Document Summary

This is a Consultant's Task Assignment Notification (DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for the Florida Geological Survey Warehouse Dehumidification project. The primary consultant is The Dodstone Group Architects, represented by Karin Zawrotny, with subconsultants McGinniss + Fleming Engineering and Bliss & Niytray. The contract is identified as CN804 (Project Number SCFAC, Task Assignment 7) and is managed by FDEP's Vu Nguyen, with Richard Marcil serving as the project manager.

The scope of work encompasses comprehensive design, permitting, and construction administrative services to install a dehumidification system in the warehouse's storage areas. Services include background drawings and field verification, schematic design, construction documents at 60%, 90%, and 100% completion levels, bidding and permitting services, State Fire Marshal permit application, shop review and RFI responses, pre-construction meeting attendance, and site visits during interim, substantial, and final phases. The total fixed-price contract amount is $55,037.28 with no cost reimbursement component. Work is authorized upon execution with a completion date of February 15, 2027. The contract is funded through Organization Code 37020100000 with an allocation of $55,037.28 (EO: PF, Fund: 408001). All deliverables are to be provided electronically in PDF format unless otherwise specified, with performance reviewed by FDEP to confirm completeness, accuracy, and timeliness.

View the file

Other files

File Type Posted
CN-370000-CN804-CMC1.pdf PDF
CN-370000-CN804-T2.pdf PDF
CN-370000-CN804-T2CO1.pdf PDF
CN-370000-CN804-T8CO1.pdf PDF
CN-370000-CN804-T3.pdf PDF
CN-370000-CN804-T3CO1.pdf PDF
CN-370000-CN804-T6CO1.pdf PDF
CN-370000-CN804-CN804.pdf PDF
CN-370000-CN804-T1.pdf PDF
CN-370000-CN804-T8CO2.pdf PDF
CN-370000-CN804.pdf PDF
CN-370000-CN804-T1CO1.pdf PDF
CN-370000-CN804-T2.pdf.crdownload CRDOWNLOAD file
CN-370000-CN804-T4.pdf PDF
CN-370000-CN804-T5.pdf PDF
CN-370000-CN804-T6.pdf PDF
CN-370000-CN804-T8.pdf PDF
CN-370000-CN804.pdf.crdownload CRDOWNLOAD file
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. 0 /2025 of 2

FDEP Contract No: Project Number: Task Assignment No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement (Not to Exceed):

Total Task Amount:

Signatures and Date:

1.

Budget Representative, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Signature Date

4.

Signature Date

5.

Contract Authority, FDEP Signature Date

CN804 SCFAC 7

Warehouse HVAC

The Dodstone Group Architects Karin Zawrotny

(850) 656-7326 kzawrotny@dodstone.com

Vu Nguyen

(850) 245-2630 vu.nguyen@floridadep.gov

Design, permitting and construction administrative services to install a dehumidification system per the attached dated June 2, 2025.

Richard Marcil

Upon Execution 02/15/2027

$55,037.28 $0.00 $55,037.28

Traci Billingsley

Richard Marcil

Karin Zawrotny

Vu Nguyen

Michael W. Foster Jr., P.E.

06/17/2025

06/25/2025

Traci Billingsley Digitally signed by Traci Billingsley Date: 2025.06.17 15:12:06 -04'00'

Richard Rene Marcil, III Digitally signed by Richard Rene Marcil, III Date: 2025.06.24 07:44:05 -04'00'

Karin I. Zawrotny Digitally signed by Karin I. Zawrotny Date: 2025.06.25 14:45:49 -04'00'

Florida Geological Survey

Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.06.27 16:44:04 -04'00'

Michael W.

Foster Jr., P.E.

Digitally signed by Michael W. Foster Jr., P.E.

