This document is the CTOF (Canteen, Theater, and Other Facilities) General Provisions Memorandum, which establishes standard contractual terms and conditions for Non-Appropriated Fund Instrumentality (NAFI) contracts with the Department of Defense.
The memorandum outlines fundamental contract administration procedures including definitions of key parties (NAFI, Contracting Officer, and Contractor), dispute resolution processes with appeal rights to the Armed Services Board of Contract Appeals, and governance under substantive U.S. law. It establishes critical operational clauses covering examination of records for contracts over $10,000 involving price and costing data; assignment procedures requiring Contracting Officer approval; gratuities prohibitions with penalties of three to ten times costs for violations; and termination provisions for both convenience and cause. The memorandum specifies inspection and acceptance at destination unless otherwise provided, payment procedures aligned with the Prompt Payment Act, and commercial warranty requirements at the most favorable terms offered. Additional provisions address tax treatment, proof of shipment documentation for overseas and parcel post deliveries, electronic fund transfer payment requirements, and contractor certification of non-debarment status. The document incorporates numerous Federal Acquisition Regulation (FAR) clauses by reference including provisions on Changes (FAR 52.243-1), Davis-Bacon Act compliance, Service Contract Act wage determinations, Contract Work Hours and Safety Standards, Buy American Act requirements, Equal Opportunity employment, convict labor prohibitions, fraud convictions prohibitions, segregated facilities prohibitions, and hazardous material identification with Material Safety Data Sheet requirements. These incorporated clauses apply with "Government" replaced by "NAFI" and become self-deleting when inapplicable based on contract type or dollar amount.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CTOF GENERAL PROVISIONS MEMORANDUM
l. Definitions. As used throughout this contract, the following terms and abbreviations have the meanings set forth below:
a. The term "contract" means this agreement or order and any modifications hereto.
b. The abbreviation "NAFI" means Non-Appropriated Fund Instrumentality of the United States
Government.
c. The term "Contracting Officer" means the person executing or responsible for administering this contract on behalf of the NAFI, which is a party hereto, or their successor or successors. d.
The term "Contractor" means the party responsible for providing supplies and/or services at a certain price or rate to the NAFI under this contract.
d. The abbreviation “FAR” means Federal Acquisition Regulation.
2. Disputes.
a. Except as otherwise provided in this contract, any dispute or claim concerning this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall state his decision in writing and mail or otherwise furnish a copy of it to the Contractor. Within
30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the Armed Services Board of
Contract Appeals, and the decision of the Board shall be final and conclusive; provided that if no such appeal is filed, the decision of the Contracting Officer shall be final and conclusive. The
Contractor shall be afforded an opportunity to be heard and to offer evidence in support of any appeal under this clause. Pending final decision on such a dispute, however, the Contractor shall proceed diligently with the performance of the contract and in accordance with the decision of the Contracting Officer unless directed to do otherwise by the Contracting Officer. b. A claim by the Contractor shall be made in writing and submitted to the Contracting Officer for a written decision. Contractors shall provide the certification specified below when submitting any claim.
Any person duly authorized to bind the Contractor with respect to the claim may execute the certification.
“I certify that the claim is made in good faith; that the supporting data is accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the Contractor believes the Government is liable; and that I am duly authorized to certify on behalf of the Contractor.”
b. This "Disputes" clause does not preclude consideration of law questions in connection with decisions provided for in paragraph "a" above, provided, that nothing in this contract shall be construed as making final the decision of any administrative official, representative, or board on a question of law.
3. Law Governing Contracts. In any dispute arising out of this contract, the decision of which requires consideration of law questions, the rights and obligations of the parties shall be interpreted and determined in accordance with the substantive laws of the United States of
America.
4. Legal Status. The NAFI is an integral part of the Department of Defense and is an instrumentality of the United States Government. Therefore, NAFI contracts are United States
Government contracts; however, they do not obligate appropriated funds of the United States.
5. Examination of Records. This clause is applicable under contracts that are entered into by means of negotiation and where price and costing data are required to support a determination of price reasonableness. This clause does not apply to commercial items or when the Contracting
Officer determines that prices agreed upon are based on adequate price competition. The
Contractor agrees that the Contracting Officer or his duly authorized representative shall have the right to examine and audit the books and records of the Contractor directly pertaining to the contract during the period of the contract and until the expiration of three years after the final payment.
6. Assignment. The Contractor or its assignee’s rights to be paid amounts due as a result of performance of this contract, may be assigned. No assignment by the Contractor, assigning its rights or delegating its obligations under this contract will be effective and binding on the NAFI until the written terms of the assignment have been approved in writing by the Contracting
Officer.
