CN-370000-DC790-T15.pdf

PDF 1 MB Posted

Attached to
Master Agreement FL|DC790|0474ea1b477747a3498680d147aed680
Contract number
DC790
Issued by
Florida

About this file

Document Summary

This is a Consultant's Task Assignment Notification issued by the Florida Department of Environmental Protection (FDEP), Bureau of Design and Construction (BDC), for design services at Highlands Hammock State Park. The contract is awarded to Jones Edmunds & Associates, Inc., with contract number DC790, Task Assignment 15, and project number 60959. The project involves architectural and engineering design services for ADA restroom renovations at the Recreation Hall facility. The consultant's representative is Jamie Bell, and the FDEP contract manager is Katie Parrish, with project management oversight by Hubert Baxter.

The scope of work consists of four design service tasks: Existing Conditions Survey, Concept Design Development (30%), Design Development (90%), and Construction Documents Development (100%). The fixed price for design services totals $18,132.19, with a consultant subconsultant cost of $1,170.00 for environmental materials testing and analysis, and reimbursable expenses of $842.55, for a total task amount of $20,144.74. Payment is made upon completion and approval of each task deliverable. The project start date is upon execution, with a completion date aligned to the contract completion date. Cost reimbursement is not to exceed $842.55. The contract was executed in November 2014 with signatures from contract authority, contract managers, project manager, and budget representatives.

View the file

Other files

File Type Posted
CN-370000-DC790-A2.pdf PDF
CN-370000-DC790-T12.pdf PDF
CN-370000-DC790-T17.pdf PDF
CN-370000-DC790-T8.pdf PDF
CN-370000-DC790-TA5 CO3.pdf PDF
CN-370000-DC790-TA5 CO4.pdf PDF
CN-370000-DC790-TA5.pdf PDF
CN-370000-DC790-A1.pdf PDF
CN-370000-DC790-A3.pdf PDF
CN-370000-DC790-T10CO1.pdf PDF
CN-370000-DC790-T12CO1.pdf PDF
CN-370000-DC790-T13.pdf PDF
CN-370000-DC790-T9.pdf PDF
CN-370000-DC790-TA2.pdf PDF
CN-370000-DC790-T14.pdf PDF
CN-370000-DC790-T16.pdf PDF
CN-370000-DC790-T7.pdf PDF
CN-370000-DC790-TA3.pdf PDF
CN-370000-DC790.pdf PDF
CN-370000-DC790-T10.pdf PDF
CN-370000-DC790-T11.pdf PDF
CN-370000-DC790-T12CO2.pdf PDF
CN-370000-DC790-T14CO1.pdf PDF
CN-370000-DC790-T6.pdf PDF
CN-370000-DC790-T8CO1.pdf PDF
CN-370000-DC790-TA17CO01.pdf PDF
CN-370000-DC790-TA5 CO1.pdf PDF
CN-370000-DC790-TA5 CO2.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DC790, Task Assignment 15 Highlands Hammock State Park-Rec Hall ADA Restroom Renovation

PROPOSAL SUMMARY

Task 1 – Existing Conditions Survey Task 1 will include a Kickoff Meeting with BDC and Park staff to confirm project success factors and the Owner’s vision. The Kickoff Meeting will occur via teleconference and will be followed by an existing conditions survey site visit.

Deliverables:

1. Within 5 business days of the Kickoff Meeting with BDC and Park staff, submit via email to the BDC Project Manager a report of the meeting minute’s document in 8-1/2x11 pdf format.

2. At the completion of the Existing Conditions Survey, submit via email to the BDC Project Manager, documentation of the facility toilet rooms existing conditions in the area of the proposed modifications, including dimensioning of walls, fixtures, and equipment, etc. Documentation will include floor plan drawings as well as elevation drawings and photographs when appropriate, relevant to the proposed modifications. The existing conditions documents will be delivered to BDC in pdf and AutoCAD format.

The pdf size will be scaled to fit an 11-inch-x-17-inch format.

Performance Measures: The BDC project manager will review the submittals; verify the tasks were completed and received as per the proposed time schedule; was in a legible format; contains on-site investigations including drawings, photographs and a description of the existing conditions; and contained sufficient information to fully describe the existing conditions.

