CN-550000-CAT42-W0030000.pdf

PDF 252 KB Posted

Attached to
Master Agreement FL|CAT42|abb46c6807b72da2db8caf6da1266d7b
Contract number
CAT42
Issued by
Florida

About this file

This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT) for District 3, specifically a Continuing Services Design Consultant contract with Alday-Howell Engineering, Inc. The contract is for Task Work Order No. 3, associated with Contract No. CAT42, focusing on a sidewalk design project in Liberty County, Florida.

The project involves designing approximately 0.42 miles of six-foot concrete sidewalk along Theo Jacobs Way, CR 12, and Michaux Road, connecting the Bristol Library to Veterans Park. The total contract value is $296,839.00, broken down into $233,321.00 for Basic Services (paid as a lump sum based on percentage of completion) and $63,518.00 for Survey Services (paid at loaded billing rates). The project is designated as a Community Awareness Plan (CAP) Level 1 project, with no public meetings required. The sidewalk will be constructed along existing roadways with no additional right-of-way needed, and the project is located on a designated Hurricane Evacuation Route with posted speed limits of 45 mph on CR 12 and 35 mph on Michaux Road. The contract is set to be completed by 3/31/2026.

View the file

Other files

File Type Posted
CN-550000-ARY07-S0080000.pdf PDF
CN-550000-CAT42-W0030100.pdf PDF
CN-550000-CAT42-W0060000.pdf PDF
CN-550000-CAT42-W0010000.pdf PDF
CN-550000-CAT42-W0020000.pdf PDF
CN-550000-CAT42-W0020100.pdf PDF
CN-550000-CAT42-W0050000.pdf PDF
ContractBudgetExport.csv CSV file
CN-550000-CAT42-W0040000.pdf PDF
CN-550000-CAT42-00020000.pdf PDF
CN-550000-CAT42.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

3/31/2026

*Limiting or Estimating/Budgeted Amount.

Distribution:

Task Work Order No.:

Contract No.: Payment FM No.:

CAT42 45523513201

$925,613.00

(name) (title) Signature

Jason D. Peters, P.E. Director of Transportation Operations

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

(LS2) Lump sum paid based on % of completion

(LA4) Units worked at loaded billing rates in Table 6

Page 1 Total

Page 2 thru 6 Subtotal

Total

Basic Services (LS)

Alday-Howell Engineering, Inc.

3017 Highway 71 North, Marianna, Florida 32446

(To be entered upon execution of T.W.O.)

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$296,839.00

$233,321.00 Limit

Survey Services (LA4) $63,518.00 Limit

Signature

PM, Consultant, FS, PSU A. Goines

Vice President

$296,839.00

$0.00

(name) (title)

Travis Howell, P.E.

$296,839.00

Encumber by Task

Total authorizations to date (including this one):

Departmental Approval:

Consultant Acceptance:

Brief Task Description:

Continuing Services Design Consultant- Veterans Park Sidewalk from the Bristol Library to Veterans Park in Liberty County, Scope of Services attached.

F.A.P No. D325 002 B

Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

11/6/2024

October 17, 2024

CONSULTANT SCOPE OF WORK

FDOT District 3

Continuing Services Design Consultant

Alday-Howell Engineering, Inc.

(Contract # C-AT42/FPID # 418439-4-32-03)

FPID 455235-1-32-01 (Task Work Order # 3)

VETERANS PARK SIDEWALK FROM THE BRISTOL LIBRARY

TO VETERANS PARK

Section # 56020000, MP 20.106 to MP 20.278 (CR 12)

Section # 56601000, MP 0.000 to MP 0.081 (Michaux Road)

Section # 56900013, MP 0.000 to MP 0.163 (Theo Jacobs Way)

LIBERTY COUNTY

Purpose

This task work order primarily consists of the design of approximately 0.42 miles of six-foot (6’) concrete sidewalk in Liberty County. The proposed sidewalk will be constructed along the north side of Theo Jacobs Way, from CR 12 to Veterans Memorial Park, along the east side of CR 12, from Theo Jacobs Way to Michaux Road, and along the south side of Michaux Road from CR 12 to Harrell Memorial Library. The typical section consists of two-lane roadways with unpaved shoulders. The right-of-way varies for each roadway. No additional right-of-way will be required.