7. Gratuities.
a. The NAFI may, by written notice to the Contractor, terminate the right of the Contractor to proceed under this contract if it is found, after notice and hearing, by the Secretary of the Air
Force or their duly authorized representative, that gratuities (in the form of entertainment, gifts, or otherwise) were offered or given by the Contractor, or any agent, or representative of the
Contractor, to any officer or employees of the Government or the NAFI with a view toward securing favorable treatment with respect to the awarding or amending, or the making of any determinations with respect to the performing of such contract.
b. In the event this contract is terminated as provided in paragraph "a" hereof, the NAFI shall be entitled (i) to pursue the same remedies against the Contractor as it could pursue in the event of a breach of contract by the Contractor, and (ii) as a penalty in addition to any other damages to which it may be entitled by law, to exemplary damages in an amount (as determined by the
Secretary of the Air Force or their duly authorized representative) which shall be not less than three nor more than ten times the cost incurred by the Contractor in providing any such gratuities to any such officer or employee.
c. The rights and remedies of the NAFI provided in this clause shall not be exclusive and are in addition to any other rights and remedies provided by law or under this contract.
8. Termination for Convenience. The Contracting Officer, by written notice, may terminate this contract, in whole or in part, when it is in the best interest of the NAFI. If this contract is for supplies and is so terminated, the Contractor shall be compensated in accordance with FAR, Sub
Parts 49.1 and 49.2 in effect on this contract's date. To the extent that this contract is for services and is so terminated, the NAFI shall be liable only for payment in accordance with the payment provisions of this contract for services rendered prior to the effective date of termination, providing there are no Contractor claims covering nonrecurring costs for capital investment. If there are any such Contractor claims, they shall be settled in accordance with FAR, Sub Parts
49.1 and 49.2.
9. Cancellation By Mutual Agreement. Should the situation warrant, the parties upon mutual agreement and no costs, may cancel this contract.
10. Termination for Cause.
a. (1) The NAFI may, subject to paragraphs (c) and (d) below, by written notice of cause to the
Contractor, terminate this contract in whole or in part if the Contractor fails to- (i) Deliver the supplies or perform the service within the time specified within this contract or any Extension;
(ii) Make progress, so as to endanger performance of this contract (but see subparagraph (a)(2) below); or
(iii) Perform any of the other provisions of this contract (but see subparagraph (a)(2) below).
(2) The NAFI's right to terminate this contract under subdivisions (1)(ii) and (1)(iii) above, may be exercised if the Contractor does not cure such failure within 10 days (or more if authorized in writing by the Contracting Officer) after receipt of notice from the Contracting Officer specifying the failure.
b. If the NAFI terminates this contract in whole or in part, it may acquire, under the terms and in the manner the Contracting Officer considers appropriate, supplies or services similar to those terminated, and the Contractor will remain liable to the NAFI for any excess costs for those supplies or services. However the Contractor must continue the work not terminated.
c. The Contractor shall not be liable for any excess costs if the failure to perform the contract arises from causes beyond the control and without the fault or negligence of the Contractor.
Examples of such causes include (1) acts of God or of the public enemy, (2) act of the NAFI in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and; (9) unusually severe weather. Defaults by subcontractors at any tier for any reason do not constitute causes beyond the control and without the fault or negligence of the Contractor.
d. If this contract is terminated for cause, the NAFI may require the Contractor to transfer title and deliver to the NAFI as directed by the Contracting Officer, any
(1) completed supplies, and
(2) partially completed supplies and materials, parts, tool dies, jigs, fixtures, plans, drawings, information, and contract rights (collectively referred to as manufacturing materials in the clause) that the Contractor has specifically produced or acquired for the terminated portion of this contract. Upon direction of the Contracting Officer, the Contractor shall also protect and preserve property in its possession in which the NAFI has an interest.
e. The NAFI shall pay the contract price for completed supplies delivered and accepted. The
Contractor and Contracting Officer shall agree on the amount of payment for manufacturing materials delivered and accepted and for the protection and preservation of the property. Failure to agree will be a dispute under the Disputes Clause. The NAFI may withhold from these amounts any sum the Contracting Officer determines to be necessary to protect the NAFI against loss because of outstanding liens or claims of former lien holders.
f. If, after termination, it is determined that the cause by the Contractor was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for convenience of the NAFI.
g. The rights and remedies of the NAFI in this clause are in addition to any other rights and remedies provided by law or under this contract.
11. Inspection and Acceptance. Inspection and acceptance will be at destination, unless otherwise provided in this contract. Notwithstanding the requirements for any NAFI inspection and test contained in specifications applicable to this contract, except where specialized inspections or tests are specified for performance solely by the NAFI, the Contractor, shall perform or have performed the inspections and tests required to substantiate that the supplies provided under the contract conform to the drawings, specifications, and contract requirements listed herein, including if applicable the technical requirements for the manufacturers' part numbers specified herein. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. Acceptance of the supplies or services or a written notice of rejections must be accomplished on or before the third working day following delivery of the supplies or services, unless otherwise specified in this contract.