Fixed Price Cost: $4,423.40 Reimbursable Cost: $842.55 Total Task 1 Cost: $5,265.95

Task 2 – Concept Design Development (30%) Task 2 will include validation and development of schematic plan layouts for each toilet room provided by the BDC Project Manager and will include proposed modifications and/or options to meet the project design intent. This information will be documented at a conceptual design level and will be submitted in pdf format via email to the BDC Project Manager. The submittal will be discussed at a teleconference with BDC representatives and the design staff.

Deliverables:

1. Submit conceptual architectural floor plans for the facility’s two toilet rooms via e-mail to the BDC Project Manager for BDC review and comments. Conceptual plans will include proposed plan layouts of modified toilet rooms. One conceptual plan layout for each toilet room will be developed. The pdf size will be scaled to fit an 11-inch-x-17-inch format.

2. Within 5 days after the teleconferenced concept design review, submit via email to the BDC Project Manager a meeting minutes report in pdf format.

Performance Measures: The BDC project manager will review the submittal and verify that it was received as per the proposed time schedule; was in a legible format and contains sufficient information to fully describe the design concepts (30%).

Fixed Price Cost: $3,532.95

Task 3 – Design Development (90%) The Design Development Phase will involve designing to a 90% level of completion. Jones Edmunds will submit via e-mail to the BDC Project Manager a complete set of the 90% design documents for BDC review and comments. The documents will be formatted as 8-1/2-inch-x-11-inch pdf files except the drawings, which will be scale-formatted as 11-inch-x-17-inch pdf files. The submittal will be discussed at a teleconference with BDC representatives and the design staff.

Deliverables:

1. Submit to the BDC Design Development drawings in the BDC 24-inch-x-36-inch standard that will include the standard BDC border. The drawings will be scale formatted to 11-inch-x-17-inch pdf files and will consist of the following:

a) Cover sheet.

b) Abbreviations, legend, and general notes.

c) Existing conditions, photographs, and demolition plans.

d) Environmental notes and schedules.

DC790, Task Assignment 15 Highlands Hammock State Park-Rec Hall ADA Restroom Renovation

e) Architectural plans, elevations, sections, schedules, and details.

f) Mechanical plans, schedules, and details.

g) Plumbing plans, schedules, and details.

h) Electrical plans, schedules, and details.

NOTE: All drawings will be completed to a 90% level.

2. Submit to BDC draft technical specifications in CSI format for environmental, architectural, mechanical, plumbing, and electrical design in MS Word in the BDC 8-1/2-inch-x-11-inch standard format and delivered as pdf files.

3. Submit to BDC a Rough Order of Magnitude (ROM) Construction Cost Opinion in MS Excel format and pdf formats. The deliverable will be a written cost opinion containing line item descriptions, unit costs, quantities, line item totals, and aggregate totals.

4. Within 5 business days after the teleconferenced Design Development review meeting, submit via email to the BDC Project Manager a meeting minutes report in pdf format.

Performance Measures: The BDC project manager will review the submittal and verify that it was received as per the proposed time schedule; was in a legible format and contains sufficient information to fully describe the design development (90%).

Fixed Price Cost: $9,829.13

Task 4 – Construction Documents Development (100%) The Construction Document Phase will involve completing the design to a 100% level of completion. The deliverables will include incorporating previous design development comments. The documents will be completed, signed, and sealed for use in permit application submittals by others.

Deliverables

1. Submit to the BDC six sets of signed-and-sealed final Construction Document drawings (24-inch-x-36-inch dated drawing sheets) incorporating BDC and Park staff comments from the Design Development Phase submittal. Three sets will be provided for State Fire Marshal review, and three sets will be provided for the Contractor’s Building Department submittal. Drawing sheets will include the sheets listed in Design Development Phase.

2. Submit to the BDC three copies of final technical specifications for environmental, architectural, technical, plumbing, and electrical design elements.

3. Submit to the BDC three copies of a final ROM Construction Cost Opinion.

Performance Measures: The BDC project manager will review the submittal and verify that it was received as per the proposed time schedule; was in a legible format and contains sufficient information to fully describe the design development (90%).

Fixed Price Cost: $1,516.71

Payment: will be made upon the completion of each task/deliverable and submittal and approval by DEP of the task/deliverable for the amount specified for that deliverable.

Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.