CR 12 has been designated as a “Hurricane Evacuation Route”.

The posted (justified) speed limit is 45 mph along CR 12 and 35 mph along Michaux Road. There is no assigned speed limit for Theo Jacobs Way. Therefore, an assumed speed limit of 35 mph will be applied. Appropriate design speeds will be determined during design.

This project shall be designed per applicable sections of the Continuing Services Design Consultant

Contract C-AT42, this specific scope of work, and as made known by the DEPARTMENT.

Coordination Requirements

This project should be coordinated with all adjacent County, State or private projects, although none have been identified at this time.

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

Features installed on COUNTY R/W by non-FDOT/COUNTY, private entities should be considered by the CONSULTANT as they related to potential impacts. This construction activities of this project may encounter landscaping, irrigation, signs, mailboxes, etc. The construction plans must address the course of action for coordination of any impacts to these features.

Public Involvement

This project has been determined to be a Community Awareness Plan (CAP) Level 1 project. For CAP Level 1 projects, a brief plan must be developed for documentation purposes (see Section

3.1.1 of the Continuing Services Design Consultant Contract C-AT42). Public Information Meetings/Workshops are not required for CAP Level 1 projects.

Development of Community Awareness Plan (CAP): The CONSULTANT shall prepare a Community Awareness Plan (CAP) for review and approval by the DEPARTMENT within 30 calendar days after receiving Notice to Proceed. The objective of the plan is to notify local governments, affected property owners, tenants, and the public of the DEPARTMENT’S proposed construction and the anticipated impact of that construction. The CAP shall address timeframes for each review and shall include tentative dates for each public involvement requirement for the project. The CAP will also document all public involvement activities conducted throughout the project’s duration. In addition to the benefits of advance notification, the process should allow the DEPARTMENT to resolve controversial issues during the design phase. Four areas of specific concern are: (1) Influences on access to businesses and residences, (2) Drainage, (3) Maintenance of Traffic during construction, and (4) right-of-way acquisition.

The CONSULTANT shall prepare an email notification and a distribution list for plans at Phase II, Phase III, and any subsequent Phase IV re-submittal to the office(s) designated by the local government(s) and applicable regional authorities for a three-week review. The email notifications and plans will be distributed by the DEPARTMENT. The need to re-submit Phase IV Plans will depend on the duration of time spent “on the shelf” and the number of changes that have occurred since the last submittal to the Local Governments at Phase III. See Section 2.19 of contract C- AT42 regarding Phase IV re-submittals. The Phase IV re-submittal to the Local Governments should take place well in advance of the Final Submittal to the District for Plans Processing to allow time to address comments received from the Local Governments.

Each comment or request provided by the local government shall be evaluated by the CONSULTANT and discussed with the DEPARTMENT’s Design Project Manager. Responses will be prepared by the CONSULTANT for the District Consultant Project Management Engineer’s signature. All comments or requests shall be responded to in writing within thirty (30) calendar days of receipt of comments.

Specific Design Considerations

The CONSULTANT shall coordinate with all DEPARTMENT functional areas as plans are being developed to ensure input and compliance to the Scope of Services.

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

• Roadway

The CONSULTANT shall provide sidewalk construction plans as per sections 4 and 5 of contract C-AT42.

The CONSULTANT shall provide a fully electronic signed and sealed set of plans for letting. Deliverables must be developed in the correct format as required by the FDOT

CADD Manual and the CADD Criteria Handbook.

The CONSULTANT shall provide a TCP Level 1 and will provide a Lane Closure Analysis.