Date: 2025.07.01 13:13:23 -04'00'

DDivision oof RRecreation aand PParks

CConsultant’s TTask AAssignment NNotification

FFLORIDA DEPARTMENT OF

EENVIRONMENTAL PPROTECTION

DRP-084

Rev. /2025 2 of 2

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total:

SCFAC NA 37020100000 083643/00 408001 NA PF $55,037.28

$55,037.28

Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AR0015211

Subtask 1a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Project Manager $155.65 2 $311.30 Registered Architect 1 $113.20 18 $2,037.60 Support Staff 2 $56.60 2 $113.20

$2,462.10

Subtask 1a Background Drawings & Field Verification $2,462.10

Background Drawings & Field Verification

Firm Name

Dodstone Architects

Subtask 2a Schematic Design

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 0.5 $97.64 Project Manager $155.65 2 $311.30 Support Staff 2 $56.60 3 $169.80

$578.74 Principal/PE $180.00 2 $360.00 Project Manager $165.00 12 $1,980.00 Engineer II $105.00 25 $2,625.00 Technician I $55.00 37 $2,035.00

$7,000.00

Subtask 2a Schematic Design $7,578.74

Firm Name

McGinniss + Fleming

Subtask 2b 60% CDs

Price Cost

Principal $195.27 1 $195.27 Project Manager $155.65 10 $1,556.50 Registered Architect 1 $113.20 14 $1,584.80 Support Staff 2 $56.60 3 $169.80

$3,506.37 Principal/PE $180.00 4 $720.00 Project Manager $165.00 12 $1,980.00 Engineer II $105.00 30 $3,150.00 Technician I $55.00 58 $3,190.00

$9,040.00 Principal $248.73 1 $248.73 Engineer $148.97 5 $744.85 CAD Technician $139.66 6 $837.96 Admin Assistant $83.80 2 $167.60

$1,999.14

Subtask 2b 60% CDs $14,545.51

Bliss & Niytray

Firm Name

Subtask 2c 90% CDs

Price Cost

Principal $195.27 1 $195.27 Project Manager $155.65 8 $1,245.20 Registered Architect 1 $113.20 15 $1,698.00 Support Staff 2 $56.60 3 $169.80

$3,308.27 Principal/PE $180.00 2 $360.00 Project Manager $165.00 10 $1,650.00 Engineer II $105.00 8 $840.00 Technician I $55.00 21 $1,155.00

$4,005.00 Principal $248.73 3 $746.19 CAD Technician $139.66 5 $698.30 Admin Assistant $83.80 1 $83.80

$1,528.29

Subtask 2c 90% CDs $8,841.56

Bliss & Niytray

Firm Name

Subtask 2d 100% CDs

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 2 $390.54 Project Manager $155.65 2 $311.30 Registered Architect 1 $113.20 4 $452.80 Support Staff 2 $56.60 2 $113.20

$1,267.84 Principal/PE $180.00 1 $180.00 Project Manager $165.00 1 $165.00 Technician I $55.00 3 $165.00

$510.00 Principal $248.73 1 $248.73 Admin Assistant $83.80 2 $167.60

$416.33

Subtask 2d 100% CDs $2,194.17

Bliss & Niytray

Firm Name

Subtask 3a Bidding Services

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 1 $195.27 Project Manager $155.65 4 $622.60 Registered Architect 1 $113.20 2 $226.40 Support Staff 2 $56.60 2 $113.20

$1,157.47 Principal/PE $180.00 1.5 $270.00 Technician I $55.00 8 $440.00

$710.00

Subtask 3a Bidding Services $1,867.47

Firm Name

Subtask 3b Permitting Services

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 1 $195.27 Project Manager $155.65 5 $778.25 Registered Architect 1 $113.20 6 $679.20 Support Staff 2 $56.60 2 $113.20

$1,765.92 Principal/PE $180.00 1.5 $270.00 Technician I $55.00 8 $440.00

$710.00

Subtask 3b Permitting Services $2,475.92

Firm Name

Dodstone Architects

McGinniss + Fleming

Subtask 3c SFM permit application

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 1 $195.27 Project Manager $155.65 2 $311.30 Registered Architect 1 $113.20 5 $566.00 Support Staff 2 $56.60 2 $113.20

$1,185.77

Subtask 3c SFM permit application $1,185.77

Subtask 3d Shop Review and RFI Responses

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 2 $390.54 Project Manager $155.65 8 $1,245.20 Registered Architect 1 $113.20 24 $2,716.80 Support Staff 2 $56.60 5 $283.00

$4,635.54 Principal/PE $180.00 2 $360.00 Project Manager $165.00 5 $825.00 Engineer II $105.00 10 $1,050.00 Technician I $55.00 10 $550.00