95693-259-14 Page 1 October 23, 2014

October 23, 2014

Hubert Baxter, Architect Florida Department of Environmental Protection Carr Building 3800 Commonwealth Boulevard Tallahassee, Florida 32399

Dear Mr. Baxter:

RE: Highlands Hammock State Park – Recreation Hall Restrooms Renovation Project REVISED PROPOSAL: Design Services

Jones Edmunds & Associates, Inc. is pleased to present this revised proposal to provide design services to the Florida Department of Environmental Protection (FDEP) Bureau of Design and Construction (BDC) for improvements at Highlands Hammock State Park. The design involves renovations to restroom facilities within the Recreation Hall facility as follows:

1. Remodeling the existing Men’s and Women’s toilet rooms to provide accessibility in conformance with the Americans with Disabilities Act (ADA).

2. Removing existing plumbing fixtures and providing new fixtures.

3. Providing new toilet partitions.

4. Repairing and renovating existing finishes within the renovated areas.

5. Renovating adjacent nonstructural walls and framing to increase space for toilet rooms.

The project’s Scope of Services is based on discussions and email correspondence with BDC’s Project Manager on July 3, 2014. Background information provided by BDC includes a project meeting report dated December 11, 2013, and three record drawing sheets of the facility’s original design plans, elevations, and details. As discussed with the BDC Project Manager, the design will provide modifications within the existing building envelope, a change from the December 11, 2013, meeting report.

This revised proposal, in accordance with email correspondence and telephone discussions with BDC management on July 25, 2014, includes a reduced fee with fewer estimated hours, including reduced participation by the Senior Principal and Project Manager; project coordination will be handled primarily by the Project Architect. To support the reduced fee and

95693-259-14 Page 2 October 23, 2014 our interpretation of BDC’s intent for the project, we have modified our scope under Concept Design Development by limiting the submittal to developing one option—this option being the schematic drawings provided by BDC’s Project Manager earlier in the proposal phase of this project.

95693-259-14 Page 3 October 23, 2014

I. SCOPE OF SERVICES

The following tasks are proposed for this project:

• Task 1 – Existing Conditions Survey

• Task 2 – Concept Design Development

• Task 3 – Design Development

• Task 4 – Construction Document Development

A. Task 1 – Existing Conditions Survey

Task 1 will include a Kickoff Meeting with BDC and Park staff to confirm project success factors and the Owner’s vision. The Kickoff Meeting will occur via teleconference and will be followed by an existing conditions survey site visit.

Deliverables:

1. Within 5 business days of the Kickoff Meeting with BDC and Park staff, submit via email to the BDC Project Manager a report of the meeting minutes document in 8-1/2x11 pdf format.

2. At the completion of the Existing Conditions Survey, submit via email to the BDC Project Manage, documentation of the facility toilet rooms existing conditions in the area of the proposed modifications, including dimensioning of walls, fixtures, and equipment, etc. Documentation will include floor plan drawings as well as elevation drawings and photographs when appropriate, relevant to the proposed modifications. The existing conditions documents will be delivered to BDC in pdf and AutoCAD format. The pdf size will be scaled to fit an 11-inch-x-17-inch format.

B. Task 2 – Concept Design Development

Task 2 will include validation and development of schematic plan layouts for each toilet room provided by the BDC Project Manager and will include proposed modifications and/or options to meet the project design intent. This information will be documented at a conceptual design level and will be submitted in pdf format via email to the BDC Project Manager. The submittal will be discussed at a teleconference with BDC representatives and the design staff.

Deliverables:

1. Submit conceptual architectural floor plans for the facility’s two toilet rooms via e-mail to the BDC Project Manager for BDC review and comments. Conceptual plans will include proposed plan layouts of modified toilet rooms. One conceptual plan layout for each toilet room will be developed. The pdf size will be scaled to fit an 11-inch-x-17-inch format.

95693-259-14 Page 4 October 23, 2014

2. Within 5 business days after the teleconferenced concept design review, submit via email to the BDC Project Manager a meeting minutes report in pdf format.

C. Task 3 – Design Development

The Design Development Phase will involve designing to a 90% level of completion. Jones Edmunds will submit via e-mail to the BDC Project Manager a complete set of the 90% design documents for BDC review and comments. The documents will be formatted as 8-1/2-inch-x-11-inch pdf files except the drawings, which will be scale-formatted as 11-inch-x-17-inch pdf files.

The submittal will be discussed at a teleconference with BDC representatives and the design staff.

