This is a Task Assignment Change Order Form (Change Order 01) issued by the Florida Department of Environmental Protection's Division of Recreation and Parks. The document authorizes a change order to FDEP Contract No. CN804 for professional architectural and engineering services at Silver Springs State Park. The consulting firm is Dodstone Architects, represented by Principal Jodie Dodson, AIA, with field verification services provided by Bliss and Nyitray. The contract manager is Laurinda Micheels of FDEP's Bureau of Design & Construction.

The change order increases the task assignment amount by $127,677.20, bringing the total task amount with all change orders to $135,488.00 (from an original amount of $7,810.80). The services encompass the complete design and construction administration for the Lundy Building Reroof project, including field investigation, 60% and 100% construction document preparation, bidding services, pre-construction meeting, limited construction administration, and five interim site visits plus substantial completion and final site visits. Key deliverables include field reports, construction documents in PDF format, responses to bid questions, and site visit reports. The work is funded through FDEP's budget code 61598/37503000203/675005/U3200/131500, with the original task execution date of September 4, 2025, and task end date of June 30, 2026. Payment is contingent upon submission and approval of deliverables, with the contract terminable for failure to perform satisfactory work within specified timeframes.

View the file

Other files

File Type Posted
CN-370000-CN804-T3.pdf PDF
CN-370000-CN804-T3CO1.pdf PDF
CN-370000-CN804-T6CO1.pdf PDF
CN-370000-CN804-T7.pdf PDF
CN-370000-CN804-CMC1.pdf PDF
CN-370000-CN804-T2.pdf PDF
CN-370000-CN804-T2CO1.pdf PDF
CN-370000-CN804-CN804.pdf PDF
CN-370000-CN804-T1.pdf PDF
CN-370000-CN804-T8CO2.pdf PDF
CN-370000-CN804.pdf PDF
CN-370000-CN804-T1CO1.pdf PDF
CN-370000-CN804-T2.pdf.crdownload CRDOWNLOAD file
CN-370000-CN804-T4.pdf PDF
CN-370000-CN804-T5.pdf PDF
CN-370000-CN804-T6.pdf PDF
CN-370000-CN804-T8.pdf PDF
CN-370000-CN804.pdf.crdownload CRDOWNLOAD file
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Division of Recreation and Parks

Task Assignment Change Order Form

FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

DRP-085

Rev. 0 /2025 1 of 2

FDEP Contract No: Project Number:

Task Assignment No: Change Order No:

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Description of Change:

Change in Task Amount

Item Reimbursement Fixed Fee Total Original Task Amount Task Amount Including All Previous Change Orders Net Increase/Decrease in Task Amount for this Change Order Task amount with All Change Orders

CN804 61598

08 01

Lundy Re-roof

Dodstone Architects Jodie Dodson, AIA

(850) 656-7326 jdodson@dodstone.com

Laurinda Micheels

(850) 245-2781 laurinda.micheels@floridadep.gov

Professional architectural and engineering services to provide construction documents to compete the repair of the roof of the Lundy building, per the attached proposal dated December 23, 2025.

$ 0.00 $ 7,810.80

$ 0.00 $ 7,810.80

$ 0.00 $ 127,677.20

$ 0.00 $ 135,488.00

$ 7,810.80

$ 7,810.80

$ 127,677.20

$ 135,488.00

Silver Springs State Park

FFLORIDAA DEPARTMENTT OF Divisionn off Recreationn andd Parks ENVIRONMENTALL PROTECTIONN Task Assignment Change Order Form

Change in Task Time

Original Task Execution Date Original Task End Date Present Task End Date Net Change in Days New Task End Date

Funding Information

29 Digit FLAIR Code:

Project # Grant # Org Code Cat/Year Fund Module Object Code

EO Amount

Total

Approval Signatures

Budget Representative, FDEP

Project Manager, FDEP

Contract Authority, FDEP

Signature

Signature

Signature

Signature

Signature

Date

Date

Date

Date

Date

DRP-085

Rev. 2 of 2 d nta atu

09/04/2025 06/30/2026 06/30/2026 06/30/2026

61598 37503000203 100718/00 675005 U3200 131500 X2 $ 127,677.20

$ 127,677.20

Tamika Bass

Terry McCullum Jr.

