This document contains questions and answers regarding a solicitation for rebuilding administrative areas at Paramount Ranch and Rocky Oaks in California's Santa Monica Mountains National Recreation Area. The solicitation seeks to rebuild administrative buildings, residential buildings, barns and event spaces at Paramount Ranch, as well as administrative and residential buildings at Rocky Oaks. Questions cover clarification of requirements for site work, utilities, structures, finishes and systems. Responses clarify materials, methods and responsibilities for items including foundations, structural elements, exterior finishes, mechanical and electrical systems. The National Park Service is the contracting agency, with a response deadline of October 31, 2022 that has since been extended. Pricing is to be provided for base requirements as well as optional bid line items for additional scope.

View the file

Other files

File Type Posted
B09_A6_Final_Q_A_Responses_0006.xlsx XLSX spreadsheet
Sol_140P2022R0066_Amd_0006.pdf PDF
B09_Amd_5_Schedule_of_Changes_Q_A_0005.pdf PDF
Sol_140P2022R0066_Amd_0005.pdf PDF
B09_SAMO_P_R_Sign_in_sheet_0004.pdf PDF
SAMO_Bidding_Questions_Documents_0004.zip ZIP file
B09_A3_Rev_Solit_Clauses_Construction_0004.pdf PDF
B09_SAMO_P_R_Business_Card_Sheet_0004.pdf PDF
Sol_140P2022R0066_Amd_0004.pdf PDF
Sol_140P2022R0066_Amd_0003.pdf PDF
B09_SAMO_-_303051_PR__310132_RO_-_Pre-Bid_Walkthrough_Directions_0003.pdf PDF
Sol_140P2022R0066_Amd_0002.pdf PDF
B09_A2_Rev_Solit_Clauses_Construction_0002.docx DOCX document
B09_A2_Q_A_0002.xlsx XLSX spreadsheet
B09_A1_Q_A_0001.pdf PDF
Sol_140P2022R0066_Amd_0001.pdf PDF
B08_Atch__10_SAMO_Rebuild_Paramount_Ranch_Final_100__CD_Blank_Contract_Price_Schedule.xlsx XLSX spreadsheet
B08_Atch__5_DBA_WD_CA20220022_09022022.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part2.pdf PDF
B08_Atch__7_Solit_PSP_Vol_I_PastPerf.docx DOCX document
B08_Atch__6_Solit_PSP_Vol_I_ProjExp_REQD.docx DOCX document
B08_Atch__9_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Atch__8_Solit_PSP_Vol_II_GenRefs.doc DOC document
B08_Atch__12_Subcontracting_Plan.doc DOC document
B08_Atch__3_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Specifications.pdf PDF
B08_Atch__4_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Drawings.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part1.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part3.pdf PDF
Sol_140P2022R0066.pdf PDF
B08_Atch__1_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Specifications.pdf PDF
B08_Atch__11_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Contract_Price_Schedule_Blank.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Solicitation No. 140P2022R0066, SAMO-303051/3101323
QuestionsAnswersAmendment
1Please provide date/time of the site walkThe date/time of the pre-proposal site visit has not been determined yet. When it is, an amendment will be posted to www.sam.gov providing all offerors with the information.1
2We are a Small Business under the SBA criteria for small business.

Per page 1 of the "B08_Atch_12_Subcontracting Plan", and per page 50 of the Solicitation under item 3,it is noted that "SMALL BUSINESS SUBCONTRACTING PLAN: Small business offerors are not required to submit a subcontracting plan; however, large business offerors shall complete and submit the attached Subcontracting Plan Form in response to the requirements of clause 52.219-9."

But then on page 54 of 55, under Evaluation Factors, under "Volume I --Non-Price Proposal", under "Factor 6 Small Business Participation", it is noted:

"All offerors (both other than small businesses and small businesses) will be evaluated on the extent of proposed participation/commitment to use U.S. small businesses in the performance of this acquisition (as small business prime offerors or small business subcontractors) relative to the objectives and requirements established herein. Small business offerors will receive the maximum credit for this evaluation factor and do not need to submit any documentation supporting this evaluation factor"

Thus the information about who fills out the Small Business Subcontracting Plan is in conflict in the solicitation.

The Small Business Subcontracting Plan identifies subcontracting goals for a variety of disadvantaged company times. Since we are a Small Business and are apparently not required to fill out the Subcontracting Plan, then we will not be providing any information in our proposal related to percentage work performed by various disadvantaged business categories, as called out in the Plan under Items "2", "3", and on through item "11".

