CN-370000-CN814-T3.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|CN814|91372d3fb0c88d0c2cd72afb7c581dc2
Contract number
CN814
Issued by
Florida

About this file

This document is a Consultant's Task Assignment Notification from the Florida Department of Environmental Protection's Division of Recreation and Parks, involving WSP Environment and Infrastructure, Inc. as the consultant. The contract is for the Weeki Wachee Point Bar Restoration project located at Weeki Wachee Springs State Park, with the primary FDEP contact being Vu Nguyen and the WSP representative being Jennifer Sagan.

The task assignment covers professional services to develop conceptual restoration designs and a permit application package for restoring three point bars along the Weeki Wachee River. The project is divided into four tasks: data compilation and survey, conceptual design, 60% design documents, and permitting services. The total contract value is $48,011.97, comprising $47,574.18 in fixed price costs and $437.79 in reimbursable costs. The project is scheduled to run from project execution (anticipated on 3/1/2025) through 6/15/2025, with payment made upon FDEP approval of deliverables for each task. The work will involve surveying, design development, and permit application preparation for point bars #6, #21, and #30, with the goal of restoring historic point bar edges and implementing ecological improvements.

View the file

Other files

File Type Posted
CN-370000-CN814-T5.pdf PDF
ContractBudgetExport.csv CSV file
CN-370000-CN814-T1.pdf PDF
CN-370000-CN815-T3.pdf PDF
CN-370000-CN814-T6.pdf PDF
CN-370000-CN814-T8.pdf PDF
CN-370000-CN814.pdf PDF
CN-370000-CN814-CO1.pdf PDF
CN-370000-CN814-T2.pdf PDF
CN-370000-CN814-T4.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Division of Recreation and Parks

Consultant’s Task Assignment Notification

FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

DRP-084

Rev. 03/03/2025 1 of 2

FDEP Contract No: Project Number: Task Assignment No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement (Not to Exceed):

Total Task Amount:

Signatures and Date:

1.

Budget Representative, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Contract Manager, FDEP Signature Date

4.

Consultant Signature Date

5.

Contract Authority, FDEP Signature Date

814 D4-281-03-RM25 03

Weeki Wachee Springs State Park Weeki Wachee Point Bar Restoration

WSP Environment and Infrastructure, Inc.

Jennifer Sagan

(352) 474-9818 Jennifer.Sagan@wsp.com

Vu Nugyen

(850) 245-2630 vu.nguyen@floridadep.gov

Provide professional services to develop conceptual restoration designs and a permit application package to restore 3 point bars along the Weeki Wachee River per the attached proposal dated 1/27/2025. Subtasks using CN204 rates are indicated by *.

Chris Becker or successor

Upon Execution 06/15/2025

$47,574.18 $437.79 $48,011.97

Chris Brannon

Chris Becker

Vu Nugyen

Cristine Mehle

Michael W. Foster Jr., PE

CHRIS BRANNON Digitally signed by CHRIS BRANNON Date: 2025.03.12 09:30:14 -04'00' 03/14/2025

Chris Becker Digitally signed by Chris Becker Date: 2025.03.12 10:37:28 -04'00' 03/14/2025

Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.03.12 14:45:50 -04'00' 03/14/2025

Digitally signed by Mehle, Christine (USCM717518) DN: cn=Mehle, Christine (USCM717518), ou=Active, email=christine.mehle@wsp.com Date: 2025.03.13 08:16:30 -04'00'

Mehle, Christine

(USCM717518) 03/14/2025

Michael W. Foster Jr., P.E.

Digitally signed by Michael W. Foster Jr., P.E.