Deliverables:

1. Submit to the BDC Design Development drawings in the BDC 24-inch-x-36-inch standard that will include the standard BDC border. The drawings will be scale-formatted to 11-inch-x-17-inch pdf files and will consist of the following:

a) Cover sheet.

b) Abbreviations, legend, and general notes.

c) Existing conditions, photographs, and demolition plans.

d) Environmental notes and schedules.

e) Architectural plans, elevations, sections, schedules, and details.

f) Mechanical plans, schedules, and details.

g) Plumbing plans, schedules, and details.

h) Electrical plans, schedules, and details.

NOTE: All drawings will be completed to a 90% level.

2. Submit to BDC draft technical specifications in CSI format for environmental, architectural, mechanical, plumbing, and electrical design in MS Word in the BDC 8-1/2-inch-x-11-inch standard format and delivered as pdf files.

3. Submit to BDC a Rough Order of Magnitude (ROM) Construction Cost Opinion in MS Excel format and pdf formats. The deliverable will be a written cost opinion containing line item descriptions, unit costs, quantities, line item totals, and aggregate totals.

4. Within 5 business days after the teleconferenced Design Development review meeting, submit via email to the BDC Project Manager a meeting minutes report in pdf format.

D. Task 4 – Construction Documents Development

The Construction Document Phase will involve completing the design to a 100% level of completion. The deliverables will include incorporating previous design development comments.

95693-259-14 Page 5 October 23, 2014

The documents will be completed, signed, and sealed for use in permit application submittals by others.

Deliverables

1. Submit to the BDC six sets of signed-and-sealed final Construction Document drawings (24-inch-x-36-inch dated drawing sheets) incorporating BDC and Park staff comments from the Design Development Phase submittal. Three sets will be provided for State Fire Marshal review, and three sets will be provided for the Contractor’s Building Department submittal. Drawing sheets will include the sheets listed in Design Development Phase.

2. Submit to the BDC three copies of final technical specifications for environmental, architectural, mechanical, plumbing, and electrical design elements.

3. Submit to the BDC three copies of a final ROM Construction Cost Opinion.

II. SCHEDULE

Activity

Total Days after Task

Authorization

Total Days for each

Task Execution of Task Assignment Task 1 – Existing Conditions Survey Kickoff Meeting 8 8 Existing Conditions Survey and Documentation Submittal (20%) 22 14 Task 2 – Concept Design Development Concept Design Submittal (30%) 40 18 BDC Review 50* 10 Task 3 – Design Development Design Development Submittal (90%) 90 40 BDC Review 100* 10 Task 4 – Construction Documents Development Construction Documents Submittal (100%) 114 14

* FDEP review times are assumed; changes to review time will affect deliverable schedules accordingly. A design review meeting will occur at the end of each BDC review period.

III. PROPOSAL CLARIFICATIONS

The following proposal clarifications govern this contract. Excluded items may be provided by Jones Edmunds as an Additional Service upon prior written agreement.

A. Fire protection design alterations are not expected to be required and are excluded.

95693-259-14 Page 6 October 23, 2014

B. FDEP water and wastewater permitting is not expected to be required and is excluded since the project will involve simple plumbing connections to the existing water and wastewater systems.

C. Structural modifications are excluded. Modifications to walls and framing will be limited to interior non-loadbearing partitions. New walls will be limited to within the existing roofline and interior.

D. Sufficient electrical power is assumed to be available for the changes at the various restroom buildings.

E. Permit, plan review, and other regulatory fees are excluded. All permit fees will be paid by others.

F. Activities related to Zoning, Comprehensive Plan, Fire Marshal, and Building Permitting approvals through the County or State are excluded and are assumed to be handled by others.

G. Revisions to the design plans and/or technical specifications due to a change in existing conditions at the site after execution of this contract are excluded.

H. Plan revisions due to Building Department or Fire Marshal comments that relate to items outside this Scope of Services are excluded.

I. Construction administration is excluded.

J. Preparing as-built drawings at construction completion is excluded.

K. The labor hours listed in this fee estimate are based on the assumption that schematic layouts provided by the BDC Project Manager will be feasibly constructible within the dimensions of the existing facility and structure. Additional design and coordination effort resulting from dimensional deficiencies discovered from the Existing Conditions Survey are outside this Scope of Services and will be considered an Additional Service.

L. The quantities and labor hours listed in this fee estimate are intended as documentation and justification for the total cost of the project. Deviations or changes in the quantities and labor hours will not be reason for non-payment provided the total fee has not been exceeded.