Can you confirm and/or clarify this?Small businesses are not required to submit a Small Business Subcontracting Plan. The goal of both of these referenced sections is to encourage small business participation. Small businesses prime contractors already fulfill this by default and do not need to provide any additional information.1
3Outlook indicated that the email address for Gabriel Castellanos was not valid; is there a correct email address for him?Gabriel's email address is gabriel_castellanos@nps.gov1
4Solicitation, Factor 3, page 48 of 55 states to “assume a Notice to Proceed date of October 1, 2022” however the proposal is due October 31st. Please provide new anticipated NTP date for use in proposal schedule.Please use an anticipated NTP date of January 2, 2023. This date has also been updated in the solicitation in accordance with the direction being provided.2
5Solicitation, Factor 4, page 49 of 55 states project experience may include “up to 5 relevant projects completed in the last 5 years.” We respectfully request the allowance of projects completed in the last 6 years.We will grant the request to expand the allowance of projects completed in the last 6 years for Factor 4. The solicitation has been updated to reflect this change.2
6In regards to the above named project can you please confirm the RFI deadline, page 47 of 55 section B. states, “Pre-proposal questions shall be submitted a minimum of 10 days prior to the due date and time for proposals.” Is this 10 business days or just 10 calendar days?This is 10 calendar days and the word "calendar" has been added to the this section in the solicitation for clarification.2
7For bid Option A, Small Event Building, are we to include all underground wet and dry utilities and site improvements to and around the building?ARG: Yes, see revised language attached3
8For all bid items that call out from face of building, are we to include the foundations in that cost?ARG: Yes.3
9If Option A is not selected, are we to assume the foundation for this?ARG: No.3
10Are we to install a BAS in all the buildings?3
11Will we need to include a cost for electrical and water usage?ARG: Per Section 015000, 1.3 & Temporary electrical power need to be provided by the General Contractor. Non-potable water is available without use charges. There is no potable water on either site.3
12The spec manual says "The project civil designer should confirm if the flood designations are of concern for the civil design of the site grading and drainage of the site.” Does the design as drawn comply with the 100 year flood plain requirements?"SDE: Drawings show the proposed grading and drainage outside of the flood plain. Design intent is to maintain existing grades for work within the 100 yr flood plain and limit raising grade within the 100 yr flood plain where ever possible.3
13On sheet C1.1, there is a symbol "PD" that goes around each building. What does "PD" stand for?SDE: PD stands for Perimeter Drain. See also architectural drawings for more information.3
14Will irrigation be included in the "Site Mechanical Utilities" CLIN and planting included in the "Site Preparation and Improvements" CLIN? Please advise.ARG: Please include the irrigation system under site improvements.3
15Are the supports for utilities on the bridge existing?ARG: No.3
16What are the utility supports on the bridge made out of?ARG: Expected to be made out of steel, galvanized, bonderized, painted.3
17On the Paramount site, sheet A3.0, key note 1 calls for non-combustable wall board. What material are we to install here? Please advise.ARG: 1/2" cement boad, per wall types D, F, & G detail 2/ A9.0.3
18At the pavilion building, it is calling for 5/8'' exterior gyp board behind the board and batten cement board. Please advise on what material to provide, i.e. standard exterior gyp sheathing or a glass mat material such as Dens Glass?ARG: Basis-of-design: USG Securock, UltraLight Glass-Mat, Type X, or approved equal3
19In the barn building, Janitor room 108, the RCP on A6.0 is contradicting. Please advise on what the ceiling material is.ARG: This should be keynote 2: framed gyp bd ceiling.3
20On the building foundations, the plans call for fluid applied waterproofing on the footings (Paramount A8.0 - A8.3). Can we get a spec on this?ARG: Basis-of-design: Grace, Procor, or approved equal.3
21On Rocky Oaks site, is an enclosure screen required as shown on C7.2?SDE: No, not required.3
