Contract Att6 - Draft Template - Test Readiness Notification.docx
DOCX document 59 KB Posted
- Solicitation number
- 70T04020R9AP4052
About this file
This document is a test readiness notification template for checked baggage screening equipment deployment services. It outlines the tests and results that are required to be conducted and reported for a system technical readiness review, including a system mixed/die-back bag test, system throughput test, and test of compliance with the screening standard operating procedures. Key details covered include the airport and terminal location, bag room and node designations, equipment types and quantities, throughput requirements, and variances from standard procedures that were accepted. It also provides sections to document observations, performance issues, anomalies, and the results of individual tests run during the technical readiness review.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SENSITIVE SECURITY INFORMATION
IDIQ Number, TO number
TEST READINESS NOTIFICATION (TRN)
TO:
CC:
FROM:
DATE:
Airport:
Terminal(s) Designation:
Bag room/Node Designation:
CB SEDS TRR/Site Lead:
Cell Phone:
E-mail:
Recommendation:
|_| Proceed with ISAT |_| Do not proceed with ISAT
| Comments: |
| . |
| CB SEDS Site Lead obtained a copy of the CBIS’s final Programmable Logic Controller (PLC) code at END of TRR. |
| |_| Yes |
|_| No
| PGDS version for CBIS testing: |
| |_| 4.1 |
|_| 4.2 |_| 5.0 |_| 6.0 |_| Other (Please specify)
System Type:
|_|Mini In-Line |_| Medium Volume |_| High Volume
System Concept:
EDS Type(s):
EDS Quantity:
Design Throughput Requirement (BPH):
BMTT Setting:
GOVT Setting:
TTL Setting:
Planned CBIS ISAT Start Date: (By bag room)
Planned CBIS ISAT Finish Date: (by bag room)
TSA Accepted variances, if any, to the PGDS (attach documentation)
Time/Date Restrictions: (if other than M-F normal shift) (by bag room)
Physical Constraints (if any, by bag room):
I.e.: cutovers, access to ticket counters, overhead work, etc.)
Labor Constraints:
Date Received (Battelle):
Table 1
| RFV/CCR Number/Subject |
| Referenced PGDS Section |
| Approval Status |
OBSERVATIONS, PERFORMANCE ISSUES, and NOTES
1) Reported Results and Performance Issues:
2) List any anomalies or unique conditions:
3) Issues with safety and/or operations:
Figure 1
XXX TRR Test Results Summary
Tests are listed below per PGDS v.6 Appendix D for XXX. Tests conducted for TRR are noted as Yes or No, with explanation for any failed tests provided below.
| # |
| Test Date |
| Test |
| Line |
| Zone |
| Point of Manipulation |
| Manipulated Bag/Comments |
| # of Bags |
| Sequence |
| Complete? |
Pass-No deficiencies/defects
Pass- Minor deficiencies/defects
Fail
Introductory and Detailed Test Notes
Miscellaneous Notes:
Failed Tests:
Miscellaneous Notes:
Other Observations:
System Mixed/Die-Back Bag Test Summary
| Test Name/Iteration |
| BHS Lines – EDS Serial # |
| Result – Data |
System Mixed/Die-Back Bag Test
BHS Lines:
EDS Serial #s:
Bag Induction Points:
Bag Removal Location(s):
Total Bags Inducted:
Total Bags at CBRA:
CBRA Arrivals:
Suspect Bags:
0.0%
OOG Bags:
0.0%
EDS Error Bags:
0.0%
BHS Unknown Bags:
0.0%
Clear Bags
0.0%
| System Secure: |
| |_| Yes |
| |_| No |
| Number of Suspect Bags & Images Match: |
| |_| Yes |
| |_| No |
Fail-Safe Event Rate:
Criteria <= 0.5%
| 0 |
| 0.0% |
Invalid Arrival Rate:
Criteria <=3%
| 0 |
| 0.0% |
Bag Jam Event Rate - pre-EDS:
Criteria <= 1%
| 0 |
| 0.0% |
| Bag Jam Event Rate - Overall: Criteria = N/A |
| 0 |
| 0.0% |
Laser Read Rate:
Criteria >= 98% 0.0%
RFID Read Rate:
Criteria >= 99% N/A
Upstream Tracking Rate:
Criteria >= 97% (Average of spur lines) 0.0%
Pass/Fail:
System Mixed Test Notes
Miscellaneous Notes:
System Throughput Test Summary
| Test Name/Iteration |
| BHS Lines – EDS Serial # |
| Result – Data |
System Throughput Test
BHS Lines:
EDS Serial #s:
Bag Induction Points:
Bag Removal Location(s):
Total Bags Inducted:
0.0%
Total Bags at CBRA:
0.0%
Valid CBRA Arrivals:
Suspect Bags:
0.0%
OOG Bags:
0.0%
EDS Unknown Bags:
0.0%
BHS Unknown Bags
0.0%
| System Secure: |
| |_| Yes |
| |_| No |
| Number of Suspect Bags & Images Match: |
| |_| Yes |
| |_| No |
Fail-Safe Event Rate:
Criteria <= 0.5%
| 0 |
| 0.0% |
Invalid Arrival Rate:
Criteria <= 3%
| 0 |
| 0.0% |
| Bag Jam Event Rate - pre-EDS: Criteria <= 1% |
| 0 |
| 0.0% |
| Bag Jam Event Rate - Overall: Criteria = N/A |
| 0 |
| 0.0% |
Laser Read Rate:
Criteria >= 98% 0.0%
RFID Read Rate:
Criteria >= 99% N/A
Upstream Tracking Rate:
Criteria >= 97% (Average of spur lines) 0%
| Number of Minutes (Minutes) |
| 00:00 |
| Throughput Observed (BPH) (5 Minute Peak) |
| 0000 |
Pass/Fail:
System Throughput Test Notes
Miscellaneous Notes:
- 1 -
WARNING: THIS RECORD CONTAINS SENSITIVE SECURITY INFORMATION THAT IS CONTROLLED UNDER 49 CFR PARTS 15 AND 1520. NO PART OF THIS RECORD MAY BE DISCLOSED TO PERSONS WITHOUT A “NEED TO KNOW”, AS DEFINED IN 49 CFR PARTS 15 AND 1520, EXCEPT WITH THE WRITTEN PERMISSION OF THE ADMINISTRATOR OF THE TRANSPORTATION SECURITY ADMINISTRATION OR THE SECRETARY OF TRANSPORTATION. UNAUTHORIZED RELEASE MAY RESULT IN CIVIL PENALTY OR OTHER ACTION. FOR U.S. GOVERNMENT AGENCIES, PUBLIC DISCLOSURE IS GOVERNED BY 5 U.S.C. 552 AND 49 CFR PARTS 15 AND 1520.TRN Form Rev 01 – 11/04/15