Date: 2025.03.14 08:53:28 -04'00' 03/14/2025

Division of Recreation and Parks

Consultant’s Task Assignment Notification

FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

DRP-084

Rev. 03/03/2025 2 of 2

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total:

n/a n/a 37504000999 100718/00 675005 U1500 131500 X2 $48,011.97

$48,011.97

January 27, 2025

Mr. Chris Becker Project Manager Florida Department of Environmental Protection 1843 South Tamiami Trail Osprey, FL 34229

Re: DEP Agreement Number CN204 TA53

TA53 Weeki Wachee Point Bar Restoration

WSP Project No.: 2024US292527

Dear Mr. Becker:

WSP USA Inc. (WSP) is pleased to provide this proposal summary and labor documentation for the tasks identified below for Weeki Wachee Point Bar Restoration. The goal of the project is to provide engineering conceptual and 60% design and permit application submittal for the restoration of three (3) point bar locations. Final design and permits will be scoped in another proposal. WSP understands that the order of priority for restoration is Point Bar #21, #6, and #30. The following tasks will be performed in accordance with DEP Agreement Number CN204, Amendment No. 2 and will be completed on a lump sum basis:

Data Compilation, Desktop Analysis, and Survey Conceptual and 60% Design Documents Permit Application Submittal

Thank you and please contact the undersigned with any questions.

Sincerely, Jennifer Sagan, MS Assistant Vice President/Senior Project Manager

(352) 922-0134 jennifer.sagan@wsp.com

5411 Skycenter Drive Suite 650 Tampa, FL 33607 +1 (352) 922-0134 wsp.com

CN814 TA3

Weeki Wachee 2024 Point Bar Restoration

DEP Agreement Number CN204, Task Assignment Number TA53

Task 1 Data Compilation, Desktop Analysis, and Survey

Description: WSP will compile all available quarterly and annual monitoring data for Point Bars #6, #21 & #30, including cross-sections, soils, vegetation, scarp erosion data, photographs, and recent aerial images.

Up to six (6) cross-sections (two at each site) will be surveyed using total station at Point Bars #6, 21, & 30.

Survey of the point bars will be utilized to capture the geometry and topography of the study areas to assist with design and as a comparison for post-restoration recovery. Note that the surveys will be conducted in a relative datum (not tied to a specific vertical or horizontal datum), and monuments will be set so that future surveys can retain the same relative datum. Compilation of this data will assist with design and provide information for inclusion in permitting narratives.

Deliverable:

The topographic survey of cross-sections will be included in digital portable document format (.pdf).

Performance Measure: The Department will review the deliverables to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Task 1

Firm Name

Position Classification Hourly Rate Hours Total Fixed Price Cost

WSP Senior Principal $292.62 1 $292.62

WSP Professional Surveyor/Manager $165.64 2 $331.28

WSP Senior 2 Engineer, Geologist, Scientist, Planner $164.23 10 $1,642.30

WSP Project Engineer, Geologist, Scientist, Project Manager $123.00 20 $2,460.00

WSP Survey Tech II $92.05 3 $276.15

WSP Survey Tech I $63.59 12 $763.08

WSP Clerical $61.98 6 $371.88

Fixed Price Total Cost $6,137.31

Reimbursable Cost:

Task 1

Mileage (@ $0.445 per mile) 306 miles ( and 190 miles k)

Reimbursable Total Cost $136.17

Total for Task 1: $6,273.48

Task 2 Conceptual Design Documents

Description: WSP will develop concept-level plans for restoring Point Bars #6, #21, and #30 based on the information gathered in Task 1. WSP will create a concept design memo including location maps, summaries of restoration area and scarp heights, photos, suggested plant species list and spacing, and concept-level plans. Concept-level plans will include a planview design showing restoration of historic point bar edges, coir log placement, and planting zones for the three point bars in GIS format. This assumes the conceptual design plans will be reviewed by FDEP for one round of comments, with design changes updated during the 60% design phase (Task 3).

Deliverable:

Conceptual Design GIS plan-set and conceptual design memo in digital portable document format (.pdf).

Performance Measure: The Department will review the deliverables to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Task 2

Firm Name

Position Classification Hourly Rate Hours Total Fixed Price Cost

WSP Senior Principal $292.62 3 $877.86

WSP Senior 2 Engineer, Geologist, Scientist, Planner $164.23 28 $4,598.44

WSP Project Engineer, Geologist, Scientist, Project Manager $123.00 6 $738

WSP CADD Designer $95.02 18 $1,710.36

WSP Clerical $61.98 3 $185.94

Fixed Price Total Cost $8,110.60

Task 2

None NA

Reimbursable Total Cost $0.00

Total for Task 2: $8,110.60

Task 3 - 60% Design Documents

Description: WSP will develop 60% design plans for restoring Point Bars #6, #21, and #30 based on plans. The 60% design plans electronically drafted in