22On Rocky Oaks site, sheet A1.4 Key note 05-01 states fire protected steel moment frame. Are we to put some sort of fire coating on this and if so, can we get a spec on it?ARG: No, there is no rating requirement and it is protected by the fiber cement trim.3
23Will fluid applied waterproofing need to be installed around the footings on the Rocky Oaks Ranch buildings like the Paramount buildings?ARG: No.3
24Are these projects required to have direct digital controls?3
25Per Spec Section 01 50 00 Temporary Facilities And Controls – page 174 of 1340 Section 2.1 Materials Subsection B requires concrete bases at all temp fence posts. Can the contractor utilize sand bags in lieu of concrete bases at each T-stand base?ARG: This is acceptable, galvanized bases with sandbags are an altenative in the standard NPS specifications.3
26Is the electrical hookup permit costs from SCE incorporated into the allowance, or is it separate?ARG: SCE has confirmed that this is incorporated int othe allowance.3
27Per Spec Section 01 50 00 Temporary Facilities And Controls – page 176 of 1340 Section 3.2 Temporary Utility Installation, Subsection H Electrical Power Service and H1: Once electrical infrastructure is setup for the project (e.g. proposed onsite transformer is installed and energized and connected to a temp subpanel or permanent supanel), can we run above grade SO cords to electrical distribution equipment, or do we need to bury all temp electrical in the ground?IEI: We take no exception as this is a means of method.3
28Per Spec Section 01 67 00 Product Requirements – page 211 of 1340 Section 3.1 Protection After Installation, Subsection A which requires coverings to protect installed materials from damage: Can you please elaborate on which materials are required to be protected?ARG: This is a general statement and direction to protect installed materials as necessary.3
29Are the EV charging equipment contractor responsibility to procure and install?IEi: Yes, refer to Spec Section 262653(2.2) for EV Charging rating3
30The civil plans indicate EV charging locations and refer to electrical plans for more info. Where is the EV charging information located as we cannot find any on the electrical site plan?IEI: If this refers to the EV charging station for the ADMIN and RESIDENTIAL bldg parking lot, the electrical requirements are specified in E1.1 keynote 8. Also, refer to single line for more info.3
31Is the contractor required to include vapor mitigation systems for slab on grade flooring systems where moisture will affect the warranty of the flooring system, or should we just include moisture testing and reporting per the specification and determine if vapor mitigation systems are required based on the results of the moisture test/report?ARG/SOHA: A vapor barrier is included in Section 033000.3
32Per the Paramount Ranch plan C2.2, there is a note to reconnect existing laterals. What is the size of the laterals being reconnected?SDE: Size of (e) laterals are not known. Assume 1" laterals. Contractor to confirm in field.3
33Per the Rocky Oaks plan C1.1, the domestic water valves are not shown at tee/wye branches. Are valves needed at the branches?SDE: Yes.3
34Per the Rocky Oaks plan C1.1, the domestic water line that runs to Housing Unit 1 has four-meter boxes shown. What is the service size for these meter boxes?SDE: 1.5" meter box.3
35Per the Rocky Oaks plan C1.1, there is a note for water, sewer, and electrical stubs for future RV pads. Is the service stubs at the location of the arrows or are the stubs to the end of the dashed line? Also, the top two pads have a dashed line connecting to the fire water service. Is the fire water service being extended to the RV pads?SDE: Service stub is to the location of the arrows. Fire Water Service is not being extended to the RV pads3
36Division 28 10 00- 2 Part 2 Products Sect 2.1 : Please confirm Genetec Synergis is an approved equivalent since it is listed as the VSSIEI: Genetec is one of the listed manufacturers under 28 23 00, 2.1B. The Synergis model is acceptable.3
37Division 28 Specifications. Please confirm each site is a stand alone system and there is no requirement for either to have access to other site systemsIEI: Each building is a standalone system3
38Paramount Drawing pages T3.0 - T3.1 shows the supposed Telecom Backbone Diagram and Security Camera Diagram. Confirm who is providing back bone because it seems we are only providing patch cords between the camera and switch. The Security RFP says nothing about needing to add Switches, Patch Panels, or fiber between the buildings.

See also Div 28 23 00-8 Sect 2.6

IEI: Backbone cabling and station cabling is provided by the Telecommunications Contractor.3
39Paramount Ranch, Barn, A6.0 Plans discrepancy: Janitors Closet indicates note #3 corrugated metal panels, but the plans show Gypsum Board Ceiling. A/E please advise the correct ceiling.ARG: This should be keynote 2: framed gyp bd ceiling.3
40Paramount Ranch, Site Electrical C2.2 Utilities key Notes #21 “Conduit for power, SAP See SoCal Edison drawing for electrical design.” A/E please provide SCE drawings.ARG: SCE design drawings are avaiialbe for Paramount Ranch and Rocky Oaks. These show the conduit infrastructure and transformer pads to be provided by the contractor for SCE.3
41Specification sections 06 10 00 Rough Carpentry, 06 13 00 Heavy Timber Construction, 06 13 26 Heavy Timber Trusses, 06 16 00 Sheathing, 06 20 00 Exterior Finish Carpentry 12 32 00 Manufactured Wood Veneer-Faced Casework, states that “FSC Pure or FSC Mixed Credit” wood will need to be provided. Not only is this lumber costly, but also has long lead times. Please confirm FSC lumber is required for the above-mentioned specification sections.ARG: Current Guiding Principles for Sustainable Federal Properties call for 60% of wood products used by cost to be FSC certified so that target should be met.3
42Due to long lead time on various items on this project, we are requesting an additional 90 days added to the project duration to procure required materials. If bid option CLIN 5 on the Rocky Oaks site (administration building) is awarded, we request an additional 30 days beyond base bid. Also, if bid option CLIN 8 on the Paramount Ranch site (small event building) is awarded also we request an additional 30 days beyond base bid. A/E please advise.The project duration is going to be increased from 365 calendar days to 450 calendar days please see Amendment 4 with revised contract clause 52.211-10.3
43Rocky Oaks, Residential, Sheet A1.3 and A1.4, Floor Plan Key Notes, 10-01 “Provide corner guards at outside Corners. TYP.” A/E please confirm that all outside corners including bedrooms, living rooms, and etc. for all the units.ARG: Yes.3
44Rocky Oaks, there’s fire extinguishers spec section and detail 6/A9.8 but zero are indicated on the plans. A/E please verify if any are required for this part of the project.ARG: For Administration Building provide (2) cabinets and extinguishers at interior at gridlines 3-F and 5-F. For Residential building provide one cabinet and extinguisher per unit, at location selected by Contracting Officer.3
45Section “Instructions for the Submission of offers”, paragraph E.3, Factor 2 asks Offerors to submit an organizational chart. We respectfully request that the Government consider excluding a 1-page organizational chart from the 3-page limit for this factor.The organizational chart does not count towards the 3-page limit. The limit applies to the narrative and any pictures provided.3
46The proposals are currently due on 10/31/2022, and the RFI deadline is 10/17/2022. As of 10/13/2022, a site visit has not yet been scheduled. We respectfully request that when the site visit is scheduled, the Government also extend the proposal due date and RFI deadline so that Offerors have at least one week after the site visit to submit RFIs, and three weeks after the site visit to prepare and submit proposals.Please refer to Amendment No. 3 for site visit information and refer to the latest amendment for the current proposal submission deadline.3
47Section “Instructions for the Submission of offers”, paragraph E.3, Factors 4 and 5 reference “key trades.” Please provide a definition of a “key trade.”It is left to the offeror's discretion to determine what its key trades are in conjunction with how the work is to be accomplished.3
48Paramount finish schedule A2.10 shows 101 Barn Seating to receive CONCST-1-stained concrete. Floor plan A2.0 shows keynote 2 in that area which is for sealed concrete. Please clarify if Barn seating gets stained or sealed concrete. Same case with 401 Small Event Seating.ARG: Stained and sealed at Barn and Small Event3
49SMALL EVENT BLDG-Plese clarify the interior siding. Sheet A5.6 calls out wood siding 8"

plank but not the wood type or whether the planks are T&G, ship lap, etc. Also what type of wood is to be used, the Finish Carpentry specs indicate Western Red Cedar for casings, does that mean that the batts and build outs are WRC and the plank siding is clear fir (meaning vertical grain) Please clarify

ARG: Small Event interior siding is butt joint, for material see spec section 06 20 00, article 2.1-D-2: Board Paneling3
50PAVILION BLDG-Sheet A5.4 indicates that there is Hardie Fiber Cement Board between the

3x8 purlins. The purlins are installed 36" OC with nothing but the 1 1/8" roof sheathing. How is the FCB inst::llled to the sheathing and is there any perimeter trim around each purlin