• Drainage

All work shall comply with the requirements of the appropriate regulatory agencies and the

DEPARTMENT’s Drainage Manual.

Minimal drainage improvements are anticipated including construction of mitered end sections, repairing, reconstructing, or adjusting stormsewer inlets where impacted by the project.

The CONSULTANT shall inspect all drainage structures for function, scour, erosion, structural integrity, accumulation of sediments, and design as it pertains to pedestrian and vehicular safety. Drainage design treatments should be discussed with the Design Project

Manager and the District Drainage Office before being added to the construction plans.

• Utility Coordination

The DEPARTMENT shall be responsible for all utility coordination associated with this project. The CONSULTANT shall coordinate with the DEPARTMENT’s Area Utility

Manager, as required in section 7 of contract scope of services for C-AT42.

• Permits

The CONSULTANT shall be responsible for the identification, coordination, and applications for any permits necessary to construct this project. A permit exemption is anticipated.

• Structures

N/A - There will be no structural work included in this task work order.

• Signing and Pavement Markings

The CONSULTANT shall prepare signing and pavement marking plans per section 19 and

20 of contract C-AT42.

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

• Signalization

N/A - No signalized intersections exist within the project limits and there will be no signal work included in this task work order.

• Lighting

The CONSULTANT shall analyze and design pedestrian lighting at proposed mid-block crossings. The lighting component of this project may be prepared as a separate deliverable and executed as a JPA Roadway Illumination Services Agreement with the power provider. The DEPARTMENT will prepare and execute these agreements. The

CONSULTANT will be expected to provide input and plan sheets as necessary for the agreements.

• Landscaping

N/A – There will be no landscaping work included in this task work order.

• Survey

The Primary and Secondary Horizontal and Vertical control as well as the Design Survey will be provided by the CONSULTANT. CONSULTANT will provide a baseline of survey along the roadway centerline along with reference points and topographic information for the EOR to create a set of design plans.

The CONSULTANT will locate all above ground features and improvements for the limits of the project by collecting the required data for the purpose of creating a DTM with sufficient density. Shoot all break lines, high and low points. Effort includes field edits, analysis and processing of all field collected data, existing maps, and/or reports.

• Right-of-Way Mapping

N/A - No Right-of-Way Mapping efforts will be included in this task work order.

• Geotechnical

N/A - No Geotechnical design efforts will be included in this task work order.

• Specification Package

The CONSULTANT shall prepare and provide a complete electronic specifications package, including applicable Technical Special Provisions, for all items and areas of work as per section 3.3 of contract C-AT42.

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

• 3D Design

The CONSULTANT shall provide a 3D design and model to facilitate Automated Machine

Guidance in construction.

Project Schedule

Within ten (10) days after the Notice-To-Proceed, and prior to the CONSULTANT beginning work, the CONSULTANT shall provide a detailed project activity/event schedule with actual dates and

Department activity/event numbers for DEPARTMENT and CONSULTANT scheduled activities required to meet the current DEPARTMENT Production Date. The schedule shall be based upon the durations and schedule negotiated during the project staff hour negotiations process. For the purpose of scheduling, the CONSULTANT shall allow for a three-week review time for each phase review and other submittals as appropriate.

The schedule shall indicate, at minimum, proposed dates for Phase II, III, and IV plans and all other appropriate milestones and required submittals.

All fees and price proposals are to be based on the negotiated schedule of 16 months for final plans production.

Submittals

The CONSULTANT shall furnish construction contract documents as required by the DEPARTMENT to adequately control, coordinate, and approve the work concepts. The CONSULTANT shall distribute submittals as directed by the DEPARTMENT.

The DEPARTMENT’s Electronic Review and Comment (ERC) system will be used for project reviews. Upon Notice to Proceed, the DEPARTMENT’s Design Project Manager will coordinate with the CONSULTANT to provide the required access into the ERC system.

