This is a Task Assignment Change Order Form (CO1) issued by the Florida Department of Environmental Protection's Division of Recreation and Parks for the Cypress Room Demolition project at Silver Springs State Park. The document establishes a contractual modification between FDEP and Dodstone Architects, with Janus Research serving as a subconsultant. The contract manager for FDEP is Vu Nguyen, and the consultant representative is Jodie Dodson, AIA. The project contract number is CN804, project number 61570, and task assignment number 06.
Change Order 1 adds $16,554.31 in fixed fee services to finalize the draft Historic American Building Survey (HABS) documentation report for the Cypress Room and submit a final copy to the Florida Department of Historic Resources. The work is divided into three subtasks: Subtask 2c (HABS Documentation Final Submittal) at $4,049.32, Subtask 4b (Interpretive Exhibit Final Submittal) at $6,452.01, and Subtask 5b (Walkway Preservation Plan Final Submittal) at $6,052.98. The original task amount was $48,051.98 ($3,500.00 reimbursement, $44,551.98 fixed fee), and with all change orders, the revised contract amount is $64,606.29 ($3,500.00 reimbursement, $61,106.29 fixed fee). The task execution date is 04/28/2025 with a task end date of 12/31/2025, with no net change in days. Funding is allocated via FLAIR code 61570-37503000203-100718/00-675005-U1300-131500-X2. Deliverables include architectural and research documentation in PDF format, with review and approval requirements from FDEP and the Florida Department of Historic Resources before payment is issued.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN804-T3.pdf | ||
| CN-370000-CN804-T3CO1.pdf | ||
| CN-370000-CN804-T7.pdf | ||
| CN-370000-CN804-CMC1.pdf | ||
| CN-370000-CN804-T2.pdf | ||
| CN-370000-CN804-T2CO1.pdf | ||
| CN-370000-CN804-T8CO1.pdf | ||
| CN-370000-CN804-CN804.pdf | ||
| CN-370000-CN804-T1.pdf | ||
| CN-370000-CN804-T8CO2.pdf | ||
| CN-370000-CN804.pdf | ||
| CN-370000-CN804-T1CO1.pdf | ||
| CN-370000-CN804-T2.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-CN804-T4.pdf | ||
| CN-370000-CN804-T5.pdf | ||
| CN-370000-CN804-T6.pdf | ||
| CN-370000-CN804-T8.pdf | ||
| CN-370000-CN804.pdf.crdownload | CRDOWNLOAD file |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Division of Recreation and Parks
Task Assignment Change Order Form
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
DRP-085
Rev. 0 /2025 1 of 2
FDEP Contract No: Project Number:
Task Assignment No: Change Order No:
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Description of Change:
Change in Task Amount
Item Reimbursement Fixed Fee Total Original Task Amount Task Amount Including All Previous Change Orders Net Increase/Decrease in Task Amount for this Change Order Task amount with All Change Orders
CN804 61570
06 01
Cypress Room Demolition
Dodstone Architects Jodie Dodson, AIA
(850) 656-7326 jdodson@dodstone.com
Vu Nguyen
(850) 245-2630 vu.nguyen@floridadep.gov
Provide the services necessary to finalize the draft HABS documentation report for the Silver Springs State Park Cypress Room and submit a final copy to the Florida Department of Historic Resources, per the attached proposal dated August 20, 2025.
$ 3,500.00 $ 44,551.98
$ 3,500.00 $ 44,551.98
$ 0.00 $ 16,554.31
$ 3,500.00 $ 61,106.29
$ 48,051.98
$ 48,051.98
$ 16,554.31
$ 64,606.29
Silver Springs State Park
FFLORIDAA DEPARTMENTT OF Divisionn off Recreationn andd Parks ENVIRONMENTALL PROTECTIONN Task Assignment Change Order Form
Change in Task Time
Original Task Execution Date Original Task End Date Present Task End Date Net Change in Days New Task End Date
Funding Information
29 Digit FLAIR Code:
Project # Grant # Org Code Cat/Year Fund Module Object Code
EO Amount
Total
Approval Signatures
Budget Representative, FDEP
Project Manager, FDEP
Contract Authority, FDEP
Signature
Signature
Signature
Signature
Signature
Date
Date
Date
Date
Date
DRP-085
Rev. 2 of 2 d nta atu
04/28/2025 12/31/2025 12/31/2025 12/31/2025
61570 37503000203 100718/00 675005 U1300 131500 X2 $ 16,554.31
$ 16,554.31
Tamika Bass
Terry McCullum Jr.