$2,785.00

Subtask 3d Shop Review and RFI Responses $7,420.54

McGinniss + Fleming

Subtask 3e Pre-Construction Meeting

Price Cost

Project Manager $155.65 4 $622.60 Support Staff 2 $56.60 2 $113.20

$735.80 Principal/PE $180.00 4 $720.00 Technician I $55.00 2 $110.00

$830.00

Subtask 3e Pre-Construction Meeting $1,565.80

Firm Name

McGinniss + Fleming

Dodstone Architects

Subtask 4a Interim Site Visit Position Classification Hourly Rate Hours Total Fixed

Project Manager $155.65 3 $466.95 Registered Architect 1 $113.20 4 $452.80 Support Staff 2 $56.60 1 $56.60

$976.35 Project Manager $165.00 3 $495.00 Technician I $55.00 2 $110.00

$605.00

Subtask 4a Interim Site Visit $1,581.35

Firm Name

Subtask 4b Substantial Review

Price Cost

Project Manager $155.65 4 $622.60 Registered Architect 1 $113.20 4 $452.80 Support Staff 2 $56.60 1 $56.60

$1,132.00 Project Manager $165.00 3 $495.00 Technician I $55.00 2 $110.00

$605.00

Subtask 4b Substantial Review $1,737.00

Firm Name

Dodstone Architects

McGinniss + Fleming

Subtask 4c Final Review

Position Classification Hourly Rate Hours Total Fixed Price Cost

Project Manager $155.65 3 $466.95 Registered Architect 1 $113.20 4 $452.80 Support Staff 2 $56.60 1 $56.60

$976.35 Project Manager $165.00 3 $495.00 Technician I $55.00 2 $110.00

$605.00

Subtask 4c Final Review $1,581.35

Firm Name

Summary Provider Base Service Additional

Service Subtotal Reimb. Total

Subtask 1a DS $2,462.10 $2,462.10 $2,462.10

MFE

BNI

Subtask 2a DS $578.74 $7,578.74 $7,578.74

MFE $7,000.00

BNI

Subtask 2b DS $3,506.37 $14,545.51 $14,545.51

MFE $9,040.00

BNI $1,999.14

Subtask 2c DS $3,308.27 $8,841.56 $8,841.56

MFE $4,005.00

BNI $1,528.29

Subtask 2d DS $1,267.84 $2,194.17 $2,194.17

MFE $510.00

BNI $416.33

Subtask 3a DS $1,157.47 $1,867.47 $1,867.47

MFE $710.00

BNI

Subtask 3b DS $1,765.92 $2,475.92 $2,475.92

MFE $710.00

BNI

Subtask 3c DS $1,185.77 $1,185.77 $1,185.77

MFE

BNI

Subtask 3d DS $4,635.54 $7,420.54 $7,420.54

MFE $2,785.00

BNI

Subtask 3e DS $735.80 $1,565.80 $1,565.80

MFE $830.00

BNI

Subtask 4a DS $976.35 $1,581.35 $1,581.35

MFE $605.00

BNI

Subtask 4b DS $1,132.00 $1,737.00 $1,737.00

MFE $605.00

BNI

Subtask 4c DS $976.35 $1,581.35 $1,581.35

MFE $605.00

BNI

1a $0.00 $2,462.10 $2,462.10 $0.00 $2,462.10

2a,2b,2c,2d $33,159.98 $0.00 $33,159.98 $0.00 $33,159.98

3a,3b,3c $4,343.39 $1,185.77 $5,529.16 $0.00 $5,529.16

3d, 3e $8,986.34 $0.00 $8,986.34 $0.00 $8,986.34

4a,4b,4c $4,899.70 $0.00 $4,899.70 $0.00 $4,899.70 $51,389.41 $3,647.87 $55,037.28 0.00 $55,037.28

BASE CONTRACT

Background Drawings & Field Verification

Schematic Design

60% CDs

Project Total

Pre-Design Phases

Bidding & Permitting

Site Visits

90% CDs

100% CDs

Bidding Services

Permitting Services

SFM permit application

Shop Review and RFI Responses

Interim Site Visit

Substantial Review

Construction Documents

CA

Final Review

Pre-Construction Meeting