This document is a Task Assignment Change Order (TACO #7) issued by the State of Florida Department of Environmental Protection to Wildwood Consulting. The change order amends an existing Task Assignment (TA5) and is identified by Contract Number WQ150. The Department's Project Manager is Diana Turner, and the Contractor's Project Manager is Tiffany Busby, who serves as President of Wildwood Consulting.
The change order represents an increase in funding for the task assignment without modifications to the effort requirements or end date. The amended total Task Assignment value increases from $456,447.99 to $555,650.00, representing an additional allocation of $99,202.01. The compensation structure remains on a cost reimbursement basis. The funding is allocated through Appropriation Category 088964 under Project WQ150 (TMDL) for Fiscal Year 23, with the cost charged to Org. Code 3730301000, E.O. QK, and Object Code 131300. The change order was executed on August 14, 2025, and became effective on the same date. All other terms and conditions of the original Task Assignment remain in effect.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
TA5 7 WQ150
Increase in funds, action does not change the TA efforts nor end date
Diana Turner 850-245-8825 Wildwood Consulting
Tiffany Busby 904-797-2721
$ 555,650.00 $456,447.99
$ 555,650.00 $ 456,447.99
Wildwood Consulting
Tiffany Busby
President
8/14/2025
Tiffany L. Busby Digitally signed by Tiffany L. Busby Date: 2025.08.14 13:49:18 -04'00'
Adam Blalock
Adam Blalock Digitally signed by Adam Blalock Date: 2025.08.14 14:51:50 -04'00'
8/14/2025
3730301000 QK 131300 37300100 088964 TMDL WQ150 23 $ 99,202.01
File details come from the government source that posted it. Updated .