END OF SCOPE OF SERVICES

FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION

DIVISION OF RECREATION AND PARKS

BUREAU OF DESIGN AND CONSTRUCTION

RECREATION HALL RESTROOMS RENOVATION PROJECT

Jones Edmunds Proposal No. 95693-259-14

FEE SUMMARY

Total Total Task Hours Dollars

Design Services

TASK 1 - EXISTING CONDITIONS SURVEY 27 3,253.40

TASK 2 - CONCEPT DEVELOPMENT 32 3,532.95

TASK 3 - DESIGN DEVELOPMENT 90 9,829.13

TASK 4 - CONSTRUCTION DOCUMENTS DEVELOPMENT 15 1,516.71

Subtotal 164 18,132.19

Consultant (Environmental Materials Testing and Analysis) 1,170.00

Expenses 842.55

TOTAL FEE AMOUNT 20,144.74

DESIGN SERVICES

October 23, 2014

HIGHLANDS HAMMOCK STATE PARK

10/23/2014

H ig hl an ds H am m oc k

St at e Pa rk R

EC

R

EA

TI

O N

H A

LL

R

ES

TR

O O

M S

R

EN

O

VA

TI

O

N Jo ne s

E dm un ds

' P ro po sa l N um be r 9

-2

-1

FE

E

E S

TI

M

A

TE

D E

TA

IL

TO

TA

LS

TA

S

K P rin ci pa l

P M

A rc hi te ct M ec h

E ng

E le ct E ng E nv E ng C os t E st Te ch A dm in

H ou rs C os t

C on su lta nt E xp en se E

N

E N

E

N

E N

E

N

E N

E

N

A T

A

D

8.

0.

1.

9.

4.

0.

.8

.9

.6

D es ig n

Se rv ic es

TA

SK

EX

IS

TI

N

G C

O N

D

IT

IO

N

S

SU

R

VE

Y S ur ve y

- V er ify

, D oc um en t E xi st in g C on di tio ns

1, 3.

0.

0.

1, 3.

A sB ui lt

D oc um en ta tio n an d N ar ra tiv es

1, 0.

0.

0.

1, 0.

C od e

R ev ie w

/A D

A /M un ic ip al it y R eq ui re m en ts

9.

0.

0.

9.

TA

SK

C O

N C

EP

T

D

EV

EL

O

PM

EN

T S ite S ur ve y

- E nv iro nm en ta l S am pl in g an d

A na ly si s

1, 3.

1, 0.

0.

2, 3.

D ev el op

D es i g n

C on ce pt s

1, 4.

0.

0.

1, 4.

P re se nt

D es i g n

C on ce pt s to

F D

E P

(1 te le co nf er en ce

1.

0.

0.

1.

R O

M C os t O pi ni on

3.

0.

0.

3.

0.

0.

0.

0.

TA

SK

D

ES

IG

N

D

EV

EL

O

PM

EN

T C ov er

S he et , G en er al N ot es

9.

0.

0.

9.

E nv iro nm en ta l N ot es a nd S ch ed ul e s

9.

0.

0.

9.

E xi st in g

C on di tio ns

D em ol iti on P la n

8.

0.

0.

8.

A rc hi te ct ur al P la ns

, S ch ed ul es , a nd D et ai ls

1, 0.

0.

0.

1, 0.

M ec ha ni ca l P la ns , S ch ed ul es

, a nd

D et ai ls

1, 0.

0.

0.

1, 0.

E le ct ric al P la ns

, S ch ed ul es , a nd D et ai ls

1, 4.

0.

0.

1, 4.

Te ch ni ca l S pe ci fic at io ns

1, 0.

0.

0.

1, 0.

C on st ru ct io n

C os t O pi ni on

3.

0.

0.

3.

S ub m itt al

P re pa ra tio n

M ee tin g M in ut es

2.

0.

0.

2.

C om pl et e D ra w in gs to

1.

0.

0.

1.

C om pl et e

S pe ci fic at io ns to

5.

0.

0.

5.

C on st ru ct io n C os t O pi ni on

.8

0.

0.

.8

S i g n

S ea l, P re pa re

F in al S ub m itt al

2.

0.

0.

2.

E xp en se s (S ee E xp en se s

W or ks he et

0.

0.

2.

2.

TO

TA

LS

,6

.4

1, 0.

2.