12. Variation in Quantities. No variation in quantity of any item called for by this contract will be accepted unless authorized by the Contracting Officer.
13. Partial Deliveries. Partial deliveries are not permitted unless authorized by the terms of the contract or approved by the Contracting Officer.
14. Payments. Partial payments will be made when deliveries are authorized or as approved by the Contracting Officer. Payments and penalties for late payments are subject to the requirements established by the Prompt Payment Act, as amended, and as implemented for NAFI's. If the
NAFI makes payment but such payment fails to include a prompt payment penalty due to the
Contractor within 10 days from when the contract payment is made, penalty amounts will not be paid unless the Contractor makes a written request within forty days after the date of payment.
15. Hold and Save Harmless. The Contractor shall indemnify, hold and save harmless, and defend the NAFI, its outlets and customers from any liability, claimed or established for violation or infringement of any patent, copyright, or trademark right asserted by any third party with respect to goods hereby ordered or any part thereof. Contractor further agrees to hold the
NAFI harmless from all claims or judgments for damages resulting from the use of products or services listed in this contract, except for such claims or damages caused by, or resulting from negligence of NAFI customers, employees, agents, or representatives. Also, Contractor shall at all times hold and save harmless the NAFI, its agents, representatives, and employees from any and all suits, claims, charges, and expenses which arise out of acts or omissions of Contractor, its agents, representatives, or employees.
16. Modifications. No agreement or understanding to modify this contract will be binding upon the NAFI unless made in writing and signed by a Contracting Officer from the office that issued the contract or its successor.
17. Taxes.
a. Except as may be otherwise provided in this contract, the contract price includes all taxes, duties or other public charges in effect and applicable to this contract on the contract date, except any tax, duty, or other public charge, which by law, regulation or governmental agreement, is not applicable to expenditures made by the NAFI or on its behalf; or any tax, duty, or other public charge from which the Contractor, or any subcontractor hereunder, is exempt by law, regulation or otherwise. If any such tax, duty, or other public charge has been included in the contract price, through error or otherwise, the contract price shall be correspondingly reduced.
b. If for any reason, after the contract date of execution, the Contractor or subcontractor is relieved in whole or in part from the payment or the burden of any tax, duty, or other public charge included in the contract price, the contract price shall be correspondingly reduced; or if the Contractor or subcontractor is required to pay in whole or in part any tax, duty, of other public charge which was not applicable at the contract date of execution the contract price shall be correspondingly increased.
18. Proof of Shipment. (Applicable to shipments outside the United States through the Surface
Deployment and Distribution Command (SDDC) and Parcel Post shipments to overseas destinations.)
a. Notwithstanding any clause of this contract to the contrary, payment will be made for items not yet received, upon receipt of an invoice accompanied by an appropriate proof of shipment. If shipment is made by insured parcel post, the contractor must furnish a copy of the Insured Mail
Receipt issued by the US Postal Service. Otherwise, a stamped copy of a Certificate of Mailing issued by the US Postal Service must be furnished. If shipment is made by a common carrier
(rail, air or motor freight), the Contractor must furnish a signed copy of the shipping document on which items are receipted for by the common carrier. A signed receipt by a NAFI representative at the delivery point (CCP or POE) is also acceptable evidence of proof of shipment.
b. Forwarding a proof of shipment and an invoice for payment by the Contractor shall be construed as a certification by the contractor that the items shipped conform to the specifications.
c. Notwithstanding any provisions of this clause or any payment made pursuant to the terms of this clause prior to receipt of the items contracted for, the NAFI retains the right to inspect upon receipt and the right to reject nonconforming items. The liability of the Contractor with respect to items for which payments have been made will, after inspection by the NAFI or after the expiration of a reasonable time following delivery to the NAFI within which inspection may be made, whichever occurs first, be limited to (i) exceptions taken at the time of inspection, and (ii) latent defects, fraud, or such gross mistakes as amount to fraud.
19. Commercial Warranty. The Contractor agrees that the supplies or services furnished under this contract shall be covered by the most favorable commercial warranties the Contractor gives to any customer for such supplies or services and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the NAFI by any other clause of this contract. The printed terms and conditions of such warranty will be provided to the NAFI with the delivery of any supplies covered.
20. Advertisements. Contractor agrees that none of its nor its agent's advertisements, to include publications, merchandise, promotions, coupons, sweepstakes, contest, sales brochures, etc, shall state, infer or imply that the Contractor's products or services are approved, promoted, or endorsed by the NAFI. Any advertisement, including cents-off coupons, which refers to a NAFI will contain a statement that the advertisement is neither paid for, nor sponsored in whole or in part by, the particular activity.
