. Deviations will be measured from the top of the texture. Correct any point in the surface not meeting this requirement.
Sweep pavement and gutter. The pavement and curb surfaces shall be cleaned of all debris and left in a neat and presentable condition.
C. Edge Treatments. At the end of the day and for areas under traffic, slope vertical or near vertical longitudinal faces in the pavement surface in accordance with the requirements in the plans. Taper transverse faces to provide an acceptable ride.
D. Salvaged Materials. The loose material resulting from the operation shall become the property of the contractor. If the material is designated to remain the property of the City, it shall be as stockpiled by the Contractor at locations as shown on the plans. Prepare the stockpile site by removing vegetation and trash and by providing proper drainage. Keep salvaged paving material free from contamination during its removal, transportation, and storage. Place different types or quality of salvaged asphalt paving material into separate stockpiles. Silt fencing around stockpile areas shall be provided in accordance with Item 542, "Temporary Sediment Control Fence."
June 2008
The plans or the Engineer may allow or require the use of salvaged material for other Items in the Contract.
Item 208 Salvaging, Hauling & Stockpiling Reclaimable Asphaltic Pavement
City of San Antonio Standard Specifications for Construction 92
Dispose of unsalvageable material in accordance with applicable federal, state, and local regulations.
208.4. MEASUREMENT: Measurement under this bid item shall include removal of asphaltic concrete pavement by the cubic yard (loose vehicle measurement) of material, or by the square yard in its original position at a depth as shown on the plans.
208.5. PAYMENT: The work performed in accordance with this Item and measured as provided under "Measurement" will be paid for at the unit price bid per cubic yard for "Salvaging, Hauling and Stockpiling Reclaimable Asphaltic Pavement" or at the Unit price bid per square yard for "Salvaging, Hauling and Stockpiling Reclaimable Asphaltic Pavement" of the depth specified.
This price shall be full compensation for cleaning and removing existing pavement; for any necessary stockpile area preparation; for loading, crushing or breaking, hauling and stockpiling of the material; and for furnishing all materials, labor, tools, equipment, supplies and all incidentals necessary to satisfactorily complete the work.
When plans call for the installation of silt fencing protection around stockpile areas, the fencing will be measured and paid for under Item No. 542.
208.6. BID ITEM:
Item 208.1 - Salvaging, Hauling, and Stockpiling Reclaimable Asphaltic Pavement (_inches depth) - per square yard
Item 208.2 - Salvaging, Hauling, and Stockpiling Reclaimable Asphaltic Pavement - per cubic yard (loose vehicle measurement)
June 2008 Item 208 Salvaging, Hauling & Stockpiling Reclaimable Asphaltic Pavement
City of San Antonio Standard Specifications for Construction 96
F. Sawing Equipment. Provide power-driven concrete saws to saw the joints shown on the plans. Provide standby power-driven concrete saws during concrete sawing operations.
Provide adequate illumination for nighttime sawing.
G. Grinding Equipment. When required, provide self propelled powered grinding equipment that is specifically designed to smooth and texture concrete pavement using circular diamond blades. Provide equipment with automatic grade control capable of grinding at least a 3 foot width longitudinally in each pass without damaging the concrete.
H. Testing Equipment. Provide testing equipment regardless of job-control testing responsibilities in accordance with Item 300, "Concrete," unless otherwise shown in the plans or specified.
I. Coring Equipment. When required, provide coring equipment capable of extracting cores in accordance with the requirements ofTxDOT standard laboratory test procedure Tex-424-A.
J. Miscellaneous Equipment. Furnish both 10 foot and 15 foot steel or magnesium long handled standard straightedges. Furnish enough work bridges, long enough to span the pavement, for finishing and inspection operations. Furnish date stencils to impress pavement placement dates into the fresh concrete, with numerals approximately 2 inches high by 1 inch wide by V.. inch deep.
209.4. CONSTRUCTION: Obtain approval for adjustments to plan grade-line to maintain thickness over minor subgrade or base high spots while maintaining clearances and drainage. Maintain subgrade or base in a smooth, clean, compacted condition in conformity with the required section and established grade until the pavement concrete is placed. Keep subgrade or base damp with water sufficiently in advance of placing pavement concrete. Adequately light the active work areas for all nighttime operations. Provide and maintain tools and materials to perform testing.
A. Paving and Quality Control Plan. Unless otherwise shown on the plans, submit a paving and quality control plan for approval before beginning pavement construction operations.
Include details of all operations in the concrete paving process, including longitudinal construction joint layout, sequencing, curing, lighting, early opening, leave-outs, sawing, inspection, testing, construction methods, other details and description of all equipment. List certified personnel performing the testing. Submit revisions to the paving and quality control plan for approval.
B. Job-Control Testing. Unless otherwise shown on the plans, perform all fresh and hardened concrete job-control testing at the specified frequency. Provide job-control testing personnel meeting the requirements of Item 300, "Concrete." Provide and maintain testing equipment, including strength testing equipment at a location acceptable to the Engineer. Use of a commercial laboratory is acceptable. Maintain all testing equipment calibrated in accordance with pertinent test methods. Make strength-testing equipment available to the Engineer for verification testing.
June 2008
Provide the Engineer the opportunity to witness all tests. The Engineer may require a retest if not given the opportunity to witness. Furnish a copy of all test results to the Engineer daily.
Check the first few concrete loads for slump, air, and temperature on start-up production days to check for concrete conformance and consistency. Sample and prepare strength test specimens (2 specimens per test) on the first day of production and for each 3,000 square yards or fraction thereof of concrete pavement thereafter. Prepare at least 1 set of strength-test specimens for each production day. Perform slump, air, and temperature tests each time
Item 209 Concrete Pavement
City of San Antonio Standard Specifications for Construction 97 strength specimens are made. Monitor concrete temperature to ensure that concrete is consistently within the temperature requirements. The Engineer will direct random job control sampling and testing. Immediately investigate and take corrective action as approved if any Contractor test result, including tests performed for verification purposes, does not meet specification requirements.
When job-control testing by the Contractor is waived by the plans, the Engineer will perform the testing; however, this does not waive the Contractor's responsibility for providing materials and work in accordance with this Item.
1. Job-Control Strength. Unless otherwise shown on the plans or permitted by the Engineer, use 7-day job-control concrete strength testing in accordance with TxDOT standard laboratory test procedure Tex-418-A.
For 7-day job-control by compressive strength, use a compressive strength of 3,200 psi or a lower job-control strength value proven to meet a 28-day compressive strength of 4,400 psi as correlated in accordance with TxDOT standard laboratory test procedure Tex-427- A.
Job control of concrete strength may be correlated to an age other than 7-days in accordance with TxDOT standard laboratory test procedure Tex-427-A when approved.
Job-control strength of Class HES concrete is based on the required strength and time.
When a job-control concrete strength test value is more than 10% below the required job control strength or when 3 consecutive job-control strength values fall below the required job-control strength, investigate the strength test procedures, the quality of materials, the concrete production operations, and other possible problem areas to determine the cause.
Take necessary action to correct the problem, including redesign of the concrete mix if needed. The Engineer may suspend concrete paving if the Contractor is unable to identify, document, and correct the cause of low strength test values in a timely manner.
If any job-control strength is more than 15% below the required job-control strength, the Engineer may evaluate the structural adequacy of the pavements. When directed, remove and replace pavements found to be structurally inadequate at no additional cost.
2. Split-Sample Verification Testing. When indicated on the plans, perform split-sample verification testing with the Engineer on random samples taken and split by the Engineer at a rate of at least 1 for every 10 job-control samples. The Engineer will evaluate the results of split-sample verification testing. Immediately investigate and take corrective action as approved when results of split-sample verification testing differ more than the allowable differences shown in Table 1, or when the average of 10 job-control strength results and the Engineer's split-sample strength result differ by more than 10%.
City of San Antonio Standard Specifications for Construction 98
Table I eri 1ca 10n es me: 1m1 s V "ti f T f L" ·t
Test Method1 Allowable Differences Temperature, Tex-422-A 2°F Slump, Tex-415-A 1 inch Air content, Tex-414-A or Tex-416-A 1% Compressive strength, Tex-418-A 10% I TxDOT standard laboratory test procedures
C. Reinforcing Steel and Joint Assemblies. Accurately place and secure in position all reinforcing steel as shown on the plans and in accordance with the requirements herein. Place dowels at mid-depth of the pavement slab, parallel to the surface. Place dowels for transverse contraction joints parallel to the pavement edge. Tolerances for location and alignment of dowels will be shown on the plans. Stagger the longitudinal reinforcement splices to avoid having more than 1h of the splices within a 2 foot longitudinal length of each lane of the pavement. Use multiple-piece tie bars or drill and epoxy grout tie bars at longitudinal construction joints. Verify that tie bars that are drilled and epoxied into concrete at longitudinal construction joints develop a pullout resistance equal to a minimum of% of the yield strength of the steel after ?-days. Test 15 bars using ASTM E-488, except that alternate approved equipment may be used. All 15 tested bars must meet the required pullout strength.