Jodie Dodson, AIA
Vu Nguyen
Michael W. Foster Jr., P.E.
Tamika Bass Digitally signed by Tamika Bass Date: 2025.09.03 14:54:57 -04'00'
Terry McCullum Jr.
Digitally signed by Terry McCullum Jr.
Date: 2025.09.04 08:10:29 -04'00'
Joel L Dodson Digitally signed by Joel L Dodson Date: 2025.09.04 10:08:57 -04'00'
Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.09.04 13:41:57 -04'00'
Michael W.
Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2025.09.04 14:25:44 -04'00'
Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AR0015211
Subtask 2c HABS Documentation (Final Submittal)
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Dodstone Architects Principal $195.27 1 $195.27 Project Manager $155.65 6 $933.90 Graduate Architect 3 $101.88 6 $611.28
$1,740.45
Janus Project Manager 1 $230.92 2 $461.84 Chief Scientist $167.22 6 $1,003.32 Scientist $72.41 9 $651.69 Graphics Designer $72.79 2 $145.58 Secretary/Clerical $46.44 1 $46.44
$2,308.87
Subtask 2c HABS Documentation (Final Submittal) $4,049.32
Subtask 4b Interpretive Exhibit (Final Submittal)
Firm Name Position Classification
Hourly Rate Hours
Total Fixed Price
Cost
Project Manager $155.65 6 $933.90 Graduate Architect 3 $101.88 4 $407.52 Support Staff 1 $33.96 0 $0.00 CAD Operator 2 $84.90 0 $0.00
$1,536.69
Janus Project Manager 1 $230.92 1 $230.92 Chief Scientist $167.22 15 $2,508.30 Scientist $72.41 20 $1,448.20 Graphics Designer $72.79 10 $727.90
$4,915.32
Subtask 4b Interpretive Exhibit (Final Submittal) $6,452.01
Subtask 5b Walkway Preservation Plan (Final Submittal)
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Project Manager $155.65 8 $1,245.20 Graduate Architect 3 $101.88 4 $407.52 Support Staff 1 $33.96 0 $0.00 CAD Operator 2 $84.90 0 $0.00
$1,847.99
Janus Project Manager 1 $230.92 1 $230.92 Chief Scientist $167.22 19 $3,177.18 Scientist $72.41 10 $724.10 Graphics Designer $72.79 1 $72.79
$4,204.99
Subtask 5b Walkway Preservation Plan (Final Submittal) $6,052.98
Summary Provider Base Service Additional
Service Subtotal Reimb. Total
Column1 Column2 Column3 Column4 Column5 Column6 Column7 Column8 Column9 Subtask 2c HABS Documentation DS $1,740.45 $4,049.32 $4,049.32
Janus $2,308.87 Subtask 4b Interpretive Exhibit (Final DS $1,536.69 $6,452.01 $6,452.01
Janus $4,915.32 Subtask 5b Walkway Preservation Plan DS $1,847.99 $6,052.98 $6,052.98
Janus $4,204.99
2c, 4b, 5b $0.00 $16,554.31 $16,554.31 $0.00 $16,554.31
$0.00 $16,554.31 $16,554.31 0.00 $16,554.31
Original Contract Amount $0.00 $44,551.98 $44,551.98 $3,500.00 $48,051.98
CO1 $0.00 $16,554.31 $16,554.31 $0.00 $16,554.31
Revised Contract Amount $0.00 $61,106.29 $61,106.29 $3,500.00 $64,606.29
Site Visits CO1 Total
CO1 - Final FDHR Submittals
Pre-Design Phases Construction Doc Phase Bidding & Permitting Basic CA Services