Jodie Dodson, AIA

Laurinda Micheels

Michael W. Foster Jr., P.E.

Tamika Bass Digitally signed by Tamika Bass Date: 2026.01.08 09:29:01 -05'00'

Terry McCullum Jr.

Digitally signed by Terry McCullum Jr.

Date: 2026.01.08 09:32:08 -05'00'

Joel L Dodson Digitally signed by Joel L Dodson Date: 2026.01.08 16:21:08 -05'00'

Laurinda Micheels

Digitally signed by Laurinda Micheels Date: 2026.01.12 16:43:51 -05'00'

Michael W.

Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2026.01.13 09:44:47 -05'00'

Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AR0015211

Subtask 2a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 36 $7,029.72 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 48 $4,890.24 Graduate Architect 1 $62.26 40 $2,490.40

$14,410.36

Principal $248.73 0 $0.00 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00

$0.00

Subtask 2a $14,410.36

Field Verification

Firm Name

Dodstone Architects

Bliss and Nyitray

Field Verification

Subtask 3a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 80 $15,621.60 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 136 $13,855.68 Graduate Architect 1 $62.26 124 $7,720.24

$37,197.52

Principal $248.73 20 $4,974.60 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00

$4,974.60

Subtask 3a $42,172.12

60% Construction Documents

Firm Name

Dodstone Architects

Bliss And Nyitray

60% Construction Documents

Subtask 3b

Price Cost

Principal $195.27 62 $12,106.74 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 132 $13,448.16 Graduate Architect 1 $62.26 120 $7,471.20

$33,026.10

Principal $248.73 8 $1,989.84 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00

$1,989.84

Subtask 3b $35,015.94

Bliss And Nyitray

100% Construction Documents

Firm Name

Dodstone Architects

100% Construction Documents

Subtask 4a

Price Cost

Principal $195.27 12 $2,343.24 Project Manager $155.65 0 $0.00 Graduate Architect 3 $101.88 16 $1,630.08 Graduate Architect 1 $62.26 0 $0.00

$0.00 $3,973.32

Principal $248.73 0 $0.00 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00

$0.00

Subtask 4a $3,973.32Bidding Services

Bidding Services

Firm Name

Dodstone Architects

Bliss And Nyitray

Subtask 5a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00

$2,343.24

Subtask 5a $2,343.24

Pre-Construction Meeting

Firm Name

Pre-Construction Meeting

Subtask 5b

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 24 $4,686.48 Graduate Architect 3 $101.88 60 $6,112.80 Graduate Architect 1 $62.26 8 $498.08

$11,297.36

Subtask 5b $11,297.36Limited Construction Admin.

Limited Construction Admin.

Firm Name

Subtask 6a

Price Cost

Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00

$2,343.24

Subtask 6a $2,343.24

Dodstone Architects

Interim Architectural Site Visit 1

Interim Architectural Site Visit 1

Firm Name

Subtask 6b

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00

$2,343.24

Subtask 6b $2,343.24Interim Architectural Site Visit 2

Interim Architectural Site Visit 2

Subtask 6c

Price Cost

Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00

$2,343.24

Subtask 6c $2,343.24

Interim Architectural Site Visit 3

Firm Name

Dodstone Architects

Interim Architectural Site Visit 3

Subtask 6d

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 12 $2,343.24 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 0 $0.00

