This is a Change Order No. 2 issued by the Florida Department of Environmental Protection (FDEP) for Task Assignment No. 3 under Contract No. DC796. The contract involves DRMP (Design, Review, and Management Professional Services) with vendor Bryant King for professional services related to the Marjorie Harris Carr Cross Florida Greenway project. The change order was executed by FDEP personnel including Michael Renard (Contract Manager, BDAC, FDEP) and representatives from Dyer, Riddle, Mills & Precourt, Inc., the consultant firm, with signatures dated October 19, 2009.
The change order extends the delivery schedule for the scope of work by providing an additional 60 days after issuance of permits and permits-related documents for tree survey and permit documentation services to be completed. The original task completion date was 90 days after execution of the Task Assignment, with deliverables due 60 days after construction completion; this amendment makes the new completion deadline 60 days from the issuance of permits and easements. The present task amount remains at $83,308.40 with no financial change to the contract. No encumbrance information or additional costs are associated with this change order, which addresses delays caused by permitting issues with the City of Dunnellon related to the trail system development project.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .