This document contains questions and answers regarding Solicitation No. 140P2022R0066 from the National Park Service for the rebuild of the Paramount Ranch and Rocky Oaks Administrative Area in Santa Monica Mountains National Recreation Area in Agoura Hills, California. The questions and answers provide clarification that small business offerors are not required to submit a small business subcontracting plan as required by the solicitation. Additionally, the correct email address for the point of contact Gabriel Castellanos is provided.

View the file

Other files

File Type Posted
B09_A6_Final_Q_A_Responses_0006.xlsx XLSX spreadsheet
Sol_140P2022R0066_Amd_0006.pdf PDF
B09_Amd_5_Schedule_of_Changes_Q_A_0005.pdf PDF
Sol_140P2022R0066_Amd_0005.pdf PDF
B09_SAMO_P_R_Sign_in_sheet_0004.pdf PDF
SAMO_Bidding_Questions_Documents_0004.zip ZIP file
B09_A3_Rev_Solit_Clauses_Construction_0004.pdf PDF
B09_SAMO_P_R_Business_Card_Sheet_0004.pdf PDF
Sol_140P2022R0066_Amd_0004.pdf PDF
B09_A3_Q_A_to_AE_TEAM_REV2_Final_Copy__0004.xlsx XLSX spreadsheet
Sol_140P2022R0066_Amd_0003.pdf PDF
B09_SAMO_-_303051_PR__310132_RO_-_Pre-Bid_Walkthrough_Directions_0003.pdf PDF
Sol_140P2022R0066_Amd_0002.pdf PDF
B09_A2_Rev_Solit_Clauses_Construction_0002.docx DOCX document
B09_A2_Q_A_0002.xlsx XLSX spreadsheet
Sol_140P2022R0066_Amd_0001.pdf PDF
B08_Atch__10_SAMO_Rebuild_Paramount_Ranch_Final_100__CD_Blank_Contract_Price_Schedule.xlsx XLSX spreadsheet
B08_Atch__5_DBA_WD_CA20220022_09022022.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part2.pdf PDF
B08_Atch__7_Solit_PSP_Vol_I_PastPerf.docx DOCX document
B08_Atch__6_Solit_PSP_Vol_I_ProjExp_REQD.docx DOCX document
B08_Atch__9_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Atch__8_Solit_PSP_Vol_II_GenRefs.doc DOC document
B08_Atch__12_Subcontracting_Plan.doc DOC document
B08_Atch__3_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Specifications.pdf PDF
B08_Atch__4_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Drawings.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part1.pdf PDF
B08_Atch__2_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Drawings_Part3.pdf PDF
Sol_140P2022R0066.pdf PDF
B08_Atch__1_SAMO_Rebuild_Paramount_Ranch_100__Final_CD_Specifications.pdf PDF
B08_Atch__11_SAMO_Rebuild_Rocky_Oaks_100__Final_CD_Contract_Price_Schedule_Blank.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 140P2022R0066, SAMO-303051/310132 Questions Answers Amendment

1 Please provide date/time of the site walk The date/time of the pre-proposal site visit has not been determined yet. When it is, an amendment will be posted to www.sam.gov providing all offerors with the information. 1

We are a Small Business under the SBA criteria for small business.

Per page 1 of the "B08_Atch_12_Subcontracting Plan", and per page 50 of the Solicitation under item 3,it is noted that "SMALL BUSINESS SUBCONTRACTING PLAN: Small business offerors are not required to submit a subcontracting plan;

however, large business offerors shall complete and submit the attached Subcontracting Plan Form in response to the requirements of clause 52.219-9."

But then on page 54 of 55, under Evaluation Factors, under "Volume I --Non-Price Proposal", under "Factor 6 Small Business Participation", it is noted:

"All offerors (both other than small businesses and small businesses) will be evaluated on the extent of proposed participation/commitment to use U.S. small businesses in the performance of this acquisition (as small business prime offerors or small business subcontractors) relative to the objectives and requirements established herein. Small business offerors will receive the maximum credit for this evaluation factor and do not need to submit any documentation supporting this evaluation factor"

Thus the information about who fills out the Small Business Subcontracting Plan is in conflict in the solicitation.

The Small Business Subcontracting Plan identifies subcontracting goals for a variety of disadvantaged company times. Since we are a Small Business and are apparently not required to fill out the Subcontracting Plan, then we will not be providing any information in our proposal related to percentage work performed by various disadvantaged business categories, as called out in the Plan under Items "2", "3", and on through item "11".

Can you confirm and/or clarify this?

Small businesses are not required to submit a Small Business Subcontracting Plan. The goal of both of these referenced sections is to encourage small business participation. Small businesses prime contractors already fulfill this by default and do not need to provide any additional information.

3 Outlook indicated that the email address for Gabriel Castellanos was not valid; is there a correct email address for him? Gabriel's email address is gabriel_castellanos@nps.gov 1