AutoCAD Civil-3D (.dwg) and digital portable document format (.pdf) will have polished specifics including refined cross-sectional profiles, details for the installation of preferred treatments and materials, planting plan with species, sizes, quantities, and spacing. The final electronic file (.dwg) will be delivered to FDEP with the 100% design package. Also included with the 60% design package are technical specifications to specify the appropriate material and methods to govern the construction of the project.

opinion of probable costs (EOPC) and an updated design memo will be included in digital portable document format (.pdf) with the deliverable package. The 60% design plans will be fully packaged in formats necessary for the submission of permit applications to regulatory agencies. The 60% design plans will be reviewed by FDEP for one round of comments with design changes updated during the final 100% for construction plan development.

Deliverable:

60% design set with technical specifications, EOPC, and updated design memo in digital portable document format (.pdf).

Task 3

Firm Name

Position Classification Hourly Rate Hours Total Fixed Price Cost

WSP Senior Principal $292.62 4 $1,170.48

WSP Senior 2 Engineer, Geologist, Scientist, Planner $164.23 33 $5,419.59

WSP Project Engineer, Geologist, Scientist, Project Manager $123.00 119 $14,637.00

WSP Clerical $61.98 4 $247.92

Fixed Price Total Cost $21,474.99

Task 3

None NA

Reimbursable Total Cost $0.00

Total for Task 3: $21,474.99

Task 4 Permitting Services

Description: This scope assumes that the restoration work can be authorized under the USACE Nationwide Permit #27 and the Southwest Florida Water Management District (SWFWMD) General Environmental Resource Permit (ERP) as restoration and will include all three point bars in one permit application. WSP will gather all pertinent Uniform Mitigation Assessment Method (UMAM) field data and forms obtained in Task 1, permit figures, and design plans to draft permit applications. WSP will investigate the possibility of Sovereign Submerged Lands (SSL) along private parcels near Point Bar #21 and #30.

Additional protocols for SSL will be followed and implemented as necessary. WSP will then submit the permit packages to the appropriate permitting agency(ies). Permit application fees are included in this task and are estimated at $250.

Deliverable:

The deliverable will include a permit application package to FDEP for review and signatures, to be delivered to the FDEP project manager.

Task 4

Firm Name

Position Classification Hourly Rate Hours Total Fixed Price Cost

WSP Senior 2 Engineer, Geologist, Scientist, Planner $164.23 4 $656.92

WSP Project Engineer, Geologist, Scientist, Project Manager $123.00 72 $8,856.00

WSP CADD Designer $95.02 22 $2,090.44

WSP Clerical $61.98 4 $247.92

Fixed Price Total Cost $11,851.28

Task 4

Mileage (@ $0.445 per mile) $51.62 ( to Weeki Wachee State Park)

Permit Fee $250

Reimbursable Total Cost $301.62

Total for Task 4: $12,152.90

Project Schedule

The below project schedule assumes a Project Start to be issued on 3/1/2025 or earlier. The schedule assumes FDEP comments on the conceptual design will be received within 5 business days.

Activity Duration Commence Complete

Task 1 Data Compilation and Survey 4 weeks 3/1/2025 4/1/2025

Task 2 Conceptual Design 2 weeks 4/2/2025 4/16/2025

Task 3 60% Design 8weeks 4/17/2025 6/15/2025

Task 4 - Permitting 15 weeks 3/1/2025 6/15/2025

Summary of Fees

Pricing assumes that restoration of all three point bars is issued under one Task Assignment.

Task Task Fixed Price Cost Task Reimbursable

Task 1 Data Compilation and Survey $6,137.31 $136.17

Task 2 Conceptual Design $8,110.60 $0.00

Task 3 60% Design $21,474.99 $0.00

Task 4 - Permitting $11,851.28 $301.62

Total Fixed Price Cost: $47,574.18

Total Reimbursable Cost: $437.79

Overall Total Cost: $48,011.97

Payment will be made upon approval of deliverables for each task by the FDEP in the amount specified.