This document is a Task Assignment Change Order (TACO #4) issued by the State of Florida Department of Environmental Protection amending a task assignment with Wildwood Consulting, Inc. The change order increases funding for the existing contract while maintaining all other terms and conditions. Kevin Coyne serves as the Department's Project Manager, and Tiffany Busby, President of Wildwood Consulting, Inc., is the Contractor's Project Manager. The document was executed on February 10 and 16, 2021.
The change order modifies the compensation structure for Task Assignment #1, titled "Statewide Facilitation of Local Restoration Plan Efforts in Lieu of TMDLs & BMAPs/Statewide Support," increasing the total task assignment value from $492,371.70 to $676,921.14. This represents an increase of $184,549.44 in cost reimbursement funding. The work is performed on a cost reimbursement basis with no changes to the task assignment's completion date or attachments. The estimated budget reflects labor costs for multiple positions including Principal, Program Manager, Project Manager, and Scientists from both Wildwood Consulting and Tetra Tech, along with travel and other expenses, totaling 4,846.4 estimated hours. Funding is allocated from Appropriation Category 088964, Project WQ150, for Fiscal Year 19.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
TA1 4 WQ150
Increase in funds, action does not change the TA efforts nor end date
Kevin Coyne 850-245-8555 Contractor Wildwood Consulting, Inc. Contractor
Contractor Tiffany Busby Contractor 904-797-2721
✔ $ 676,921.14 $ 492,371.70
$ 676,921.14 $ 492,371.70 ✔ Expiration
Expiration 0
The only change to this TA is an increase in funding amounts and is summarized in the attachment to this TACO and corresponding FACTs Workbook.
Contractor Tiffany Busby
President, Wildwood Consulting, Inc.
Tiffany L. Busby Digitally signed by Tiffany L. Busby Date: 2021.02.10 14:57:38 -05'00' Julie Espy, Director Digitally signed by Julie Espy, Director
Date: 2021.02.16 13:43:41 -05'00'
3730301000 QK 131300 37300100 088964 NA WQ150 19 $ 184,549.44
Estimated Budget for Task Assignment #1 (Statewide Support) Execution - September 2021 Wildwood Consulting
Position Principal Program Manager
Project Manager Scientist I
Administrative Assistant
Senior Program Manager
Senior Project
Manager Scientist III Scientist I Hours Totals
Subtask Labor Totals
Travel Summary
Other Expenses
Subcont.
Handling
Fee Task Totals Rate 170.41$ 150.71$ 112.45$ 98.54$ 49.85$ 200.00$ 150.00$ 130.00$ 80.00$
Tasks Task 1: Statewide Facilitation of Local Restoration Plan Efforts in Lieu of TMDLs & BMAPs/Statewide Support Estimated Hours, By Position 1,840.0 522.4 1,436.0 496.0 144.0 24.0 144.0 120.0 120.0 4,846.4
TASK 1 TOTALS: 313,554.40$ 78,730.90$ 161,478.20$ 48,875.84$ 7,178.40$ 4,800.00$ 21,600.00$ 15,600.00$ 9,600.00$ 4,846.4 661,417.74$ 15,303.40$ 200.00$ -$ 676,921.14$
Wildwood Consulting Summary Items
Estimated Hours
Tetra Tech
Estimated Hours
File details come from the government source that posted it. Updated .