ARG: The cement board is installed directly to the underside of the sheathing, see wall sections 1 & 2/A8.2 , and detail 10/A8.53
51ADMIN BLDG-Sheet S2.1, Grid Line G, the exposed 6x8 posts are called out pressure treated. Please clarify if this is correct since the posts are exposed.
SOHA: Call out should for exterior exposed posts incorrect, they should not be PT. See note 9.3
52RESIDENTIAL BLDG-Sheet S2.3, the same issue as noted in Para 3, the plans indicate that the stair stringers and exposed beams are pressure treated and exposed. Please clarify this is correct
SOHA: Residential building should be PT at the porch, 4x6 rafters at eaves shall be redwood or alaskan cedar grade 1.3
53RESIDENTIAL BLDG-Sheet S2.3, the 3x6 decking is noted as pressure treated and exposed. Please clarify this is correct, also is the decking T&G or do the planks butt each other. We

recommend T &G

SOHA: PT for residential building with butt joints.3
54PAVILION-Sheet S2.3, Grid Lines A and C, the plans do not indicate how the 6xi2 beams

and truss are attached to the 8x8 posts. Will these connections require ECCL68 caps at each

connection.SOHA: Connection detail deferred since truss manufacturer will dictate.3
55PAVILION-Sheet S2.3, the plans reflect some type of hardware at the fascia to outrigger
attachment. Please clarify the connection. Also, the plans reflect Det 8/S6.4, which doesn't exist.SOHA: Detail callout should be 9/S6.4.3
56Rocky Oaks - Rough carpentry specs 061000 part 2 producs 2.1.B indicates that wood is to be FSC Certified. Currently FSC is not available due to supply problems. Can this requirement be removed.ARG: Current Guiding Principles for Sustainable Federal Properties call for 60% of wood products used by cost to be FSC certified so that target should be met.3
57Rocky Oaks - Rough carpentry spec 061000 part 2 products 2.1D reflects moisture content to be 19% is this before covering?SOHA: Yes, before covering3
58Paramount Ranch - Rough Carpentry spec 061300 part 2 item 2.2C reflects the timber moisture is 19% at time of dressing. Roack Oaks Rough Caprenty spect does not indicate that the timer (5" and over in size) is to be 19%at time of dressing. Please advise how to bid this
SOHA: Spec 061300 is for heavy timber. Heavy timber is exposed, so will never be covered, hence spec saying 19% max at time of dressing.3
59Paramount Ranch - Sheet S2.1 Note 9 states that all exposed lumber shall be either redwood or alaskan cedar grade #1. Does this include the 6x12 beams, 4x6 roof rafters, all exposed fascia and exposed 2x6 decking. Does this note apply to all buildings or just the Admin. Bldg. It appears taht every set of plans have different requirements. Please advise.SOHA: All exterior exposed lumber shall be redwood or alaskan cedar grade #1 or better. There is to be no exposed PT wood on the Paramount Ranch buildings.3
60Rocky Oaks – Site Utilities C1.1 and C1.2 indicates “Bollard SLP, TYP” around the transformer. Referred to SLP, L1.2 indicates “pad mounted transformer and bollards. See Civil engineer’s drawings.” 01/L2.02 drawing show a Bollard for RV Stall Marker and 01/L3.3 Light Bollards. A/E please verify which type of bollards should be use.SDE: For purposes of bidding, the wood bollard on detail 01/L2.02 can be replaced with a 6" concrete filled schedule 40 steel pipe. Deepen the concrete footing 24" to 48".3
61Rocky Oaks – Site Utilities for the Transformers pads size. The documents do not clearly show the dimensions and requirements for the transformer pads. A/E please adviseSDE: See SCE drawings for more information.3
62Paramount Ranch Specs Section 01 67 00 (Page 185) Product Requirements, 1.3 Submittals, 4. Chain of Custody: Submit chain-of- custody documentations for sustainable forestry for these products; Wood Door and Windows. Spec section does not indicate certified wood, FSC certification required for wood doors and wood windows. A/E please verify doors and windows do not require FSC certification.ARG: Confirmed.3
63Paramount Ranch, Site and Utility Plans do not show any existing utilities to be remove, demo, and/or abandon in-place. We’re assuming there’s existing utilities to the existing buildings. A/E please advise.SDE: Exisitng utilities on bridge to be removed and replaced. Other disused utilities shall be locally removed when they conflict with new work, otherwise abandon in place.3
65General A/E please confirm only riser ductwork will require pressure testing. A/E please classify pressure class for testing.IEI: Refer spec 23 05 93.3
66Paramount Ranch, per Keynote 9 on M2.0, Keynote 5 on M2.2 and Keynote 4 on M2.5, the drawings call for a piping stub out above ceiling for future units. A/E please advise on requirements for stub out.IEI: Coordinate with manufacuter for refrigerant pipe size per not 9 on M2.0 and note 4 on M2.5.3