Phase Submittal Delivery: The delivery will include ONLY the submittal components (not the entire project directory and files). The delivery will be transmitted to the DEPARTMENT’s Design Project Manager via ftp site, FTA, or other electronic file storage media and will include all construction plans components (roadway, signing & pavement marking, signalization, etc.) in *.pdf format, as well as the other submittal components described below for each submittal. The CONSULTANT shall provide a *.kmz file of the project with each submittal. The *.kmz file needs to include the layers necessary to compare proposed construction features with the existing utilities as well as the limits of construction (LOC) and right-of-way (R/W).

PRIOR TO PHASE I SUBMITTAL:

UAO Identification / Sunshine 811 “Design” Ticket: A copy of the Sunshine 811 “design” ticket listing all utility owners within the project limits shall be transmitted to the Design Project Manager and the Area Utility Manager at the onset of the design survey effort. The ticket shall be included with all phase submittals. See Section 7.2 of the Continuing Services Design Consultant Contract

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

C-AT42 for additional information regarding this requirement.

Quality Assurance/ Quality Control (QA/QC) Plan: The CONSULTANT shall submit their QA/QC Plan that will be used during the design of this project to the DEPARTMENT’s Design Project Manager for reference within 20 (twenty) calendar days of the written Notice to Proceed.

As a minimum, the QA/QC Plan shall include the details of all plan review processes to be utilized and sufficient file documentation to show that the QA/QC plan has been followed. See Section 3.0 (Project Common Tasks) of the Continuing Services Design Consultant Contract C-AT42.

Miscellaneous Design/ Production Document Submittals: The CONSULTANT shall submit to the DEPARTMENT for review, and receive concurrence for, the Initial Project Schedule, Community Awareness Plan (CAP), Typical Section Package, Design Variations and/or Exceptions (if applicable), and other documents as required by the FDOT Design Manual (FDM) and the Scope of Services.

PHASE I:

The PHASE I submittal will NOT be entered into ERC for review.

At the time of Phase I (30%) plans, the CONSULTANT shall submit the construction cost estimate using the DEPARTMENT’s Long Range Estimating System (L.R.E.).

The District Preliminary Estimates Office will provide the CONSULTANT with a version of the L.R.E. in the system for their use.

PHASE II:

The CONSULTANT shall submit to the DEPARTMENT’s Design Project Manager for distribution:

▪ one (1) electronic copy of the Plans,

▪ one (1) electronic copy of the QC Marked-up Plans,

▪ one (1) electronic copy of any Technical Special Provision (if applicable)

The submittal shall, at a minimum, include *.pdf files of the components listed above, as well as the Project-DOCUMENTATION.zip folder (see FDM 111.7), *.kmz file of the project, Sunshine 811 “design” ticket, Utility Conflict Matrix, and a scanned copy of the Constructability Phase Review Checklist (per the Construction Project

Administration Manual (CPAM)).

Along with the Phase II plans submittal, the CONSULTANT shall submit the construction cost estimate using the DEPARTMENT’s Long Range Estimating System

(L.R.E.). The District Preliminary Estimates Office will provide the CONSULTANT with a version of the L.R.E. in the system for their use.

The CONSULTANT shall submit plans to each of the affected local government(s) designated contact for a three-week review. See Section 3.1.2 of of the Continuing

Services Design Consultant Contract C-AT42 for details regarding Local Government

Involvement.

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

PHASE III:

The CONSULTANT shall submit to the DEPARTMENT’s Design Project Manager for distribution:

▪ one (1) electronic copy of the Plans,

▪ one (1) electronic copy of the QC Marked-up Plans,

▪ one (1) electronic copy of the Estimated Quantities Report (EQR),

▪ one (1) electronic copy of any Technical Special Provision (if applicable)

▪ one (1) electronic copy of the CONSULTANT’s Construction Cost

Estimate,

▪ one (1) electronic copy of the CONSULTANT’s Contract Time Estimate, the project, Sunshine 811 “design” ticket, Utility Conflict Matrix, and a scanned copy of the Constructability Phase Review Checklist (per the Construction Project

Administration Manual (CPAM)).