,1

.7

H O

U R

S C

O S

TS

TA

SK

C O

N

ST

R U

C

TI

O N

D O

C U

M

EN

TS

D

EV

EL

O

PM

EN

T

PROJECT EXPENSE CALCULATOR

PROJECT NAME Highlands Hammock Recreation Hall Restroom Renovation

PROPOSAL NUMBER 95693-259-14

DATE PREPARED 10/23/2014 B&W copy cost per 11x17 page 0.10$ PREPARED BY J. Bell B&W copy cost per page $0.05

Color copy cost per page $0.50 Plot Drawings Cost per SF $0.125

Reproduction

Contract Copies (sets) Internal Copies (sets) Total Copies

No of pages Color

Cost per copy Color

Sub Total Copies Color

Total Page cost

No of pages B & W

Drawing Width (in)

Drawing Length

(in)

Cost per page

B & W Sub Total B & W

Total Page cost

Final Total

Concept Validation Drawings - Half Size 11 x 17 6 6 $0.50 0 $0.00 3 $0.10 18 $1.80 $1.80 Drawings - Full Size * 3 3 $0.75 0 $0.00 3 24 36 $0.75 9 $6.75 $6.75 Specifications 3 3 $0.50 0 $0.00 180 $0.05 540 $27.00 $27.00 Cost Estimate 0 0 $0.50 0 $0.00 2 $0.05 0 $0.00 $0.00

Doc Total $0.00 Design Development Drawings - Half Size 11 x 17 6 6 $0.50 0 $0.00 21 $0.10 126 $12.60 $12.60 Drawings - Full Size 24 x 36 3 3 $0.75 0 $0.00 21 24 36 $0.75 63 $47.25 $47.25 Specifications 3 3 $0.50 0 $0.00 180 8.5 11 $0.05 540 $27.00 $27.00 Cost Estimate 0 0 $0.50 0 $0.00 2 8.5 11 $0.05 0 $0.00 $0.00

CD ROM 0 0 $15.00 0 $0.00 1 $15.00 0 $0.00 $0.00

Doc Total $35.55 Construction Documents Drawings - Half Size 11 x 17 0 0 $0.50 0 $0.00 21 $0.10 0 $0.00 $0.00 Drawings - Full Size 24 x 36 6 6 $0.75 0 $0.00 21 24 36 $0.75 126 $94.50 $94.50 Specifications 3 3 $0.50 0 $0.00 180 8.5 11 $0.05 540 $27.00 $27.00 Cost Estimate 3 3 $0.50 0 $0.00 2 8.5 11 $0.05 6 $0.30 $0.30

CD ROM 0 0 $15.00 0 $0.00 1 $15.00 0 $0.00 $0.00

Shipping 2 2 $15.00 0 $0.00 1 $15.00 2 $30.00 $30.00

Doc Total $121.80

Subtotal $157.35

Mileage Costs* Winter Haven to Site (task 1)

Titusville to Site (Task 2)

(Task 1 only) Trips 1 1 0 0 Miles per trip 100 260 32 0 $/mile 0.445$ 0.445$ 0.55$ 0.55$ Total Cost 44.50$ 115.70$ -$ -$ 160.20$

AirFare Costs Trip Name Trip Name Trip Name Trip Name Trips 0 0 0 0 RT Air Fare $500 $500 $500 $500 Total Cost -$ -$ -$ -$ -$

Rental Car TVL to Site Trip Name Trip Name Trip Name (Task 2) Trips 0 0 0 0

Rental Fee $0 $0 $0 $0 Fuel Cost $0 $0 $0 $0 Total Cost -$ -$ -$ -$ -$

Per Diem GNV Day Trip GNV Overnight Trip Name Trip Name Trips 0 0 Days # of staff 1 1 Per Diem $38.75 $38.75 $38.75 Overnight $150.00 Total Cost -$ -$ -$ -$ -$

Field Supplies/Other Asbestos Test results Item 2 Item 3 Item 4 Qnty 75 0 0 0 Unit Cost $7 $0 $0 $0 Total Cost $525 $0 $0 $0 525.00$

TOTAL $842.55

Table A. Billing Rates Per DC780 (Revised July 1, 2011)

See Attachment C-1 for Billing Rates Detail-->

Table B. Staffing Plan Employees Not Included in Table A, Pay Grades and Billing Rates

