CN-370000-WQ179-T9.pdf
PDF 376 KB Posted
- Contract number
- HW510
- Issued by
- Florida
About this file
This is a Task Assignment (TA) document entered into by the State of Florida Department of Environmental Protection and SediVision, LLC. The task assignment is numbered 9 under Contract Number WQ179 and is effective through December 31, 2025. The Department's Project Manager is Michael Barr, and the Contractor's Project Manager is Denver J. Sutler, Jr. The work is designated for the Indian River County South Regional Wastewater Treatment Facility, located in Indian River County, Florida.
The contractor shall provide wastewater tank mapping and capacity loss estimation services for one Oxidation Ditch and one Secondary Anoxic Zone at the specified facility, with sediment sampling available upon request. The contractor must submit a mapping plan within 30 days of assignment, with the Department providing 10 days for review and approval. Following approval, the contractor has 10 days to begin the mapping process and 90 days from completion to deliver a map showing debris location and calculations of volume-proportioning amounts and capacity loss as a percentage. The total task assignment value is $29,200.00 on a cost reimbursement basis, funded through Organizational Code 37220200000 with appropriation category 143276 and project number WQ179 for fiscal year 2024. No performance bonds, liquidated damages, retainage, or additional insurance are required. The Department reserves the right to reject deliverables and may assess penalties of 1% invoice reduction per day for timeline delays, unless the timeline is extended in writing by the Department.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A12-45936.pdf | ||
| A13-45942.pdf | ||
| A2-45715.pdf.crdownload | CRDOWNLOAD file | |
| A4-45718.pdf | ||
| A5-45726.pdf | ||
| A7-45741.pdf | ||
| CN-370000-HW510-TD28G.pdf | ||
| ContractVendorExport.csv | CSV file | |
| A3-45716.pdf | ||
| A9-45766.pdf | ||
| CN-370000-HW510-A14.pdf | ||
| CN-370000-HW510-CO004.pdf | ||
| CN-370000-HW510-TD06L.pdf | ||
| CN-370000-WQ179-T9CO1.pdf | ||
| ContractPaymentsExport.csv | CSV file | |
| FIL1-45709.pdf | ||
| FIL15-45923.pdf | ||
| FIL16-45925.pdf | ||
| A10-45921.pdf | ||
| A6-45736.pdf | ||
| CN-370000-CN804-T9.pdf | ||
| CN-370000-HW510-FIL20.pdf | ||
| CN-370000-WQ179-T8CO2.pdf | ||
| ContractDeliverablesExport.csv | CSV file | |
| FIL10-45739.pdf | ||
| FIL14-45762.pdf | ||
| FIL17-45927.pdf | ||
| A1-45705.pdf | ||
| A10-45921.pdf.crdownload | CRDOWNLOAD file | |
| A11-45932.pdf | ||
| A2-45715.pdf | ||
| A8-45746.pdf | ||
| CN-370000-HW510-CO001.pdf | ||
| CN-370000-HW510-CO002.pdf | ||
| CN-370000-HW510-CO003.pdf | ||
| CN-370000-WQ179.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| FIL11-45740.pdf | ||
| FIL12-45745.pdf | ||
| FIL13-45749.pdf |
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Digitally signed by Angela Knecht Date: 2025.04.28 14:56:54 -04'00'
Attachment 1, Page 1 of 2
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment (TA) No.: 9 Scope of Work
ATTACHMENT 1
1. Scope of Work.
The Contractor shall provide wastewater tanks due to accumulated debris at one (1) Oxidation Ditch and one (1) Secondary Anoxic Zone at the Indian River County South Regional Wastewater Treatment Facility. Sediment sampling may be included upon request from the public utility and written approval from the Department's Contract Manager.
2. Definitions.
In this Contract, the following terms shall be defined as set forth below:
a. Debris: Solid material (sand and grit) that accumulates at the bottom of wastewater tanks.
b. Publicly Owned Utilities: utilities owned by governmental entities or political subdivisions/public utility districts.
3. Contractor Responsibilities.
a. Tasks and timeline. Contractor will provide a mapping plan to the Department for each tank assigned within 30 days of assignment. The plan will include a price, estimated timeline and schedule of events. Once a plan is submitted, the Department will have ten (10) days to review and approve the plan. Once a plan is approved, Contractor may begin the mapping process in accordance with the agreed upon schedule.
Within ten (10) days of an approved plan, Contractor will use its scientifically-backed method of determining the amount of debris within an assigned tank and its loss of capacity according to the plan submitted to the Department.
b. Deliverables. Within 90 days of completion of the mapping process, Contractor will provide to the Department and the public utility:
i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved.
c. Performance Measures.
Manager, the Contractor may proceed with payment request submittal.
Maximum Budget for TA 9: $29,200.00
4. Department Responsibilities.
The before payment. If of receipt, they will be deemed rejected.
5. Enforcement.
The Department reserves the right to reject deliverables as incomplete, inadequate, or unacceptable due, in whole or
Contract. Failure to fulfill the
Attachment 1, Page 2 of 2 applicable technical requirements or complete all tasks or activities in accordance with the Scope of Work will result in rejection of the deliverable and the associated invoice. No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall: a. Re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within thirty (30) days of being notified of the unsatisfactory deliverable. b. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or Task Assignments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved; and/or 4) terminate the Contract for failure to perform. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
6. Additional Insurance Requirements.
None.
7. Payment and Performance Bonds.
There are no bonds required under this TA.
8. Liquidated Damages.
There are no liquidated damages under this TA.
9. Retainage.
No retainage is required under this TA.
10. Additional Terms.
None.