If any of the test results do not meet the required minimum pullout strength, perform corrective measures to provide equivalent pullout resistance. Repair damage from testing.
Acceptable corrective measures include but are not limited to installation of additional or longer tie bars.
1. Manual Placement. Secure reinforcing bars at alternate intersections with wire ties or locking support chairs. Tie all splices with wire.
2. Mechanical Placement. If mechanical placement of reinforcement results in steel misalignment or improper location, poor concrete consolidation, or other inadequacies, complete the work using manual methods.
D. Joints. Install joints as shown on the plans. Joint sealants are not required on concrete pavement that is to be overlaid with asphaltic materials. Clean and seal joints in accordance with TxDOT Item 438, "Cleaning and Sealing Joints and Cracks (Rigid Pavement and Bridge Decks)." Repair excessive spalling of the joint saw groove using an approved method before installing the sealant. Seal all joints before opening the pavement to all traffic. When placing of concrete is stopped, install a rigid transverse bulkhead, accurately notched for the reinforcing steel and shaped accurately to the cross-section of the pavement.
June 2008
1. Placing Reinforcement at Joints. Where the plans require an assembly of parts at pavement joints, complete and place the assembly at the required location and elevation with all parts rigidly secured in the required position. Accurately notch joint materials for the reinforcing steel.
2. Transverse Construction Joints.
a. Jointed Concrete Pavement. When the placing of concrete is intentionally stopped, install and rigidly secure a complete joint assembly and bulkhead in the planned transverse contraction joint location. When the placing of concrete is unintentionally
City of San Antonio Standard Specifications for Construction 99 stopped, install a transverse construction joint either at a planned transverse contraction joint location or mid-slab between planned transverse contraction joints.
For mid-slab construction joints, install tie bars of the size and spacing used in the longitudinal joints.
b. Curb Joints. Provide joints in the curb of the same type and location as the adjacent pavement. Use expansion joint material of the same thickness, type, and quality required for the pavement and of the section shown for the curb. Extend expansion joints through the curb. Construct curb joints at all transverse pavement joints. For non-monolithic curbs, place reinforcing steel into the plastic concrete pavement as shown on the plans unless otherwise approved. Form or saw the weakened plane joint across the full width of concrete pavement and through the monolithic curbs.
Construct curb joints in accordance with Item 500, "Concrete Curb, Gutter, and Curb and Gutter."
E. Placing and Removing Forms. Use clean and oiled forms. Secure forms on a base or firm subgrade that is accurately graded and that provides stable support without deflection and movement by form riding equipment. Pin every form at least at the middle and near each end.
Tightly join and key form sections together to prevent relative displacement.
Set side forms far enough in advance of concrete placement to permit inspection. Check conformity of the grade, alignment, and stability of forms immediately before placing concrete, and make all necessary corrections. Use a straightedge or other approved method to test the top of forms to ensure that the ride quality requirements for the completed pavement will be met. Stop paving operations if forms settle or deflect more than Ys inch under finishing operations. Reset forms to line and grade, and refinish the concrete surface to correct grade.
A void damage to the edge of the pavement when removing forms. Repair damage resulting from form removal and honeycombed areas with a mortar mix within 24 hours after form removal unless otherwise approved. Clean joint face and repair honeycombed or damaged areas within 24 hours after a bulkhead for a transverse construction joint has been removed unless otherwise approved. When forms are removed before 72 hours after concrete placement, promptly apply membrane curing compound to the edge of the concrete pavement.
Forms that are not the same depth as the pavement but are within 2 inches of that depth are permitted if the subbase is trenched or the full width and length of the form base is supported with a firm material to produce the required pavement thickness. Promptly repair the form trench after use. Use flexible or curved wood or metal forms for curves of 100 foot radius or less.
F. Concrete Delivery. Clean delivery equipment as necessary to prevent accumulation of old concrete before loading fresh concrete. Use agitated delivery equipment for concrete designed to have a slump of more than 5 inches. Segregated concrete is subject to rejection.
Place agitated concrete within 60 minutes after batching. Place non-agitated concrete within 45 minutes after batching. In hot weather or under conditions causing quick setting of the concrete, times may be reduced by the Engineer. Time limitations may be extended if the Contractor can demonstrate that the concrete can be properly placed, consolidated, and finished without the use of additional water.
June 2008 Item 209 Concrete Pavement
City of San Antonio Standard Specifications for Construction 100
G. Concrete Placement. Do not allow the pavement edge to deviate from the established paving line by more than Yi inch at any point. Place the concrete as near as possible to its final location, and minimize segregation and re-handling. Where hand spreading is necessary, distribute concrete using shovels. Do not use rakes or vibrators to distribute concrete.
