About this file

This is a Task Assignment Change Order Form (Change Order No. 02) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for a professional architectural services contract with Dodstone Architects. The contract pertains to the Lundy Building Re-roof project at Silver Springs State Park. The FDEP Contract No. is CN804, Project No. 61598, and Task Assignment No. 08. The consultant representative is Jodie Dodson, AIA, and the FDEP Contract Manager is Laurinda Micheels. All parties executed the change order on April 20, 2026, with final approval from Contract Authority Michael W. Foster, Jr., P.E. on April 24, 2026.

The change order authorizes professional services to revise previously submitted construction details and specifications to incorporate a contractor-requested roof system design. The net increase in task amount for this change order is $18,293.12, bringing the total task amount including all change orders to $153,781.12. The cost is structured as a fixed fee of $18,293.12 with no reimbursable expenses. The work involves 30 working days for rework of 60% construction details and specifications, commencing upon acceptance of Change Order 02 and receipt of pull test verification. The task end date has been extended from June 30, 2026 to December 18, 2029, representing a net extension of 1,267 days. Funding is allocated under FLAIR Code 61598-37503000203-100718/00-675005-U1300-131500-X2 in the amount of $18,293.12. The labor cost breakdown includes 40 hours at $195.27 (Principal), 65 hours at $101.88 (Graduate Architect 3), and 62 hours at $62.26 (Graduate Architect 1).

View the file

Other files

File Type Posted
CN-370000-CN804-T3.pdf PDF
CN-370000-CN804-T3CO1.pdf PDF
CN-370000-CN804-T6CO1.pdf PDF
CN-370000-CN804-T7.pdf PDF
CN-370000-CN804-CN804.pdf PDF
CN-370000-CN804-T1.pdf PDF
CN-370000-CN804.pdf PDF
CN-370000-CN804-T1CO1.pdf PDF
CN-370000-CN804-T2.pdf.crdownload CRDOWNLOAD file
CN-370000-CN804-T4.pdf PDF
CN-370000-CN804-T5.pdf PDF
CN-370000-CN804-T6.pdf PDF
CN-370000-CN804-T8.pdf PDF
CN-370000-CN804.pdf.crdownload CRDOWNLOAD file
CN-370000-CN804-CMC1.pdf PDF
CN-370000-CN804-T2.pdf PDF
CN-370000-CN804-T2CO1.pdf PDF
CN-370000-CN804-T8CO1.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Division of Recreation and Parks

Task Assignment Change Order Form

FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

DRP-085

Rev. /2025 1 of 2

FDEP Contract No: Project Number:

Task Assignment No: Change Order No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Description of Change:

Change in Task Amount

Item Reimbursement Fixed Fee Total Original Task Amount Task Amount Including All Previous Change Orders Net Increase/Decrease in Task Amount for this Change Order Task amount with All Change Orders

CN804 61598

08 02

Silver Springs State Park Lundy Re-roof

Dodstone Architects Jodie Dodson, AIA

(850) 656-7326 jdodson@dodstone.com

Laurinda Micheels

(850) 245-2781 laurinda.micheels@floridadep.gov

Professional services necessary to revise the previously submitted details and specifications and incorporate the contractor-requested roof system as well as a time extension, per attached proposal and time extension request dated April 17, 2026.

$ 0.00 $ 7,810.80

$ 0.00 $ 135,488.00

$ 0.00 $ 18,293.12

$ 0.00 $ 153,781.12

$ 7,810.80

$ 135,488.00

$ 18,293.12

$ 153,781.12

FFLORIDAA DEPARTMENTT OF Divisionn off Recreationn andd Parks ENVIRONMENTALL PROTECTIONN Task Assignment Change Order Form

Change in Task Time

Original Task Execution Date Original Task End Date Present Task End Date Net Change in Days New Task End Date

Funding Information

29 Digit FLAIR Code:

Project # Grant # Org Code Cat/Year Fund Module Object Code

EO Amount

Total

Approval Signatures

Budget Representative, FDEP

Project Manager, FDEP

Contract Authority, FDEP

Signature

Signature

Signature

Signature

Signature

Date

Date

Date

Date

Date

DRP-085

Rev. 2 of 2 d nta atu

09/04/2025 06/30/2026 06/30/2026 1,267 12/18/2029

61598 37503000203 100718/00 675005 U1300 131500 X2 $ 18,293.12

$ 18,293.12

Tamika Bass

Terry McCullum Jr.

Dodstone Architects

Laurinda Micheels

Michael W. Foster, Jr., P.E.

Tamika Bass Digitally signed by Tamika Bass Date: 2026.04.20 12:31:52 -04'00'

Terry McCullum Jr.

Digitally signed by Terry McCullum Jr.

Date: 2026.04.20 13:05:46 -04'00'

Joel L Dodson Digitally signed by Joel L Dodson Date: 2026.04.20 13:52:42 -04'00'

Laurinda Micheels Digitally signed by Laurinda Micheels Date: 2026.04.20 16:41:35 -04'00'

Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2026.04.24 08:51:15 -04'00'

Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AR0015211

Subtask 3c

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 40 $7,810.80 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 65 $6,622.20 Graduate Architect 1 $62.26 62 $3,860.12

$18,293.12

Subtask 3c $18,293.12

Rework 60% Construction Details and Specifications

Firm Name

Dodstone Architects

Rework 60% Construction Details and Specifications

Summary Provider Base Service Additional

Service Subtotal Reimb. Total

Column1 Column2 Column3 Column4 Column5 Column6 Column7 Column8 Column9

Subtask 3c Rework 60% Construction Details and Specifications DS $18,293.12 $18,293.12 $18,293.12

Task 3c $0.00 $18,293.12 $18,293.12 $0.00 $18,293.12 $0.00 $18,293.12 $18,293.12 $0.00 $18,293.12

Summary Base Service Additional

Service Subtotal Reimb. Total Original Contract $0.00 $7,810.80 $7,810.80 $0.00 $7,810.80 Change Order 1 $113,266.84 $14,410.36 $127,677.20 $0.00 $127,677.20 Change Order 2 $0.00 $18,293.12 $18,293.12 $0.00 $18,293.12 Project Total $113,266.84 $40,514.28 $153,781.12 $0.00 $153,781.12

Change Order 2

PROJECT TOTAL

60% detail revision Project Total

McCullum, Terry

From: Lauren Shields <lshields@dodstone.com> Sent: Friday, April 17, 2026 2:59 PM To: McCullum, Terry Cc: Jodie Dodson Subject: Re: Silver Springs State Park Lundy Re-roof - Time Extension

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Hi Terry, Yes, that is correct. Please extend Task Assignment 8 to December 18, 2029.

Thank you, On Fri, Apr 17, 2026 at 2:48 PM McCullum, Terry <Terry.McCullum@floridadep.gov> wrote:

Lauren, 1267 days would put the task assignment expiration on December 18, 2029, which is the end of the current master contract. Is that the date for which you were requesting?

Respectfully, Terry McCullum, Jr., PMP®

Florida Department of Environmental Protection

Division of Recreation and Parks

Bureau of Design and Construction

Design Section Leader

Terry.McCullum@FloridaDEP.gov

Office: (850) 245-2466

Mobile: (850) 694-2332

File details come from the government source that posted it. Updated .