6715 Paramount Ranch, per sheet M2.2, there are two callouts for Keynote 9; however, Keynote 9 is not defined. A/E please advise on requirements for Keynote 9.IEI Response: note 9 should be "interlock motorized damper with fan, close the motorized damper when exhaust fan is not in operation"3
68Paramount Ranch, per sheet keynote 6 on M2.4 and keynote 8 on M2.2 call out for a motorized dampers to interlock with the associated fan. Will local status (position sensor) or display be required to indicate position? A/E please advise.IEI: Local status ( position sensor) will required.3
69Paramount Ranch, per sheet keynote 6 on M2.4 and keynote 8 on M2.2 call out for a motorized dampers to interlock with the associated fan. Will local status (position sensor) or display be required to indicate position? A/E please advise.
IEI: Local status ( position sensor) will required.3
70Paramount Ranch, The Electrical/Telecom Room 204 is to have a T-stat for EF-4. Currently there are no conditioning capabilities in that room. A/E please advise if conditioning is required, if not please confirm the T-stat should be considered a fan switch.IEI: No AC required for electrical/ telcome room. EF-4 control to maintain room temperature. Fan will be turn on when the room temperature exceed the setpoint. Refer sequence on spec 23 09 33.3
71Paramount Ranch, Current duct support details on sheet M6.2 show sway braces and ATR, which is typically used for seismic applications. It is understood that structural attachments will be reviewed as a submittal in the future. A/E please provide gravity load details for ductwork.IEI: Per spec 23 05 48 contractor to provide calculation to review3
72Rocky Oaks, per Keynote 6 on M2.1 states that ductwork is to be connected to a range hood. A/E please advise on the need for firewrap and if applicable, any termination details.IEI: No firewrap is required.3
73Rocky Oaks, A/E please confirm design intent and termination point for duct in red and the associated riser. Keynote 1 states that this is to be connected to the water heater. Keynote 4 indicates the water heater vent. A/E please confirm if Keynote 4 is to be for a water heater flue.IEI: The water heater is electrical heat pump not gas fired. No gas fired equipment flue will be required.3
74Rocky Oaks, per Keynote 11 on M2.2 states there is to be an exhaust riser. It appears that this riser is to be connected to a range hood from level 1 to the roof. A/E please confirm the need for firewrap and termination details for level 1 and level 2.IEI: No firewrap is required.3
75Rocky Oaks, Current duct support details on sheet M6.2 show sway braces and ATR, which is typically used for seismic applications. It is understood that structural attachments will be reviewed as a submittal in the future. A/E please provide gravity load details for ductwork.IEI: Per spec 23 05 48 contractor to provide calculation to review.3
76Paramount Ranch, 7/A8.8 shows B.O.D. Krieger. There are no specs section for Metal door types KK(Barn) and LL(Small Event Building). A/E please provide specs.ARG: Additional specification sections are provided.3
77Division 28 10 00- 2 Part 2 Products Sect 2.1 : Please confirm Genetec Synergis is an approved equivalent since it is listed as the VSSIEI: Genetec is listed in Section 282300. Synergis is an acceptable model.3
78Division 28 Specifications. Please confirm each site is a stand alone system and there is no requirement for either to have access to other site systemsIEI: Each building is a stand alone system.3
79Paramount Drawing pages T3.0 - T3.1 shows the supposed Telecom Backbone Diagram and Security Camera Diagram. Confirm who is providing back bone because it seems we are only providing patch cords between the camera and switch. The Security RFP says nothing about needing to add Switches, Patch Panels, or fiber between the buildings.

See also Div 28 23 00-8 Sect 2.6

IEI: Backbone cabling and station cabling is provided by the Telecommunications Contractor.3
80Paramount: The specifications manual (pg. 154 of 1318) Section F. Site Enclosure Fence states that before construction operations begin, we must furnish and install chain link fencing to prevent people/animals from easily entering the site except by entrance gate.ARG: Yes, furnish fencing. Logistics plans have been marked up with approximate extents. For Paramount the minimum expectation is to enclose the building site with chain link fencing and use orange barrier fencing for other locations when work is in progress.

For Rocky Oaks the minimum expectation is to enclose the two building sites with chain link fencing and use orange barrier fence for other locations when work is in progress.