$2,343.24

Subtask 6d $2,343.24

Interim Architectural Site Visit 4

Firm Name

Interim Architectural Site Visit 4

Subtask 6e

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $248.73 12 $2,984.76 Project Manager Sr. Eng. $159.61 0 $0.00 Project Engineer $148.97 0 $0.00 Cad Manager $139.66 0 $0.00 Administrative Assistant $83.80 0 $0.00

$2,984.76

Subtask 6e $2,984.76

Firm Name

Bliss And Nyitray

Interim Structural Site Visit 1

Interim Structural Site Visit 1

Subtask 6f

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $195.27 15 $2,929.05 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 2 $124.52

$3,053.57

Subtask 6f $3,053.57

Substantial Architectural Site Visit

Firm Name

Substantial Architectural Site Visit

Subtask 6g

Price Cost

Principal $195.27 15 $2,929.05 Graduate Architect 3 $101.88 0 $0.00 Graduate Architect 1 $62.26 2 $124.52

$3,053.57

Subtask 6g $3,053.57Final Architectural Site Visit

Final Architectural Site Visit

Summary Provider Base Service Additional

Service Subtotal Reimb. Total

Column1 Column2 Column3 Column4 Column5 Column6 Column7 Column8 Column9 Subtask 2a Field Verification DS $14,410.36 $14,410.36 $14,410.36

0 BNI $0.00

Subtask 3a 60% Construction DS $37,197.52 $42,172.12 $42,172.12

BNI $4,974.60 $0.00

Subtask 3b 100% Construction DS $33,026.10 $35,015.94 $35,015.94

BNI $1,989.84 $0.00

Subtask 4a Bidding Services DS $3,973.32 $3,973.32 $3,973.32

BNI $0.00 $0.00

Subtask 5a Pre-Construction Meeting DS $2,343.24 $2,343.24 $2,343.24

BNI $0.00 $0.00

Subtask 5b Limited Construction DS $11,297.36 $11,297.36 $11,297.36

BNI $0.00 $0.00

Subtask 6a Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24

BNI $0.00 $0.00

Subtask 6b Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24

BNI $0.00 $0.00

Subtask 6c Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24

BNI $0.00 $0.00

Subtask 6d Interim Architectural Site DS $2,343.24 $2,343.24 $2,343.24

BNI $0.00 $0.00

Subtask 6e Interim Structural Site DS $0.00 $2,984.76 $2,984.76

0 BNI $2,984.76 $0.00

Subtask 6f Substantial Architectural DS $3,053.57 $3,053.57 $3,053.57

0 BNI $0.00 $0.00

Subtask 6g Final Architectural Site DS $3,053.57 $3,053.57 $3,053.57

0 BNI $0.00 $0.00

Task 2 $0.00 $14,410.36 $14,410.36 $14,410.36 Task 3 $77,188.06 $77,188.06 $77,188.06 Task 4 $3,973.32 $3,973.32 $3,973.32 Task 5 $13,640.60 $13,640.60 $13,640.60 Task 6 $18,464.86 $18,464.86 $18,464.86

$113,266.84 $14,410.36 $127,677.20 0.00 $127,677.20 Site Visits Project Total

Change Order 1

Pre-Design Phases Construction Doc Phase Bidding & Permitting Basic CA Services

Description

Subtask 2a Field Verification 30 From Authorization of CO1 Subtask 3a 60% Construction Documents 60 From Authorization of CO1 Subtask 3b 100% Construction Documents 30 From completion of Subtask 3a Subtask 4a Bidding Services TBD Subtask 5a Pre-Construction Meeting TBD Subtask 5b Limited Construction Admin. TBD Subtask 6a Interim Architectural Site Visit 1 TBD Subtask 6b Interim Architectural Site Visit 2 TBD Subtask 6c Interim Architectural Site Visit 3 TBD Subtask 6d Interim Architectural Site Visit 4 TBD Subtask 6e Interim Structural Site Visit 1 TBD Subtask 6f Substantial Architectural Site Visit TBD Subtask 6g Final Architectural Site Visit TBD

Change Order 01 Working Days