This document provides details for a federal contract solicitation seeking bids to replace variable air volume assemblies at the West Palm Beach Veterans Affairs Medical Center. The Department of Veterans Affairs Network Contracting Office 8 is soliciting bids to replace 1,184 variable air volume boxes in the main hospital and 119 boxes in the community living center. Bids are due by December 2, 2021. The contractor will be responsible for providing all labor, materials, tools and equipment to replace the air terminal units, reheat coils, control valves, and associated direct digital controls and thermostats. The solicitation number is 36C24822R0002 and the project drawings provide additional details. The contract is set aside for Service-Disabled Veteran-Owned Small Businesses. The award is anticipated to be a firm-fixed-price contract between $10-20 million. The solicitation will be issued on October 28, 2021 and all information will be posted on sam.gov.

View the file

Other files

File Type Posted
Award Notice 36C24822C0036.docx DOCX document
36C24822R0002 0006.docx DOCX document
36C24822R0002 0005.docx DOCX document
Combined Specifications 548-16-612 12152021.pdf PDF
548-16-612 VA West Palm Beach Replace VAV Drawings 12152021.pdf PDF
36C24822R0002 0004.docx DOCX document
Brand Name JOFOC VAV Box Replacement Project execute_Redacted.pdf PDF
36C24822R0002 0003.docx DOCX document
36C24822R0002 0002.docx DOCX document
23 09 23 Direct Digital Control System For HVAC.pdf PDF
MH601 Drawing Rev 2.pdf PDF
Site VIsit 36C24822R0002 Sign In_Redacted.pdf PDF
36C24822R0002 0001.docx DOCX document
Attachment M Requirement Specifications.pdf PDF
Attachment A General Decision Number FL20210220 10012021.pdf PDF
Attachment D Pre-Award Contractor Safety and Environmental Record Form.pdf PDF
Attachment Q Sample HVAC Equipment Schedule.pdf PDF
36C24822R0002_1 11092021.pdf PDF
Attachment H Project Price Breakdown.xlsx XLSX spreadsheet
Attachment E Above Ceiling Permit 11-10-17.pdf PDF
Attachment K PAST PERFORMANCE QUESTIONNAIRE.pdf PDF
Attachment J Experience Information Sheet.docx DOCX document
Attachment C Hot Work Permit.pdf PDF
Attachment B West Palm Beach VAMC Campus Map.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LOCATION MAP

N

F

A

D

I

ET

D S T

N U

E

TM

AP

R

E NT O

S

A

T SE FO

REM

ACI

N

VE RATE

A

FAI R

F

S VA Medical Center West Palm Beach

7305 N. Military Trail West Palm Beach, Florida 33410

STATE OF FLORIDA

N.T.S.

N

WEST PALM BEACH

KEY WEST

MIAMI

TAMPA

ORLANDO

PENSACOLA

TALLAHASSEE

GAINESVILLE VAMC

JACKSONVILLE

OCALA CBOC

VILLAGES CBOC

VALDOSTA CBOC

WEST

PALM

BEACH

BUILDING 1

BUILDING 3

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. of

CONSULTANTS: ARCHITECT/ENGINEERS:

group mes

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

550 North Reo Street Suite 203 Tampa, FL 33609 813.289.4700

COA # 8304

DALE A. BACIK, P.E.

FULLY SPRINKLERED

8/

/2

:2 5:

A

M

REPLACE VAV BOXES AND

UPGRADE TO DIRECT DIGITAL

CONTROLS

LOCATION, SITE PLAN, AND SHEET

INDEX

WEST PALM BEACH, FLORIDA

08/20/2018 REM/DAB REM

548-16-612

01, 03

GI001

EP400 ENLARGED ELECTRICAL PLANS

EP401 ENLARGED ELECTRICAL PLANS

EP402 ENLARGED ELECTRICAL PLANS

EP403 ENLARGED ELECTRICAL PLANS

EP501 ELECTRICAL DETAILS

EP601 ELECTRICAL SCHEDULES

EP602 ELECTRICAL SCHEDULES

EP603 ELECTRICAL SCHEDULES

EP604 ELECTRICAL SCHEDULES

EP605 ELECTRICAL SCHEDULES

EP606 ELECTRICAL SCHEDULES

EP607 ELECTRICAL SCHEDULES

INDEX OF DRAWINGS

DRAWING

NUMBER DRAWING TITLE

E001 ELECTRICAL LEGEND, NOTES AND ABBREVIATIONS

EP110 BUILDING 1 BASEMENT OVERALL PLAN

EP110i-1-R BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - EAST - POWER EP110i-2-R BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER EP110i-3-R BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - WEST - POWER