Coordinate alignment and locations with tree and plant protections specification requirements in Sections 011100 and 015639.3
81Paramount: Subsection F1. On the same page explains the extent of the fence is to enclose entire or a portion deemed sufficient to accommodate construction operations.ARG: See response to question 80.3
82The erosion control plan for Rocky Oaks on C4.0 indicates a construction fence in the legend, but it does not appear to be shown on the planARG: See response to question 80.3
83The Paramount Ranch erosion control plan on C4.0 does not show a construction fence on the drawing or legend. Therefore, please indicate the extent of temp fencing that needs to occur at each site. Is the intent to block entrance from the frontage of each property, or is the intent to surround the entire project area?ARG: See response to question 80.3
84Please confirm that there is no permanent perimeter fencing required on either site.ARG: Confirmed, no permanent perimeter fencing.3
85Factor 2 Management Approach. There is a 3 page limitation. Can you confirm that the org chart is in addition to the 3 page limit, and not included as one of the 3 pages?Correct3
86There was no mention of resumes to be included in the proposal, nor was there any room for resumes in the described proposal layout. Please confirm you do not want resumes included.3
87Now that Amendment 3 pushed the due date out by one week, we are assuming that the RFI’s push out too, and that we have through November 28 to submit RFI’sIn accordance with the clause, Instructions for the Submission of Offers and Other Information (Section L of the solicitation), pre-proposal questions can be submitted up to 10 calendar days prior to the due date and time for proposals.3
88Rock Oaks, T4.1 &T5.4, Note 11, Who is responsible for providing & Installing the Recessed Media Enclosure shown on Sheets T4.1 Keynote #11 & T5.4?IEI: The Electrical Contractor is to provide the recessed media enclosure.3
89Rock Oaks, T5.5, call out 2, Who is responsible for providing and installing the Outdoor wall mount Enclosure shown on Sheet T5.5?IEI: The Electrical Contractor is to provide the wall mount enclosure.3
90Rock Oaks, T1.1, Note 4, Who is responsible for providing and installing the NEMA-4R wall mount Enclosure shown on sheet T4.1 Keynote #9?IEI: The Electrical Contractor is to provide the wall mount enclosure.3
91Rock Oaks, T1.1, Note 4, Keynote #4 on Sheet T1.1 states that, "Cabling to Lakretz Building TBD by NPS for future Connectivity" Please confirm there is NO cabling requirements or scope of work for the Telecom Contractor at the Lakretz Building.IEI: There is no cabling requirements to the La Kretz building.3
92Rock Oaks, T1.1 & T4.1, ISP Cable, Riser diagram shows Copper, Fiber & Coax cable feeding the new Admin Building & the new Residential Building from the existing service provider vault. What are the connection requirements in this ISP Vault? Will the ISP be delivering the cable to the IDF's in the Admin & Residential Buildings, or only to the ISP vault? Please provide further connection details in the ISP Vault.IEI: ISP to provide cabling to Admin and Residential buildings.3
93Paramount, 271300, T3.0, Fiber/Copper Backbone Riser Diagram Sheet notes: 7 & 8 indicate (1) 25-pair copper and (1) SM 24 Strand fiber cable both feeding the Restroom Building elec/telecom 204. The diagram does not indicate where the cables are coming from and who is responsible for pulling these cables into this location. Please provide detail for the location of these cables so we can determine the pulling distance.IEI: This cabling is to be fed from the existing gateway in the Longhorn building.3
94Paramount, POE Hybrid System, T4.1, for the POE Hybrid System please clarify who is responsible for providing & installing the following items shown on sheet T4.1 - #3 1. Oberon 3032/32" Bollard. 2. NEMA 4 Enclosure inside Bollard. 3. Ground bus bar insdie NEMA Enclosure. 4. Access Point inside bollard. Please provide part numbers for items required by Telecom Contractor.IEI:1. Civil contractor to provide the footing for the bollard. Oberon Part # 39-303X-FOOTING-KIT