1. Pavement. Consolidate all concrete by approved mechanical vibrators operated on the front of the paving equipment. Use immersion-type vibrators that simultaneously consolidate the full width of the placement when machine finishing. Keep vibrators from dislodging reinforcement. Use hand-operated vibrators to consolidate concrete in areas not accessible to the machine-mounted vibrators. Do not operate machine-mounted vibrators while the paving equipment is stationary. Vibrator operations are subject to review.
2. Date Imprinting. Imprint dates in the fresh concrete indicating the date of the concrete placement. Make impressions approximately 1 foot from the outside longitudinal construction joint or edge of pavement and approximately 1 foot from the transverse construction joint at the beginning of the placement day. Orient the impressions to be read from the outside shoulder in the direction of final traffic. Impress date in DD MM YY format. Imprinting of the Contractor name or logo in similar size characters to the date is allowed.
3. Curbs. Where curbs are placed separately, conform to the requirements of Item 500, "Concrete Curb, Gutter, and Curb and Gutter."
4. Temperature Restrictions. Place concrete that is between 40°F and 95°F when measured in accordance with TxDOT standard laboratory test procedure Tex-422-A at the time of discharge, except that concrete may be used if it was already in transit when the temperature was found to exceed the allowable maximum. Take immediate corrective action or cease concrete production when the concrete temperature exceeds 95°F.
Do not place concrete when the ambient temperature in the shade is below 40°F and falling unless approved. Concrete may be placed when the ambient temperature in the shade is above 35°F and rising or above 40°F. When temperatures warrant protection against freezing, protect the pavement with an approved insulating material capable of protecting the concrete for the specified curing period. Submit for approval proposed measures to protect the concrete from anticipated freezing weather for the first 72-hours after placement. Repair or replace all concrete damaged by freezing.
H. Spreading and Finishing. Unless otherwise shown on the plans, finish all concrete pavements with approved self-propelled equipment. Use power-driven spreaders, power driven vibrators, power-driven strike-off, and screed, or approved alternate equipment. Use the transverse finishing equipment to compact and strike off the concrete to the required section and grade without surface voids. Use float equipment for final finishing. Use concrete with a consistency that allows completion of all finishing operations without addition of water to the surface. Use the minimal amount of water fog mist necessary to maintain a moist surface. Reduce fogging if float or straightedge operations result in excess slurry.
June 2008
1. Finished Surface. Perform sufficient checks with long-handled 10 foot and 15 foot straightedges on the plastic concrete to ensure that the final surface is within the tolerances specified in Surface Test A in TxDOT standard test procedure Item 585, "Ride Quality for Pavement Surfaces." Check with the straightedge parallel to the centerline.
City of San Antonio Standard Specifications for Construction 101
2. Maintenance of Surface Moisture. Prevent surface drying of the pavement before application of the curing system by means that may include water fogging, the use of wind screens and the use of evaporation retardants. Apply evaporation retardant at the rate recommended by the manufacturer. Reapply the evaporation retardant as needed to maintain the concrete surface in a moist condition until curing system is applied. Do not use evaporation retardant as a finishing aid. Failure to take acceptable precautions to prevent surface drying of the pavement will be cause for shut down of pavement operations.
3. Surface Texturing. Complete final texturing before the concrete has attained its initial set. Drag the carpet longitudinally along the pavement surface with the carpet contact surface area adjusted to provide a satisfactory coarsely textured surface. Prevent the carpet from getting plugged with grout. Do not perform carpet dragging operations while there is excessive bleed water.
A metal-tine texture finish is required for all areas with a posted speed limit in excess of 45 mph. A metal-tine texture finish is required unless otherwise shown on the plans for areas with a posted speed limit Jess than 45 mph. Immediately following the carpet drag, apply a single coat of evaporation retardant at a rate recommended by the manufacturer.
Provide the metal-tine finish immediately after the concrete surface has set enough for consistent tining. Operate the metal-tine device to obtain grooves spaced at I inch, approximately 3/16 inch deep, with a minimum depth of Ya inch, and approximately 1/12 inch wide. Do not overlap a previously tined area. Use manual methods to achieve similar results on ramps and other irregular sections of pavements. Repair damage to the edge of the slab and joints immediately after texturing. Do not tine pavement that will be overlaid or that is scheduled for blanket diamond grinding or shot blasting.
When carpet drag is the only surface texture required by the plans, ensure that adequate and consistent micro-texture is achieved by applying sufficient weight to the carpet and keeping the carpet from getting plugged with grout, as directed by the Engineer. Target a carpet drag texture of .04 inch, as measured by Tex-436-A Correct any location with a texture less than .03 inch by diamond grinding or shot blasting. The Engineer will determine the test locations at points located transversely to the direction of traffic in the outside wheel path.