21. Discounts for Prompt Payment.
a. Discounts for prompt payment will not be considered in the evaluation of offers. However, any offered discount will form a part of the award, and will be taken if payment is made within the discount period indicated in the offer by the offeror. As an alternative to offering a prompt payment discount in conjunction with the offer, offerors awarded contracts may include prompt payment discounts on individual invoices.
b. In connection with any discount offered for prompt payment, time shall be computed from the date of the invoice. If the Contractor has not placed a date on the invoice, the due date shall be calculated from the date the designated billing office receives a proper invoice, provided the agency annotates such invoice with the date of receipt at the time of receipt. For the purpose of computing the discount earned, payment shall be considered to have been made on the date that appears on the payment check or, for an electronic funds transfer, the specified payment date.
When the discount date falls on a Saturday, Sunday, or legal holiday when Federal Government offices are closed and Government business is not expected to be conducted, payment may be made on the following business day.
22. Invoices.
a. An invoice is a written request for payment under the contract for supplies delivered or for services rendered. In order to be proper, an invoice should include (and in order to support the payment of interest penalties, must include) the following:
(i) Invoice date;
(ii) Name of Contractor;
(iii) Contract number (including order number, if any), contract line item number, contract description of supplies or services, quantity, contract unit of measure and unit price, and extended total;
(iv) Shipment number and date of shipment (Bill of Lading number and weight of shipment will be shown for shipments on Government Bills of Lading);
(v) Name and address to which payment is to be sent (which must be the same as that in the contract or on a proper notice of assignment);
(vi) Name (where practicable), title, phone number and mailing address of person to be notified in event of a defective invoice; and
(vii) Any other information or documentation required by other provisions of the contract (such as evidence of shipment). Invoices shall be prepared and submitted in duplicate (one copy shall be marked “Original") unless otherwise specified.
b. For purposes of determining if interest begins to accrue under the PROMPT PAYMENT ACT
(PUBLIC LAW 97-177):
(i) A proper invoice will be deemed to have been received when it is received by the office designated in the contract for receipt of invoices and acceptance of the supplies delivered or services rendered has occurred.
(ii) Payment shall be considered made on the date on which a check for such payment is dated.
(iii) Payment terms (e.g., "Net 20") offered by the contractor will not be deemed Required payment dates.
(iv) The following periods of time will not be included:
(A) After receipt of improper invoice and prior to notice of any defect or impropriety, but not to exceed three days for meat and meat food products, five days for perishable agricultural commodities, and 15 days in all other cases, and
(B) Between the date of a notice of any defect or impropriety and the date a proper invoice is received. When the notice is in writing, it shall be considered made on the date shown on the notice.
23. Electronic Fund Transfer Payments. Federal law 31 USC requires Federal payments to be made by electronic fund transfer. Any payment made on this contract will be made using the
Government Purchase Card as the method of EFT (unless otherwise specified within the contract or exempted by law).
24. Notification of Debarment/Suspension Status. The Contractor shall provide immediate notice to the Contracting Officer in the event of being suspended, debarred or declared ineligible by any other Federal Department or agency, or upon
25. List of FAR Clauses Incorporated
The provisions of the following clauses set forth in the Federal Acquisition Regulation (FAR) or
DoD FAR Supplement are hereby incorporated into this order or contract by reference with the same force and effect as though herein set forth in full. As used in the following clauses, the term
"Government" is deleted and the abbreviation "NAFI" is substituted in lieu thereof. The date of each clause shall be the current date set forth in FAR or DoD FAR Supplement on the issuance date of this order or contract. Clauses made inapplicable by the reference or by the kind of order, contract (e.g., orders or contract for services instead of supplies) or dollar amount are self-deleting. The complete text of any clause incorporated in this order or contract by reference may be obtained from the contracting officer.
25.1. FAR 52.243-1 - Changes - Fixed-Price. (Aug 1987)
(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:
(1) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications.
(2) Method of shipment or packing.
(3) Place of delivery.
(b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the
Contracting Officer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
(c) The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract.
(d) If the Contractor’s proposal includes the cost of property made obsolete or excess by the change, the Contracting Officer shall have the right to prescribe the manner of the disposition of the property.
(e) Failure to agree to any adjustment shall be a dispute under the Disputes clause. However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.
(b) If any such change causes an increase or decrease in the estimated cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, or otherwise affects any other terms and conditions of this contract, the Contracting
Officer shall make an equitable adjustment in the—
(1) Estimated cost, delivery or completion schedule, or both;
(2) Amount of any fixed fee; and
(3) Other affected terms and shall modify the contract accordingly.
(c) The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract.
(d) Failure to agree to any adjustment shall be a dispute under the Disputes clause. However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.
