This is a Task Assignment Change Order Form (Change Order 01) issued by the Florida Department of Environmental Protection's Division of Recreation and Parks. The document authorizes a change order to FDEP Contract No. CN804 for professional architectural and engineering services at Silver Springs State Park. The consulting firm is Dodstone Architects, represented by Principal Jodie Dodson, AIA, with field verification services provided by Bliss and Nyitray. The contract manager is Laurinda Micheels of FDEP's Bureau of Design & Construction.
The change order increases the task assignment amount by $127,677.20, bringing the total task amount with all change orders to $135,488.00 (from an original amount of $7,810.80). The services encompass the complete design and construction administration for the Lundy Building Reroof project, including field investigation, 60% and 100% construction document preparation, bidding services, pre-construction meeting, limited construction administration, and five interim site visits plus substantial completion and final site visits. Key deliverables include field reports, construction documents in PDF format, responses to bid questions, and site visit reports. The work is funded through FDEP's budget code 61598/37503000203/675005/U3200/131500, with the original task execution date of September 4, 2025, and task end date of June 30, 2026. Payment is contingent upon submission and approval of deliverables, with the contract terminable for failure to perform satisfactory work within specified timeframes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN804-T3.pdf | ||
| CN-370000-CN804-T3CO1.pdf | ||
| CN-370000-CN804-T6CO1.pdf | ||
| CN-370000-CN804-T7.pdf | ||
| CN-370000-CN804-CMC1.pdf | ||
| CN-370000-CN804-T2.pdf | ||
| CN-370000-CN804-T2CO1.pdf | ||
| CN-370000-CN804-CN804.pdf | ||
| CN-370000-CN804-T1.pdf | ||
| CN-370000-CN804-T8CO2.pdf | ||
| CN-370000-CN804.pdf | ||
| CN-370000-CN804-T1CO1.pdf | ||
| CN-370000-CN804-T2.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-CN804-T4.pdf | ||
| CN-370000-CN804-T5.pdf | ||
| CN-370000-CN804-T6.pdf | ||
| CN-370000-CN804-T8.pdf | ||
| CN-370000-CN804.pdf.crdownload | CRDOWNLOAD file |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Division of Recreation and Parks
Task Assignment Change Order Form
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
DRP-085
Rev. 0 /2025 1 of 2
FDEP Contract No: Project Number:
Task Assignment No: Change Order No:
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Description of Change:
Change in Task Amount
Item Reimbursement Fixed Fee Total Original Task Amount Task Amount Including All Previous Change Orders Net Increase/Decrease in Task Amount for this Change Order Task amount with All Change Orders
CN804 61598
08 01
Lundy Re-roof
Dodstone Architects Jodie Dodson, AIA
(850) 656-7326 jdodson@dodstone.com
Laurinda Micheels
(850) 245-2781 laurinda.micheels@floridadep.gov
Professional architectural and engineering services to provide construction documents to compete the repair of the roof of the Lundy building, per the attached proposal dated December 23, 2025.
$ 0.00 $ 7,810.80
$ 0.00 $ 7,810.80
$ 0.00 $ 127,677.20
$ 0.00 $ 135,488.00
$ 7,810.80
$ 7,810.80
$ 127,677.20
$ 135,488.00
Silver Springs State Park
FFLORIDAA DEPARTMENTT OF Divisionn off Recreationn andd Parks ENVIRONMENTALL PROTECTIONN Task Assignment Change Order Form
Change in Task Time
Original Task Execution Date Original Task End Date Present Task End Date Net Change in Days New Task End Date
Funding Information
29 Digit FLAIR Code:
Project # Grant # Org Code Cat/Year Fund Module Object Code
EO Amount
Total
Approval Signatures
Budget Representative, FDEP
Project Manager, FDEP
Contract Authority, FDEP
Signature
Signature
Signature
Signature
Signature
Date
Date
Date
Date
Date
DRP-085
Rev. 2 of 2 d nta atu
09/04/2025 06/30/2026 06/30/2026 06/30/2026
61598 37503000203 100718/00 675005 U3200 131500 X2 $ 127,677.20
$ 127,677.20
Tamika Bass
Terry McCullum Jr.
Jodie Dodson, AIA
Laurinda Micheels
Michael W. Foster Jr., P.E.
Tamika Bass Digitally signed by Tamika Bass Date: 2026.01.08 09:29:01 -05'00'
Terry McCullum Jr.
Digitally signed by Terry McCullum Jr.
Date: 2026.01.08 09:32:08 -05'00'
Joel L Dodson Digitally signed by Joel L Dodson Date: 2026.01.08 16:21:08 -05'00'
Laurinda Micheels
Digitally signed by Laurinda Micheels Date: 2026.01.12 16:43:51 -05'00'
Michael W.
Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2026.01.13 09:44:47 -05'00'
Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AR0015211
Subtask 2a
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $195.27 36 $7,029.72 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 48 $4,890.24 Graduate Architect 1 $62.26 40 $2,490.40
$14,410.36
Principal $248.73 0 $0.00 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00
$0.00
Subtask 2a $14,410.36
Field Verification
Firm Name
Dodstone Architects
Bliss and Nyitray
Field Verification
Subtask 3a
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $195.27 80 $15,621.60 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 136 $13,855.68 Graduate Architect 1 $62.26 124 $7,720.24
$37,197.52
Principal $248.73 20 $4,974.60 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00
$4,974.60
Subtask 3a $42,172.12
60% Construction Documents
Firm Name
Dodstone Architects
Bliss And Nyitray
60% Construction Documents
Subtask 3b
Price Cost
Principal $195.27 62 $12,106.74 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 132 $13,448.16 Graduate Architect 1 $62.26 120 $7,471.20
$33,026.10
Principal $248.73 8 $1,989.84 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00
$1,989.84
Subtask 3b $35,015.94
Bliss And Nyitray
100% Construction Documents
Firm Name
Dodstone Architects
100% Construction Documents
Subtask 4a
Price Cost
Principal $195.27 12 $2,343.24 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 16 $1,630.08 Graduate Architect 1 $62.26 0 $0.00
$0.00 $3,973.32
Principal $248.73 0 $0.00 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00
$0.00
Subtask 4a $3,973.32Bidding Services
Bidding Services
Firm Name
Dodstone Architects
Bliss And Nyitray
Subtask 5a
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00
$2,343.24
Subtask 5a $2,343.24
Pre-Construction Meeting
Firm Name
Pre-Construction Meeting
Subtask 5b
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $195.27 24 $4,686.48 Graduate Architect 3 $101.88 60 $6,112.80 Graduate Architect 1 $62.26 8 $498.08
$11,297.36
Subtask 5b $11,297.36Limited Construction Admin.
Limited Construction Admin.
Firm Name
Subtask 6a
Price Cost
Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00
$2,343.24
Subtask 6a $2,343.24
Dodstone Architects
Interim Architectural Site Visit 1
Interim Architectural Site Visit 1
Firm Name
Subtask 6b
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00
$2,343.24
Subtask 6b $2,343.24Interim Architectural Site Visit 2
Interim Architectural Site Visit 2
Subtask 6c
Price Cost
Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00
$2,343.24
Subtask 6c $2,343.24
Interim Architectural Site Visit 3
Firm Name
Dodstone Architects
Interim Architectural Site Visit 3
Subtask 6d
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00
$2,343.24
Subtask 6d $2,343.24
Interim Architectural Site Visit 4
Firm Name
Interim Architectural Site Visit 4
Subtask 6e
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $248.73 12 $2,984.76 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00
$2,984.76
Subtask 6e $2,984.76
Firm Name
Bliss And Nyitray
Interim Structural Site Visit 1
Interim Structural Site Visit 1
Subtask 6f
Position Classification Hourly Rate Hours Total Fixed Price Cost
Principal $195.27 15 $2,929.05 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 2 $124.52
$3,053.57
Subtask 6f $3,053.57
Substantial Architectural Site Visit
Firm Name
Substantial Architectural Site Visit
Subtask 6g
Price Cost
Principal $195.27 15 $2,929.05 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 2 $124.52
$3,053.57
Subtask 6g $3,053.57Final Architectural Site Visit
Final Architectural Site Visit
Summary Provider Base Service Additional
Service Subtotal Reimb. Total
Column1 Column2 Column3 Column4 Column5 Column6 Column7 Column8 Column9 Subtask 2a Field Verification DS $14,410.36 $14,410.36 $14,410.36
0 BNI $0.00
Subtask 3a 60% Construction DS $37,197.52 $42,172.12 $42,172.12
BNI $4,974.60 $0.00
Subtask 3b 100% Construction DS $33,026.10 $35,015.94 $35,015.94
BNI $1,989.84 $0.00
Subtask 4a Bidding Services DS $3,973.32 $3,973.32 $3,973.32
BNI $0.00 $0.00
Subtask 5a Pre-Construction Meeting DS $2,343.24 $2,343.24 $2,343.24
BNI $0.00 $0.00
Subtask 5b Limited Construction DS $11,297.36 $11,297.36 $11,297.36
BNI $0.00 $0.00
Subtask 6a Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24
BNI $0.00 $0.00
Subtask 6b Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24
BNI $0.00 $0.00
Subtask 6c Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24
BNI $0.00 $0.00
Subtask 6d Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24
BNI $0.00 $0.00
Subtask 6e Interim Structural Site DS $0.00 $2,984.76 $2,984.76
0 BNI $2,984.76 $0.00
Subtask 6f Substantial Architectural DS $3,053.57 $3,053.57 $3,053.57
0 BNI $0.00 $0.00
Subtask 6g Final Architectural Site DS $3,053.57 $3,053.57 $3,053.57
0 BNI $0.00 $0.00
Task 2 $0.00 $14,410.36 $14,410.36 $14,410.36 Task 3 $77,188.06 $77,188.06 $77,188.06 Task 4 $3,973.32 $3,973.32 $3,973.32 Task 5 $13,640.60 $13,640.60 $13,640.60 Task 6 $18,464.86 $18,464.86 $18,464.86
$113,266.84 $14,410.36 $127,677.20 0.00 $127,677.20 Site Visits Project Total
Change Order 1
Pre-Design Phases Construction Doc Phase Bidding & Permitting Basic CA Services
Description
Subtask 2a Field Verification 30 From Authorization of CO1 Subtask 3a 60% Construction Documents 60 From Authorization of CO1 Subtask 3b 100% Construction Documents 30 From completion of Subtask 3a Subtask 4a Bidding Services TBD Subtask 5a Pre-Construction Meeting TBD Subtask 5b Limited Construction Admin. TBD Subtask 6a Interim Architectural Site Visit 1 TBD Subtask 6b Interim Architectural Site Visit 2 TBD Subtask 6c Interim Architectural Site Visit 3 TBD Subtask 6d Interim Architectural Site Visit 4 TBD Subtask 6e Interim Structural Site Visit 1 TBD Subtask 6f Substantial Architectural Site Visit TBD Subtask 6g Final Architectural Site Visit TBD
Change Order 01 Working Days