B08_Atch__11_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Contract_Price_Schedule_Blank.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
Rebuild Paramount Ranch & Rocky Oaks Administrativ
Solicitation number
140P2022R0066
Issued by

About this file

This price schedule contract template outlines pricing requirements for the Rebuild Rocky Oaks project to reconstruct residential and administrative buildings and perform associated site work at Santa Monica Mountains National Recreation Area in Agoura Hills, California. Offerors must submit pricing for the base scope of work including residential building, site utilities, site work, and electrical service, as well as two bid options for an administration building and stone veneer. Pricing is to be provided as lump sums or unit prices with extended totals as specified. The total proposed price should include the base work and all options. The National Park Service is the contracting agency.

View the file

Other files

File Type Posted
B09_A6_Final_Q_A_Responses_0006.xlsx XLSX spreadsheet
Sol_140P2022R0066_Amd_0006.pdf PDF
B09_Amd_5_Schedule_of_Changes_Q_A_0005.pdf PDF
Sol_140P2022R0066_Amd_0005.pdf PDF
B09_SAMO_P_R_Sign_in_sheet_0004.pdf PDF
SAMO_Bidding_Questions_Documents_0004.zip ZIP file
B09_A3_Rev_Solit_Clauses_Construction_0004.pdf PDF
B09_SAMO_P_R_Business_Card_Sheet_0004.pdf PDF
Sol_140P2022R0066_Amd_0004.pdf PDF
B09_A3_Q_A_to_AE_TEAM_REV2_Final_Copy__0004.xlsx XLSX spreadsheet
Sol_140P2022R0066_Amd_0003.pdf PDF
B09_SAMO_-_303051_PR__310132_RO_-_Pre-Bid_Walkthrough_Directions_0003.pdf PDF
Sol_140P2022R0066_Amd_0002.pdf PDF
B09_A2_Rev_Solit_Clauses_Construction_0002.docx DOCX document
B09_A2_Q_A_0002.xlsx XLSX spreadsheet
B09_A1_Q_A_0001.pdf PDF
Sol_140P2022R0066_Amd_0001.pdf PDF
B08_Atch__10_SAMO_Rebuild_Paramount_Ranch_Final_100__CD_Blank_Contract_Price_Schedule.xlsx XLSX spreadsheet
B08_Atch__5_DBA_WD_CA20220022_09022022.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part2.pdf PDF
B08_Atch__7_Solit_PSP_Vol_I_PastPerf.docx DOCX document
B08_Atch__6_Solit_PSP_Vol_I_ProjExp_REQD.docx DOCX document
B08_Atch__9_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Atch__8_Solit_PSP_Vol_II_GenRefs.doc DOC document
B08_Atch__12_Subcontracting_Plan.doc DOC document
B08_Atch__3_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Specifications.pdf PDF
B08_Atch__4_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Drawings.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part1.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part3.pdf PDF
Sol_140P2022R0066.pdf PDF
B08_Atch__1_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Specifications.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule

Contract Price Schedule
National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18
Solicitation Number: 140P2022R0066
PARK - PMIS: SAMO-310132
Developed Area: 5,852 Gross Area of New Buildings
Project Title: Rebuild Rocky Oaks
Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of summation error, the total corrected amounts govern. Round totals & extended prices to whole dollars. Refer to section “H” of this solicitation for additional information regarding contract options.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQuantityUnit of MeasureUnit PriceTotal Price
1Base Bid - RESIDENTIAL BUILDING1Lump Sum
2Base Bid - SITE UTILITIES1Lump Sum
3Base Bid - SITEWORK1Lump Sum
4Base Bid - ELECTRICAL UTILITY SERVICE DESIGN AND UTILITY-PERFORMED INSTALLATION1Allowance$20,000.00$20,000
TOTAL BASE PRICE (Contract Line Item Numbers 1 - 4) ---------------------------------------------------------------------------------
5Bid Option 1 - ADMINSTRATION BUILDING1Lump Sum
6Bid Option 2 - STONE VENEER BASE AT RESIDENTIAL BUILDING1Lump Sum
TOTAL PRICE FOR BID OPTIONS 1 - 2 (CLINS 5 - 6) ----------------------------------------------------------------------------
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) --------------------------
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.

File details come from the government source that posted it. Updated .