(e) Notwithstanding the terms and conditions of paragraphs (a) and (b) of this clause, the estimated cost of this contract and, if this contract is incrementally funded, the funds allotted for the performance of this contract, shall not be increased or considered to be increased except by specific written modification of the contract indicating the new contract estimated cost and, if this contract is incrementally funded, the new amount allotted to the contract. Until this modification is made, the Contractor shall not be obligated to continue performance or incur costs beyond the point established in the Limitation of Cost or Limitation of Funds clause of this contract.
25.1.1. Alternate I (Apr 1984). If the requirement is for services, other than architect-engineer or other professional services, and no supplies are to be furnished, substitute the following paragraph (a) for paragraph (a) of the basic clause:
(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:
(1) Description of services to be performed.
(2) Time of performance (i.e., hours of the day, days of the week, etc.).
(3) Place of performance of the services.
25.1.2. Alternate II (Apr 1984). If the requirement is for services (other than architect-engineer services, transportation, or research and development) and supplies are to be furnished, substitute the following paragraph (a) for paragraph (a) of the basic clause:
(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:
(1) Description of services to be performed.
(2) Time of performance (i.e., hours of the day, days of the week, etc.).
(3) Place of performance of the services.
(4) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government, in accordance with the drawings, designs, or specifications.
(5) Method of shipment or packing of supplies.
(6) Place of delivery.
25.2. FAR 52.222-13 - Compliance with Davis-Bacon and related Act Regulations (Feb
1988). All rulings and interpretations of the Davis-Bacon and Related Acts contained in 29 CFR parts 1, 3, and 5 are hereby incorporated by reference in this contract.
25.3. FAR 52.222-41 - Service Contract Act of 1965, as Amended (Nov 2007).
(a) Definitions. As used in this clause—
“Act” means the Service Contract Act of 1965 (41 U.S.C. 351, et seq.).
“Contractor,” when this clause is used in any subcontract, shall be deemed to refer to the subcontractor, except in the term “Government Prime Contractor.”
“Service employee” means any person engaged in the performance of this contract other than any person employed in a bona fide executive, administrative, or professional capacity, as these terms are defined in Part 541 of Title 29, Code of Federal Regulations, as revised. It includes all such persons regardless of any contractual relationship that may be alleged to exist between a
Contractor or subcontractor and such persons.
(b) Applicability. This contract is subject to the following provisions and to all other applicable provisions of the Act and regulations of the Secretary of Labor (29 CFR Part 4). This clause does not apply to contracts or subcontracts administratively exempted by the Secretary of Labor or exempted by 41 U.S.C. 356, as interpreted in Subpart C of 29 CFR Part 4.
(c) Compensation.
(1) Each service employee employed in the performance of this contract by the Contractor or any subcontractor shall be paid not less than the minimum monetary wages and shall be furnished fringe benefits in accordance with the wages and fringe benefits determined by the Secretary of
Labor, or authorized representative, as specified in any wage determination attached to this contract.
(2)(i) If a wage determination is attached to this contract, the Contractor shall classify any class of service employee which is not listed therein and which is to be employed under the contract
(i.e., the work to be performed is not performed by any classification listed in the wage determination) so as to provide a reasonable relationship (i.e., appropriate level of skill comparison) between such unlisted classifications and the classifications listed in the wage determination. Such conformed class of employees shall be paid the monetary wages and furnished the fringe benefits as are determined pursuant to the procedures in this paragraph (c).
(ii) This conforming procedure shall be initiated by the Contractor prior to the performance of contract work by the unlisted class of employee. The Contractor shall submit Standard Form
(SF) 1444, Request For Authorization of Additional Classification and Rate, to the Contracting
Officer no later than 30 days after the unlisted class of employee performs any contract work.
The Contracting Officer shall review the proposed classification and rate and promptly submit the completed SF 1444 (which must include information regarding the agreement or disagreement of the employees’ authorized representatives or the employees themselves together with the agency recommendation), and all pertinent information to the Wage and Hour Division, Employment Standards Administration, U.S. Department of Labor. The Wage and Hour Division will approve, modify, or disapprove the action or render a final determination in the event of disagreement within 30 days of receipt or will notify the Contracting Officer within 30 days of receipt that additional time is necessary.
(iii) The final determination of the conformance action by the Wage and Hour Division shall be transmitted to the Contracting Officer who shall promptly notify the Contractor of the action taken. Each affected employee shall be furnished by the Contractor with a written copy of such determination or it shall be posted as a part of the wage determination.
(iv)(A) The process of establishing wage and fringe benefit rates that bear a reasonable relationship to those listed in a wage determination cannot be reduced to any single formula. The approach used may vary from wage determination to wage determination depending on the circumstances. Standard wage and salary administration practices which rank various job classifications by pay grade pursuant to point schemes or other job factors may, for example, be relied upon. Guidance may also be obtained from the way different jobs are rated under Federal pay systems (Federal Wage Board Pay System and the General Schedule) or from other wage determinations issued in the same locality. Basic to the establishment of any conformable wage rate(s) is the concept that a pay relationship should be maintained between job classifications based on the skill required and the duties performed.