EP111 BUILDING 1 FIRST FLOOR OVERALL PLAN

EP111-4-R BUILDING 1 FIRST FLOOR RENOVATION PLAN - CHAPEL - POWER

EP111i-1-R BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP111i-2-R BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER EP111i-3-R BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - WEST - POWER

EP112 BUILDING 1 SECOND FLOOR OVERALL PLAN

EP112i-1-R BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP112i-2-R BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER EP112i-3-R BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - WEST - POWER

EP113 BUILDING 1 THIRD FLOOR OVERALL PLAN

EP113i-1-R BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP113i-2-R BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER EP113i-3-R BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - WEST - POWER

EP114 BUILDING 1 FOURTH FLOOR OVERALL PLAN

EP114i-1-R BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP114i-2-R BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER EP114i-3-R BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - WEST - POWER

EP115 BUILDING 1 FIFTH FLOOR OVERALL PLAN

EP115i-1-R BUILDING 1 FIFTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP115i-2-R BUILDING 1 FIFTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER

EP116 BUILDING 1 SIXTH FLOOR OVERALL PLAN

EP116i-1-R BUILDING 1 SIXTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP116i-2-R BUILDING 1 SIXTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER

EP117 BUILDING 1 SEVENTH FLOOR OVERALL PLAN

EP117i-1-R BUILDING 1 SEVENTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP117i-2-R BUILDING 1 SEVENTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER

EP118 BUILDING 1 EIGHTH FLOOR OVERALL PLAN

EP118i-1-R BUILDING 1 EIGHTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER

EP119 BUILDING 1 NINTH FLOOR OVERALL PLAN

EP119i-1-R BUILDING 1 NINTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - POWER EP119i-2-R BUILDING 1 NINTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - POWER

EP131-J-J BUILDING 3 RENOVATION FLOOR PLAN - AREA J - POWER

EP131-J-K BUILDING 3 RENOVATION FLOOR PLAN - AREA K - POWER

EP131-J-L BUILDING 3 RENOVATION FLOOR PLAN - AREA L - POWER

INDEX OF DRAWINGS

DRAWING

NUMBER DRAWING TITLE

MH114-2-R BUILDING 1 FOURTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH114-3-R BUILDING 1 FOURTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - WEST - HVAC MH114i-1-D BUILDING 1 FOURTH FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH114i-1-R BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH114i-1-R-P BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH114i-2-D BUILDING 1 FOURTH FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH114i-2-R BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH114i-2-R-P BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH114i-3-D BUILDING 1 FOURTH FLOOR INTERSTITIAL DEMOLITION PLAN - WEST - HVAC MH114i-3-R BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - WEST - HVAC MH114i-3-R-P BUILDING 1 FOURTH FLOOR INTERSTITIAL RENOVATION PLAN - WEST - PIPING MH115-1-R BUILDING 1 FIFTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH115-2-R BUILDING 1 FIFTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH115i-1-D BUILDING 1 FIFTH FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH115i-1-R BUILDING 1 FIFTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH115i-1-R-P BUILDING 1 FIFTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH115i-2-D BUILDING 1 FIFTH FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH115i-2-R BUILDING 1 FIFTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH115i-2-R-P BUILDING 1 FIFTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH116-1-R BUILDING 1 SIXTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH116-2-R BUILDING 1 SIXTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH116i-1-D BUILDING 1 SIXTH FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH116i-1-R BUILDING 1 SIXTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH116i-1-R-P BUILDING 1 SIXTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH116i-2-D BUILDING 1 SIXTH FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH116i-2-R BUILDING 1 SIXTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL- HVAC MH116i-2-R-P BUILDING 1 SIXTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH117-1-R BUILDING 1 SEVENTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH117-2-R BUILDING 1 SEVENTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH117i-1-D BUILDING 1 SEVENTH FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH117i-1-R BUILDING 1 SEVENTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH117i-1-R-P BUILDING 1 SEVENTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH117i-2-D BUILDING 1 SEVENTH FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH117i-2-R BUILDING 1 SEVENTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH117i-2-R-P BUILDING 1 SEVENTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH118-1-R BUILDING 1 EIGHTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH118i-1-D BUILDING 1 EIGHTH FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH118i-1-R BUILDING 1 EIGHTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH118i-1-R-P BUILDING 1 EIGHTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH119-1-R BUILDING 1 NINTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH119-2-R BUILDING 1 NINTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH119i-1-D BUILDING 1 NINTH FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH119i-1-R BUILDING 1 NINTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH119i-1-R-P BUILDING 1 NINTH FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH119i-2-D BUILDING 1 NINTH FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH119i-2-R BUILDING 1 NINTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH119i-2-R-P BUILDING 1 NINTH FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING

MH131-1-D BUILDING 3 FIRST FLOOR DEMOLITION PLAN - AREA J - HVAC

MH131-1-R BUILDING 3 FIRST FLOOR RENOVATION PLAN - AREA J - HVAC

MH131-1-R-P BUILDING 3 FIRST FLOOR RENOVATION PLAN - AREA J - PIPING

MH131-2-D BUILDING 3 FIRST FLOOR DEMOLITION PLAN - AREA K - HVAC

MH131-2-R BUILDING 3 FIRST FLOOR RENOVATION PLAN - AREA K - HVAC

MH131-2-R-P BUILDING 3 FIRST FLOOR RENOVATION PLAN - AREA K - PIPING

MH131-3-D BUILDING 3 FIRST FLOOR DEMOLITION PLAN - AREA L - HVAC

MH131-3-R BUILDING 3 FIRST FLOOR RENOVATION PLAN - AREA L - HVAC

MH131-3-R-P BUILDING 3 FIRST FLOOR RENOVATION PLAN - AREA L - PIPING

MH501 DETAILS - HVAC

MH502 DETAILS - HVAC

MH503 DETAILS - HVAC

MH601 CONTROLS - HVAC

INDEX OF DRAWINGS

DRAWING

NUMBER DRAWING TITLE

GI001 LOCATION, SITE PLAN, AND SHEET INDEX

MH001 NOTES & LEGEND - HVAC

MH002 SCHEDULES - HVAC

MH003 SCHEDULES - HVAC

MH004 SCHEDULES - HVAC

MH005 SCHEDULES - HVAC

MH006 SCHEDULES - HVAC

MH007 SCHEDULES - HVAC

MH110-1-R BUILDING 1 BASEMENT FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH110-2-R BUILDING 1 BASEMENT FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH110-3-R BUILDING 1 BASEMENT FLOOR RENOVATION - AIR DISTRIBUTION PLAN - WEST - HVAC MH110i-1-D BUILDING 1 BASEMENT INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH110i-1-R BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH110i-1-R-P BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH110i-2-D BUILDING 1 BASEMENT INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH110i-2-R BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH110i-2-R-P BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH110i-3-D BUILDING 1 BASEMENT INTERSTITIAL DEMOLITION PLAN - WEST - HVAC MH110i-3-R BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - WEST - HVAC MH110i-3-R-P BUILDING 1 BASEMENT INTERSTITIAL RENOVATION PLAN - WEST - PIPING MH111-1-R BUILDING 1 FIRST FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH111-2-R BUILDING 1 FIRST FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH111-3-R BUILDING 1 FIRST FLOOR RENOVATION - AIR DISTRIBUTION PLAN - WEST - HVAC