Full Name

Pay Grade

Direct Labor Rate

Labor Multiplier

Direct Labor Rate x

Multiplier =

Billing Rate (See Table A, Note 2) Hay, Tina AD3 20.92$ 3.0 62.76$ 60.88$ Woodman, Daina AD3 23.07$ 3.0 69.21$ 67.13$ Feller, Linda AD4 20.34$ 3.0 61.02$ 59.19$ Waldroff, Scott AR6 48.08$ 3.0 144.24$ 139.91$ Upstill, Paul AT5 26.51$ 3.0 79.53$ 77.14$ Inkell, Daniel AT6 30.90$ 3.0 92.70$ 89.92$ Roque, Susana EN1 24.04$ 3.0 72.12$ 69.96$ Smith, Joshua EN1 25.50$ 3.0 76.50$ 74.21$ Rosario, Udeni EN4 30.89$ 3.0 92.67$ 89.89$ Collett, Chad EN6 50.51$ 3.0 151.53$ 146.98$ Welkenbach, James AR6 41.21$ 3.0 123.63$ 119.92$ Cheng, Bin AT7 31.25$ 3.0 93.75$ 90.94$ Oppold, Joe EN5 44.67$ 3.0 134.01$ 129.99$ Swick, Rod EN6 53.41$ 3.0 160.23$ 155.42$ Alqallaf, Ron AT6 28.85$ 3.0 86.55$ 83.95$ Nickel, Walter EN7 59.99$ 3.0 179.97$ 174.57$

Project Name: RECREATION HALL RESTROOMS RENOVATION PROJECT Client: FDEP, Bureau of Design and Construction

Opportunity Number: 95693‐259‐14 Project Number: TBD

Expenses Markup = 1 Subconsultant Markup = 1.1 Cadd Charges, Per Hour = $12.50 GIS Charges, Per Hour = $5.00

Hourly Rates/Not To Exceed Projects:

Billing Labor Rate Table = Not Set Up Direct Labor Table = Not Set Up

Lump Sum/Percent Complete Projects:

Direct Labor Table = Not Set Up Target Direct Labor Multiplier = 3.2

Billing Rate Adjustment Factor= 2.91

Project Fixed Costs and Multipliers

Project Fixed Costs and Multipliers

1743 Wind Drift Road, Orlando, Florida 32809 Phone: 407-888-2285 Fax: 407-888-2015

July 18, 2014

Proposal Number: 07.56.4696

Jamie Bell, P.E.

Jones Edmunds & Associates, Inc.

407 South Washington Ave.

Titusville, Florida 32796

Reference: Highlands Hammock Park Asbestos Report, Drawings &

Specification Review

Dear Jamie:

Thank you for contacting Applied Environmental Health & Safety, Inc. (AEH&S) Please accept this letter as a quote for AEH&S to provide State of Florida licensed Asbestos Consultant services on the above referenced project.

ESTIMATED PROJECT COSTS

Licensed Asbestos Consultant (samp. & analysis methods determination, pricing & schedule) Up to 1 hour @ $135.00 per hour $ 135.00

Licensed Asbestos Consultant, as needed $ 270.00 Report Review, Sign off Up to 2 hours @ 135.00 per hour

Licensed Asbestos Consultant, as needed $ 675.00 Spec & Drawings Review, Sign off Up to 5 hours @ 135.00 per hour

Executive Secretary (proofing, ship & handling, administration) $90.00 Up to 2 hours @ $ 45.00 per hour.

Estimated Labor Cost, plus shipping & handling $ 1,170.00

INVOICE AND PAYMENT TERMS

It is agreed, The estimated costs based upon the information at this time, for consulting time for this project is $ 1,170.00.

Timeliness, cost effectiveness, and efficiency are AEH&S goals on all projects.

It is agreed AEH&S will not exceed this limit without first gaining your written authorization.

AEH&S will provide a detailed invoice to Jones Edmunds & Associates, reflecting the actual charges for each activity needed to complete this project.

Applied Environmental Health & Safety, Inc. submits this proposal with the sole intent to secure a contract for professional consulting services assisting Jones Edmunds & Associates, Inc. Applied Environmental Health & Safety, Inc. is prepared to proceed with the activities necessary to conduct each aspect of this proposal.

The information as it is presented and contained herein is the sole property of Applied Environmental Health & Safety, Inc. and is not offered to serve any purpose other than that for which it is intended.

Any other use of this document or its contents must first be authorized, in writing from Applied Environmental Health & Safety, Inc.