(B) In the case of a contract modification, an exercise of an option, or extension of an existing contract, or in any other case where a Contractor succeeds a contract under which the classification in question was previously conformed pursuant to paragraph (c) of this clause, a new conformed wage rate and fringe benefits may be assigned to the conformed classification by indexing (i.e., adjusting) the previous conformed rate and fringe benefits by an amount equal to the average (mean) percentage increase (or decrease, where appropriate) between the wages and fringe benefits specified for all classifications to be used on the contract which are listed in the current wage determination, and those specified for the corresponding classifications in the previously applicable wage determination. Where conforming actions are accomplished in accordance with this paragraph prior to the performance of contract work by the unlisted class of employees, the Contractor shall advise the Contracting Officer of the action taken but the other procedures in subdivision (c)(2)(ii) of this clause need not be followed.
(C) No employee engaged in performing work on this contract shall in any event be paid less than the currently applicable minimum wage specified under section 6(a)(1) of the Fair Labor
Standards Act of 1938, as amended.
(v) The wage rate and fringe benefits finally determined under this paragraph (c)(2) of this clause shall be paid to all employees performing in the classification from the first day on which contract work is performed by them in the classification. Failure to pay the unlisted employees the compensation agreed upon by the interested parties and/or finally determined by the Wage and Hour Division retroactive to the date such class of employees commenced contract work shall be a violation of the Act and this contract.
(vi) Upon discovery of failure to comply with paragraph (c)(2) of this clause, the Wage and Hour
Division shall make a final determination of conformed classification, wage rate, and/or fringe benefits which shall be retroactive to the date such class or classes of employees commenced contract work.
(3) Adjustment of compensation. If the term of this contract is more than 1 year, the minimum monetary wages and fringe benefits required to be paid or furnished thereunder to service employees under this contract shall be subject to adjustment after 1 year and not less often than once every 2 years, under wage determinations issued by the Wage and Hour Division.
(d) Obligation to furnish fringe benefits. The Contractor or subcontractor may discharge the obligation to furnish fringe benefits specified in the attachment or determined under paragraph
(c)(2) of this clause by furnishing equivalent combinations of bona fide fringe benefits, or by making equivalent or differential cash payments, only in accordance with Subpart D of 29 CFR
Part 4.
(e) Minimum wage. In the absence of a minimum wage attachment for this contract, neither the
Contractor nor any subcontractor under this contract shall pay any person performing work under this contract (regardless of whether the person is a service employee) less than the minimum wage specified by section 6(a)(1) of the Fair Labor Standards Act of 1938. Nothing in this clause shall relieve the Contractor or any subcontractor of any other obligation under law or contract for payment of a higher wage to any employee.
(f) Successor contracts. If this contract succeeds a contract subject to the Act under which substantially the same services were furnished in the same locality and service employees were paid wages and fringe benefits provided for in a collective bargaining agreement, in the absence of the minimum wage attachment for this contract setting forth such collectively bargained wage rates and fringe benefits, neither the Contractor nor any subcontractor under this contract shall pay any service employee performing any of the contract work (regardless of whether or not such employee was employed under the predecessor contract), less than the wages and fringe benefits provided for in such collective bargaining agreement, to which such employee would have been entitled if employed under the predecessor contract, including accrued wages and fringe benefits and any prospective increases in wages and fringe benefits provided for under such agreement. No Contractor or subcontractor under this contract may be relieved of the foregoing obligation unless the limitations of 29 CFR 4.1b(b) apply or unless the Secretary of
Labor or the Secretary’s authorized representative finds, after a hearing as provided in 29 CFR
4.10 that the wages and/or fringe benefits provided for in such agreement are substantially at variance with those which prevail for services of a character similar in the locality, or determines, as provided in 29 CFR 4.11, that the collective bargaining agreement applicable to service employees employed under the predecessor contract was not entered into as a result of arm’s length negotiations. Where it is found in accordance with the review procedures provided in 29 CFR 4.10 and/or 4.11 and Parts 6 and 8 that some or all of the wages and/or fringe benefits contained in a predecessor Contractor’s collective bargaining agreement are substantially at variance with those which prevail for services of a character similar in the locality, and/or that the collective bargaining agreement applicable to service employees employed under the predecessor contract was not entered into as a result of arm’s length negotiations, the Department will issue a new or revised wage determination setting forth the applicable wage rates and fringe benefits. Such determination shall be made part of the contract or subcontract, in accordance with the decision of the Administrator, the Administrative Law Judge, or the Administrative
Review Board, as the case may be, irrespective of whether such issuance occurs prior to or after the award of a contract or subcontract (53 Comp. Gen. 401 (1973)). In the case of a wage determination issued solely as a result of a finding of substantial variance, such determination shall be effective as of the date of the final administrative decision.