2. NEMA 4 enclosure to be provided by the Telecommunications Contractor. Oberon Part # 39-1026-1084-WORKBOX

3. Ground Busbar to be provided by Telecommunications Contractor.

4. Access Point inside Bollard to be provided by NPS IT department.3
95Paramount, POE Hybrid System, T3.1, for the POE Hybrid System please clarify who is responsible for providing & installing the following items shown on sheet T3.1 - #3 1. Media Converter. 2. Power Surge Protectors. 3. POE Surge Protector. 4. Outdoor Wireless Access Point. Please provide part numbers for items required by Telecom Contractor.IEI: 1, 2 and 3. Hybrid PoE system is to be coordinated with Leviton and they will provide part numbers and necessary components.
4. Outdoor Wireless Access Point to be OFCI.3
96Paramount, WAPS, Plans/Specs, Will the Wireless Access Points as well as the WAP mouting brackets or enclosures be OFCI or CFCI. Please provide specs/Part# if they are CFCIIEI: All Access Points and mounting hardware to be OFOI.3
97Paramount, 275320, Cable Television Distribution System, Spec 275320 Cable Television Distribution System is not reflected anywhere on the plans. Is this spec required in the scope of work? If yes, Please provide details on plans.IEI: Cable TV is not required at this time but was added for future use as needed.3
98Since the insurance requirements does not required builder's risk. Does the NPS has builder's risk cover under thier policy? If yes, does the coverage include GCs?NPS does not carry an insurance policy. The NPS is a federal entity and as such is self-insured. The need for builder's risk insurance is at the discretion of the contractor and should be included in their pricing as appropriate.3
99Regarding the price proposal alone. What is the basis of award?There is no basis of award for the price proposal alone. Reference Section M of the solicitation for basis of award.3
100Is the purpose of the Bid Price Schedule or the schedule of values to remove or add scope of work for the project?No, that is not the purpose of the Contract Price Schedule or the Schedule of Values. Base items will be awarded, while option items are optional and may be awarded at the government's discretion and in accordance with the terms of the contract.3
101According the instruction to bidders a schedule of values need to be turn in per each line of per the Price Schedule. In order to avoid data entry errors and discrepancies, can the owner consider and allow the SOV to be email within 24 hours after the bid deadline?
No, the Schedule of Values must be submitted with the Contract Price Schedule as part of the proposal package.3
102Paramount, 274116, Assitive Listening, T3.2 states Assistive Listening System is OFOI, but 274116 3.8 asks to provide. Please confirm if ALS is OFOI, OFCI or CFCI.IEI: Assistive Listening System is OFOI.3
103Paramount, T3.2, AV Cabling, Much of the AV equipment listed on the Equipment schedule is OFOI. Please confirm what AV cabling is OFOI, OFCI, CFCI.IEI: All cabing from the 3 gang wall plate to the devices (projectors, speakers and Projector Screens) is to be CFCI.3
104Paramount, T4.5/T3.2, Barn Control & AV Plate, Please confirm how relay will be routed for Barn's 3 projection screens.IEI: Routing from 3 Gang box (Relay) to be in conduit for its entire pathway.3
105Paramount, T3.2, Projector Control /Panasonic Digital Link, Panasonic Digital Link supports 4K signal, but not RS-232, from the DMPS3-4K-150-C. Please confirm how projectors will be controlled.IEI: Projectors will by controlled visa HD Base T digital link.3
106Paramount, T3.2, Portable AV rack connections, Are connections to Portable AV Rack CFCI?IEI: Connection to the portable AV rack to wall 3 gang box are OFOI.3
107Paramount, T3.2, POE Switch, Typical AV diagram 1/T3.2 shows PoE switch as keynote 4. Keynote 4 on AV Schedule is the Listen LS-90 Transmitter. PoE switch does not appear on the AV Equipment schedule. Is PoE Switch OFOI, OFCI, CFCI?IEI: PoE switch is OFOI.3
108Paramount, 274116, AV Products, 274116 Part2 lists many products that do not appear on AV Schedule or typical av diagram. Please confirm these products are not part of this project. (Ex: Middle Atlantic SRSR-2-24, Tascam CD-200, Tascam CD-200i, Biamp AudiaFLEX Audia SOLO, IP2, OP2e, AEC-2HD, QSC CX302V, JBL Control 26CT, 126WT, MTC-126RIF, Control 28T-60WH, MTC-28V, MTC-28V, MTC-28/25CM, Listen LS-03 LS-04.IEI: Products listed on T3.2 are the only products required for this project.3
109Rocky Oaks, 274116, AV, Please provide AV system sheet for Rocky Oaks comparable to Paramount Ranch T3.2:

AV Equipment schedule indicating OFOI or OFCI equipment.

Typical AV Diagram Rack elevations Mounting details.

IEI: AV for Rocky Oaks is for pathways only as discussed with NPS. 3