The CONSULTANT shall submit plans to each of the affected local government(s) designated contact for a three-week review. See Section 3.1.2 of the Continuing

Services Design Consultant Contract C-AT42 for details regarding Local Government

Involvement.

PHASE IV:

The CONSULTANT shall submit to the DEPARTMENT’s Design Project Manager for distribution:

▪ one (1) electronic copy of the Plans,

▪ one (1) electronic copy of the QC Marked-up Plans,

▪ one (1) electronic copy of the Estimated Quantities Report (EQR),

▪ one (1) electronic copy of the CONSULTANT’s Construction Cost

Estimate,

▪ one (1) electronic copy of the CONSULTANT’s Contract Time Estimate, the project, Sunshine 811 “design” ticket, Utility Conflict Matrix, and a scanned copy of the Constructability Phase Review Checklist (per the Construction Project

Administration Manual (CPAM)).

SUBMITTAL FOR “THE SHELF”:

The CONSULTANT must submit a District 3 Change Memo to the District

Preliminary Estimates Office to have Project Preconstruction (PrP) unlocked if changes are made following the PHASE IV submittal that affect the pay-items or quantities in

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

PrP. A copy of the District 3 Change Memo can be obtained from the

DEPARTMENT’s Design Project Manager or the District Preliminary Estimates

Office.

Upon addressing the PHASE IV review comments, the CONSULTANT shall submit to the DEPARTMENT’s Design Project Manager the following in an electronic format via ftp site, FTA, or other electronic file storage media:

▪ PHASE IV Plans,

▪ PHASE IV QC Marked-up Plans,

▪ Project-DOCUMENTATION.zip folder,

▪ Engineer’s Construction Cost Estimate,

▪ CONSULTANT’s Contract Time Estimate,

▪ *.kmz file of the project,

▪ Sunshine 811 “design” ticket,

▪ Utility Conflict Matrix,

▪ Constructability Phase Review Checklist

The CONSULTANT shall transmit the applicable electronic project files to the

DEPARTMENT’s Area Utility Manager.

PHASE IV RE-SUBMITTAL:

If the project spends one (1) year or more “on the shelf” and/or substantial changes have been made during Plans Update to the plans, pay items, or quantities after the

Phase IV review, the CONSULTANT shall prepare a second Phase IV submittal. This submittal will include the requirements listed for Phase IV. This submittal will be made well in advance of the Final Submittal to the DEPARTMENT’s Plans Processing

Group. This will allow time to address comments in advance of the Final Submittal.

The DEPARTMENT’s Design Project Manager will determine whether the Phase IV re-submittal will include a distribution to the local governments. See Section 3.1.2 of of the Continuing Services Design Consultant Contract C-AT42 for details regarding

Local Government Involvement.

The CONSULTANT must submit a District 3 Change Memo to the District

Preliminary Estimates Office to have PrP unlocked if changes are made during Plans

Update that affect the pay-items or quantities in PrP. A copy of the District 3 Change

Memo can be obtained from the DEPARTMENT’s Design Project Manager or the

District Preliminary Estimates Office.

The CONSULTANT must submit an electronic copy of the Plans Update Memo to describe in general terms the changes made to each sheet since the project was

“shelved”. A copy of the Plans Update Memo can be obtained from the

DEPARTMENT’s Design Project Manager.

Any design changes affecting utilities that occur after the PHASE IV or PHASE IV

Resubmittal must be coordinated with the DEPARTMENT’s Design Project Manager

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE and submitted to the DEPARTMENT’s Area Utility Manager so that Utility Work

Schedules can be updated.

The effort to prepare a PHASE IV Re-Submittal will be negotiated as a part of the Plans

Update Services. See Section 3.7 of the Continuing Services Design Consultant

Contract C-AT42 for more information regarding Plans Update.