(g) Notification to employees. The Contractor and any subcontractor under this contract shall notify each service employee commencing work on this contract of the minimum monetary wage and any fringe benefits required to be paid pursuant to this contract, or shall post the wage determination attached to this contract. The poster provided by the Department of Labor
(Publication WH 1313) shall be posted in a prominent and accessible place at the worksite.
Failure to comply with this requirement is a violation of section 2(a)(4) of the Act and of this contract.
(h) Safe and sanitary working conditions. The Contractor or subcontractor shall not permit any part of the services called for by this contract to be performed in buildings or surroundings or under working conditions provided by or under the control or supervision of the Contractor or subcontractor which are unsanitary, hazardous, or dangerous to the health or safety of the service employees. The Contractor or subcontractor shall comply with the safety and health standards applied under 29 CFR Part 1925.
(i) Records.
(1) The Contractor and each subcontractor performing work subject to the Act shall make and maintain for 3 years from the completion of the work, and make them available for inspection and transcription by authorized representatives of the Wage and Hour Division, Employment
Standards Administration, a record of the following:
(i) For each employee subject to the Act—
(A) Name and address and social security number;
(B) Correct work classification or classifications, rate or rates of monetary wages paid and fringe benefits provided, rate or rates of payments in lieu of fringe benefits, and total daily and weekly compensation;
(C) Daily and weekly hours worked by each employee; and
(D) Any deductions, rebates, or refunds from the total daily or weekly compensation of each employee.
(ii) For those classes of service employees not included in any wage determination attached to this contract, wage rates or fringe benefits determined by the interested parties or by the
Administrator or authorized representative under the terms of paragraph (c) of this clause. A copy of the report required by subdivision (c)(2)(ii) of this clause will fulfill this requirement.
(iii) Any list of the predecessor Contractor’s employees which had been furnished to the
Contractor as prescribed by paragraph (n) of this clause.
(2) The Contractor shall also make available a copy of this contract for inspection or transcription by authorized representatives of the Wage and Hour Division.
(3) Failure to make and maintain or to make available these records for inspection and transcription shall be a violation of the regulations and this contract, and in the case of failure to produce these records, the Contracting Officer, upon direction of the Department of Labor and notification to the Contractor, shall take action to cause suspension of any further payment or advance of funds until the violation ceases.
(4) The Contractor shall permit authorized representatives of the Wage and Hour Division to conduct interviews with employees at the worksite during normal working hours.
(j) Pay periods. The Contractor shall unconditionally pay to each employee subject to the Act all wages due free and clear and without subsequent deduction (except as otherwise provided by law or regulations, 29 CFR Part 4), rebate, or kickback on any account. These payments shall be made no later than one pay period following the end of the regular pay period in which the wages were earned or accrued. A pay period under this Act may not be of any duration longer than semi-monthly.
(k) Withholding of payments and termination of contract. The Contracting Officer shall withhold or cause to be withheld from the Government Prime Contractor under this or any other
Government contract with the Prime Contractor such sums as an appropriate official of the
Department of Labor requests or such sums as the Contracting Officer decides may be necessary to pay underpaid employees employed by the Contractor or subcontractor. In the event of failure to pay any employees subject to the Act all or part of the wages or fringe benefits due under the
Act, the Contracting Officer may, after authorization or by direction of the Department of Labor and written notification to the Contractor, take action to cause suspension of any further payment or advance of funds until such violations have ceased. Additionally, any failure to comply with the requirements of this clause may be grounds for termination of the right to proceed with the contract work. In such event, the Government may enter into other contracts or arrangements for completion of the work, charging the Contractor in default with any additional cost.
(l) Subcontracts. The Contractor agrees to insert this clause in all subcontracts subject to the Act.
(m) Collective bargaining agreements applicable to service employees. If wages to be paid or fringe benefits to be furnished any service employees employed by the Government Prime
Contractor or any subcontractor under the contract are provided for in a collective bargaining agreement which is or will be effective during any period in which the contract is being performed, the Government Prime Contractor shall report such fact to the Contracting Officer, together with full information as to the application and accrual of such wages and fringe benefits, including any prospective increases, to service employees engaged in work on the contract, and a copy of the collective bargaining agreement. Such report shall be made upon commencing performance of the contract, in the case of collective bargaining agreements effective at such time, and in the case of such agreements or provisions or amendments thereof effective at a later time during the period of contract performance such agreements shall be reported promptly after negotiation thereof.