4. Small or Irregular Placements. Where machine placements and finishing of concrete pavement are not practical, use hand equipment and procedures that produce a consolidated and finished pavement section to the line and grade.
5. Emergency Procedures. Use hand-operated equipment for applying texture, evaporation retardant, and cure in the event of equipment breakdown.
I. Curing. Keep the concrete pavement surface from drying as described in Section 209.4.H.2, "Maintenance of Surface Moisture," until the curing material has been applied. Maintain and promptly repair damage to curing materials on exposed surfaces of concrete pavement continuously for at least 3 curing days. A curing day is defined as a 24 hour period when either the temperature taken in the shade away from artificial heat is above 50°F for at least 19 hours or when the surface temperature of the concrete is maintained above 40°F for 24 hours. Curing begins when the concrete curing system has been applied. Stop concrete paving if curing compound is not being applied promptly and maintained adequately. Other methods of curing in accordance with Item 307, "Concrete Structures," may be used when specified or approved.
City of San Antonio Standard Specifications for Construction 102
1. Membrane Curing. Spray the concrete surface uniformly with 2 coats of membrane curing compound at an individual application rate of not more than 180 square feet per gallon. Do not allow the concrete surface to dry before applying the curing compound.
Use a towel or absorptive fabric to remove any standing pools of bleed water that may be present on the surface before applying the curing compound. Apply the first coat within 10 min. after completing texturing operations. Apply the second coat within 30 minutes after completing texturing operations.
Before and during application, maintain curing compounds in a uniformly agitated condition, free of settlement. Do not thin or dilute the curing compound.
Where the coating shows discontinuities or other defects or if rain falls on the newly coated surface before the film has dried enough to resist damage, apply additional compound at the same rate of coverage to correct the damage. Ensure that the curing compound coats the sides of the tining grooves.
2. Asphalt Curing. When an asphaltic concrete overlay is required, apply a uniform coating of asphalt curing at a rate of 90 to 180 square feet per gallon as required. Apply curing immediately after texturing and just after the free moisture (sheen) has disappeared.
Obtain approval to add water to the emulsion to improve spray distribution. Maintain the asphalt application rate when using diluted emulsions. Maintain the emulsion in a mixed condition during application.
3. Curing Class HES Concrete. For all Class HES concrete pavement, provide membrane curing in accordance with Section 209.4.1.1, "Membrane Curing," followed promptly by water curing until opening strength is achieved but not less than 24 hours.
J. Sawing Joints. Saw joints to the depth shown on the plans as soon as sawing can be accomplished without damage to the pavement regardless of time of day or weather conditions. Some minor raveling of the saw cut is acceptable. Use a chalk line, string line, sawing template, or other approved method to provide a true joint alignment. Provide enough saws to match the paving production rate to ensure sawing completion at the earliest possible time to avoid uncontrolled cracking. Reduce paving production if necessary to ensure timely sawing of joints. Promptly restore membrane cure damaged within the first 72 hours of curing.
K. Protection of Pavement and Opening to Traffic. Testing for early opening is the responsibility of the Contractor regardless of job-control testing responsibilities unless otherwise shown in the plans or directed. Testing result interpretation for opening to traffic is subject to the approval of the Engineer.
June 2008
1. Protection of Pavement. Erect and maintain barricades and other standard and approved devices that will exclude all vehicles and equipment from the newly placed pavement for the periods specified. Before opening to traffic, protect the pavement from damage due to crossings using approved methods. Where a detour is not readily available or economically feasible, an occasional crossing of the roadway with overweight equipment may be permitted for relocating equipment only but not for hauling material. When an occasional crossing of overweight equipment is permitted, temporary matting or other approved methods may be required.
City of San Antonio Standard Specifications for Construction 103
Maintain an adequate supply of sheeting or other material to cover and protect fresh concrete surface from weather damage. Apply as needed to protect the pavement surface from weather.
2. Opening Pavement to All Traffic. Pavement that is 7 days old may be opened to all traffic. Before opening to traffic, clean pavement, place stable material against the pavement edges, seal joints, and perform all other traffic safety related work.
3. Opening Pavement to Construction Equipment. Unless otherwise shown on the plans, concrete pavement may be opened early to concrete paving equipment and related delivery equipment after the concrete is at least 48 hours old and opening strength has been demonstrated in accordance with Section 209.4.K.4, "Early Opening to All Traffic," before curing is complete. Keep delivery equipment at least 2-feet from the edge of the concrete pavement.