FINAL PLANS SUBMITTAL TO PLANS PROCESSING:

This submittal will occur upon addressing PHASE IV (or PHASE IV RE-

SUBMITTAL) comments or following the Plans Update phase and less than one (1) year spent “on the shelf”.

If changes are made to the plans after the PHASE IV review that affect the pay-items or quantities in PrP, the CONSULTANT must submit a District 3 Change Memo to the

District Preliminary Estimates Office to have PrP unlocked. A copy of the District 3

Change Memo can be obtained from the DEPARTMENT’s Design Project Manager or the District Preliminary Estimates Office.

The CONSULTANT must submit an electronic copy of the Plans Update Memo to describe in general terms the changes made to each sheet since the project was

“shelved”. A copy of the Plans Update Memo can be obtained from the

DEPARTMENT’s Design Project Manager.

Final Project Submittal to ERC: The CONSULTANT shall submit the following to the

DEPARTMENT’s Design Project Manager via ftp site, FTA, or other electronic file storage media to post to ERC for the District’s Plans Processing Group’s review:

• electronic *.pdf copy of each component of the final plans. The plans must be electronically sealed using the Digital Delivery method for the second and subsequent submittals. Not the first.

• electronic *.pdf copy of the Estimated Quantities Report (EQR). The report must be electronically sealed using the Digital Delivery Method for the second and subsequent submittals. Not the first.

• a complete Specifications Package including any Technical Special

Provisions and/or incentive/disincentive cost analyses and backup documentation (when necessary)

• the Project-DOCUMENTATION.zip folder

• the Project-BIM.zip folder with all project design files

• the Compliance Certification Checklist Report. This report shall be signed by the Engineer of Record to certify that all electronic deliverables are complete, in the proper format, and all plans and specifications are signed and sealed with the same program.

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

Any design changes since the previous submittal affecting utilities must be coordinated with the DEPARTMENT’s Design Project Manager and submitted to the

DEPARTMENT’s Area Utility Manager so that Utility Work Schedules can be updated.

The CONSULTANT will expeditiously address the comments received in ERC and be prepared to resubmit the final plans package once the review period in ERC is complete. A minimum of two (2) complete reviews using the ERC system will occur at this juncture, followed by subsequent Final Project CD/DVD submittals as necessary.

Final Project Submittal: The CONSULTANT shall submit the following to the

DEPARTMENT’s Design Project Manager via ftp site, FTA, or other electronic file storage media for the District’s Plans Processing Group’s review once the ERC reviews are complete:

• final plans electronically sealed using the Digital Delivery method

• final Estimated Quantities Report (EQR) electronically sealed using the

Digital Delivery Method

• a complete Specifications Package including any Technical Special

Provisions and/or incentive/disincentive cost analyses and backup documentation (when necessary)

• the Project-DOCUMENTATION.zip folder

• the Project-BIM.zip folder with all project design files

• the Compliance Certification Checklist Report. This report shall be signed by the Engineer of Record to certify that all electronic deliverables are complete, in the proper format, and all plans and specifications are signed and sealed with the same program.

• all project data and its location noted in the project journal.

Upon addressing all comments received during the Final Plans Processing review, the

CONSULTANT shall transmit electronic project files to the DEPARTMENT’s Area

Utility Manager as described in the requirements above.

Once all electronic project files have been finalized, the DEPARTMENT’s Design

Project Manager shall upload the Project-DOCUMENTATION.zip folder to Electronic

Document Management System (EDMS) or Project Suite Enterprise Edition (PSEE).

See FDM 111.7 for guidance on the organization and delivery of Project

Documentation.

Docusign Envelope ID: 5B3936E7-6B02-4959-B02F-E6FD6A8B05C6Docusign Envelope ID: 47AEF598-75FA-4AE1-8569-31836E8D12BE

File details come from the government source that posted it. Updated .