(n) Seniority list. Not less than 10 days prior to completion of any contract being performed at a
Federal facility where service employees may be retained in the performance of the succeeding contract and subject to a wage determination which contains vacation or other benefit provisions based upon length of service with a Contractor (predecessor) or successor (29 CFR 4.173), the incumbent Prime Contractor shall furnish the Contracting Officer a certified list of the names of all service employees on the Contractor’s or subcontractor’s payroll during the last month of contract performance. Such list shall also contain anniversary dates of employment on the contract either with the current or predecessor Contractors of each such service employee. The
Contracting Officer shall turn over such list to the successor Contractor at the commencement of the succeeding contract.
(o) Rulings and interpretations. Rulings and interpretations of the Act are contained in
Regulations, 29 CFR Part 4.
(p) Contractor’s certification.
(1) By entering into this contract, the Contractor (and officials thereof) certifies that neither it
(nor he or she) nor any person or firm who has a substantial interest in the Contractor’s firm is a person or firm ineligible to be awarded Government contracts by virtue of the sanctions imposed under section 5 of the Act.
(2) No part of this contract shall be subcontracted to any person or firm ineligible for award of a
Government contract under section 5 of the Act.
(3) The penalty for making false statements is prescribed in the U.S. Criminal Code, 18 U.S.C.
1001.
(q) Variations, tolerances, and exemptions involving employment. Notwithstanding any of the provisions in paragraphs (b) through (o) of this clause, the following employees may be employed in accordance with the following variations, tolerances, and exemptions, which the
Secretary of Labor, pursuant to section 4(b) of the Act prior to its amendment by Pub. L. 92-473, found to be necessary and proper in the public interest or to avoid serious impairment of the conduct of Government business:
(1) Apprentices, student-learners, and workers whose earning capacity is impaired by age, physical or mental deficiency, or injury may be employed at wages lower than the minimum wages otherwise required by section 2(a)(1) or 2(b)(1) of the Act without diminishing any fringe benefits or cash payments in lieu thereof required under section 2(a)(2) of the Act, in accordance with the conditions and procedures prescribed for the employment of apprentices, student-learners, handicapped persons, and handicapped clients of sheltered workshops under section 14 of the Fair Labor Standards Act of 1938, in the regulations issued by the Administrator (29 CFR parts 520, 521, 524, and 525).
(2) The Administrator will issue certificates under the Act for the employment of apprentices, student-learners, handicapped persons, or handicapped clients of sheltered workshops not subject to the Fair Labor Standards Act of 1938, or subject to different minimum rates of pay under the two acts, authorizing appropriate rates of minimum wages (but without changing requirements concerning fringe benefits or supplementary cash payments in lieu thereof), applying procedures prescribed by the applicable regulations issued under the Fair Labor Standards Act of 1938 (29
CFR parts 520, 521, 524, and 525).
(3) The Administrator will also withdraw, annul, or cancel such certificates in accordance with the regulations in 29 CFR parts 525 and 528.
(r) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work they perform when they are employed and individually registered in a bona fide apprenticeship program registered with a State Apprenticeship Agency which is recognized by the U.S. Department of Labor, or if no such recognized agency exists in a State, under a program registered with the Office of Apprenticeship Training, Employer, and Labor Services
(OATELS), U.S. Department of Labor. Any employee who is not registered as an apprentice in an approved program shall be paid the wage rate and fringe benefits contained in the applicable wage determination for the journeyman classification of work actually performed. The wage rates paid apprentices shall not be less than the wage rate for their level of progress set forth in the registered program, expressed as the appropriate percentage of the journeyman’s rate contained in the applicable wage determination. The allowable ratio of apprentices to journeymen employed on the contract work in any craft classification shall not be greater than the ratio permitted to the Contractor as to his entire work force under the registered program.
(s) Tips. An employee engaged in an occupation in which the employee customarily and regularly receives more than $30 a month in tips may have the amount of these tips credited by the employer against the minimum wage required by section 2(a)(1) or section 2(b)(1) of the Act, in accordance with section 3(m) of the Fair Labor Standards Act and Regulations, 29 CFR Part
531. However, the amount of credit shall not exceed $1.34 per hour beginning January 1, 1981.
To use this provision—
(1) The employer must inform tipped employees about this tip credit allowance before the credit is utilized;
(2) The employees must be allowed to retain all tips (individually or through a pooling arrangement and regardless of whether the employer elects to take a credit for tips received);
(3) The employer must be able to show by records that the employee receives at least the applicable Service Contract Act minimum wage through the combination of direct wages and tip credit; and
(4) The use of such tip credit must have been permitted under any predecessor collective bargaining agreement applicable by virtue of section 4(c) of the Act.
(t) Disputes concerning labor standards. The U.S. Department of Labor has set forth in 29 CFR parts 4, 6, and 8 procedures for resolving disputes concerning labor standards requirements. Such disputes shall be resolved in accordance with those procedures and not the Disputes clause of this contract. Disputes within the meaning of this clause include disputes between the Contractor