Distribution of this document to organizations other than Jones Edmunds & Associates, Inc. is prohibited without prior written authorization from Applied Environmental Health & Safety, Inc.

Applied Environmental Health & Safety, Inc. is honored to have this opportunity to serve Jones Edmunds & Associates, Inc. in this important and timely project.

Should you have any questions regarding this proposal or any of our other services, please contact Applied Environmental Health & Safety, Inc. at your convenience.

Thank you for the opportunity to assist you in this important project.

Applied Environmental Health & Safety, Inc.

A Professional Occupational Safety and Environmental Health Consulting & Training Firm

Thomas O. Murray, MS, CIH Licensed Asbestos Consultant (IA-0000040)

Authorization to Proceed

Proposal Number: 07.56.4696

Jamie Bell, P.E.

Jones Edmunds & Associates, Inc.

407 South Washington Ave.

Titusville, Florida 32796

Reference: Highlands Hammock Park Asbestos Report, Drawings &

Specification Review

Your signature below and return of one original copy of this proposal with your purchase order reflecting the terms and conditions contained herein shall constitute Applied Environmental Health & Safety, Inc's, authorization to proceed.

NAME TITLE

PURCHASE ORDER NUMBER DATE

DC790, TA 15 Proposal Files.pdf
2014-10-23_PR#7_HighlandsHammock.pdf
2014-10-23_PR_Design_Phase.pdf
1. Remodeling the existing Men’s and Women’s toilet rooms to provide accessibility in conformance with the Americans with Disabilities Act (ADA).
2. Removing existing plumbing fixtures and providing new fixtures.
3. Providing new toilet partitions.
4. Repairing and renovating existing finishes within the renovated areas.
5. Renovating adjacent nonstructural walls and framing to increase space for toilet rooms.
I. Scope of Services
A. Task 1 – Existing Conditions Survey
Deliverables:
1. Within 5 business days of the Kickoff Meeting with BDC and Park staff, submit via email to the BDC Project Manager a report of the meeting minutes document in 8-1/2x11 pdf format.
2. At the completion of the Existing Conditions Survey, submit via email to the BDC Project Manage, documentation of the facility toilet rooms existing conditions in the area of the proposed modifications, including dimensioning of walls, fixtures, an...
B. Task 2 – Concept Design Development
Deliverables:
1. Submit conceptual architectural floor plans for the facility’s two toilet rooms via e-mail to the BDC Project Manager for BDC review and comments. Conceptual plans will include proposed plan layouts of modified toilet rooms. One conceptual plan lay...
2. Within 5 business days after the teleconferenced concept design review, submit via email to the BDC Project Manager a meeting minutes report in pdf format.
C. Task 3 – Design Development
Deliverables:
1. Submit to the BDC Design Development drawings in the BDC 24-inch-x-36-inch standard that will include the standard BDC border. The drawings will be scale-formatted to 11-inch-x-17-inch pdf files and will consist of the following:
a) Cover sheet.
b) Abbreviations, legend, and general notes.
c) Existing conditions, photographs, and demolition plans.
d) Environmental notes and schedules.
e) Architectural plans, elevations, sections, schedules, and details.
f) Mechanical plans, schedules, and details.
g) Plumbing plans, schedules, and details.
h) Electrical plans, schedules, and details.
2. Submit to BDC draft technical specifications in CSI format for environmental, architectural, mechanical, plumbing, and electrical design in MS Word in the BDC 8-1/2-inch-x-11-inch standard format and delivered as pdf files.
3. Submit to BDC a Rough Order of Magnitude (ROM) Construction Cost Opinion in MS Excel format and pdf formats. The deliverable will be a written cost opinion containing line item descriptions, unit costs, quantities, line item totals, and aggregate t...
4. Within 5 business days after the teleconferenced Design Development review meeting, submit via email to the BDC Project Manager a meeting minutes report in pdf format.
D. Task 4 – Construction Documents Development
Deliverables
1. Submit to the BDC six sets of signed-and-sealed final Construction Document drawings (24-inch-x-36-inch dated drawing sheets) incorporating BDC and Park staff comments from the Design Development Phase submittal. Three sets will be provided for Sta...
2. Submit to the BDC three copies of final technical specifications for environmental, architectural, mechanical, plumbing, and electrical design elements.
3. Submit to the BDC three copies of a final ROM Construction Cost Opinion.
II. SCHEDULE
III. PROPOSAL CLARIFICATIONS
END OF SCOPE OF SERVICES