MH111-4-D BUILDING 1 FIRST FLOOR DEMOLITION PLAN - CHAPEL - HVAC

MH111-4-R BUILDING 1 FIRST FLOOR RENOVATION PLAN - CHAPEL - HVAC

MH111i-1-D BUILDING 1 FIRST FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH111i-1-R BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH111i-1-R-P BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH111i-2-D BUILDING 1 FIRST FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH111i-2-R BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH111i-2-R-P BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH111i-3-D BUILDING 1 FIRST FLOOR INTERSTITIAL DEMOLITION PLAN - WEST - HVAC MH111i-3-R BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - WEST - HVAC MH111i-3-R-P BUILDING 1 FIRST FLOOR INTERSTITIAL RENOVATION PLAN - WEST - PIPING MH112-1-R BUILDING 1 SECOND FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH112-2-R BUILDING 1 SECOND FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH112-3-R BUILDING 1 SECOND FLOOR RENOVATION - AIR DISTRIBUTION PLAN - WEST - HVAC MH112i-1-D BUILDING 1 SECOND FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH112i-1-R BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH112i-1-R-P BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH112i-2-D BUILDING 1 SECOND FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH112i-2-R BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH112i-2-R-P BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH112i-3-D BUILDING 1 SECOND FLOOR INTERSTITIAL DEMOLITION PLAN - WEST - HVAC MH112i-3-R BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - WEST - HVAC MH112i-3-R-P BUILDING 1 SECOND FLOOR INTERSTITIAL RENOVATION PLAN - WEST - PIPING MH113-1-R BUILDING 1 THIRD FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC MH113-2-R BUILDING 1 THIRD FLOOR RENOVATION - AIR DISTRIBUTION PLAN - CENTRAL - HVAC MH113-3-R BUILDING 1 THIRD FLOOR RENOVATION - AIR DISTRIBUTION PLAN - WEST - HVAC MH113i-1-D BUILDING 1 THIRD FLOOR INTERSTITIAL DEMOLITION PLAN - EAST - HVAC MH113i-1-R BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - EAST - HVAC MH113i-1-R-P BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - EAST - PIPING MH113i-2-D BUILDING 1 THIRD FLOOR INTERSTITIAL DEMOLITION PLAN - CENTRAL - HVAC MH113i-2-R BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - HVAC MH113i-2-R-P BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - CENTRAL - PIPING MH113i-3-D BUILDING 1 THIRD FLOOR INTERSTITIAL DEMOLITION PLAN - WEST - HVAC MH113i-3-R BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - WEST - HVAC MH113i-3-R-P BUILDING 1 THIRD FLOOR INTERSTITIAL RENOVATION PLAN - WEST - PIPING MH114-1-R BUILDING 1 FOURTH FLOOR RENOVATION - AIR DISTRIBUTION PLAN - EAST - HVAC

Revisions: Date

REVISION 1: UPDATED BY WEST PALM BEACH VAMC 10/01/2021

• THESE DRAWINGS ARE DIAGRAMMATIC IN NATURE AND INDICATIVE OF WORK TO BE PROVIDED (FURNISHED AND INSTALLED) UNDER THIS CONTRACT. DRAWINGS SHOULD NOT BE SCALED. IT IS THE RESPONSIBILITY OF THE

CONTRACTOR TO FIELD VERIFY SPACE ALLOCATED PRIOR TO ORDERING EQUIPMENT.

• PERFORM ALL WORK IN COMPLIANCE WITH ALL VA STANDARDS, GUIDELINES AND SPECIFICATIONS, AND WITH ALL APPLICABLE FEDERAL, STATE, AND LOCAL CODES, REGULATIONS, AND STANDARDS ADOPTED BY THE AUTHORITY HAVING JURISDICTION. IF CONFLICTS EXIST BETWEEN THESE ENGINEERING DOCUMENTS AND CODES, THE MOST

STRINGENT REQUIREMENTS SHALL GOVERN.

• ALL CONSTRUCTION WORK SHALL ALSO MEET THE FOLLOWING CODE REQUIREMENTS:

• FLORIDA BUILDING CODE (FBC) 2014

• FLORIDA EXISTING BUILDING CODE 2014

• FBC MECHANICAL 2014

• FBC PLUMBING 2014

• FBC ENERGY CONSERVATION 2014

• FLORIDA FIRE PREVENTION CODE 2014

• NFPA 1-2015, THE UNIFORM FIRE CODE

• NFPA 101-2015, THE LIFE SAFETY CODE

• NFPA 51B-2014, STANDARD FOR FIRE PREVENTION DURING WELDING, CUTTING AND OTHER HOT WORK

• NFPA 70-2017, NATIONAL ELECTRICAL CODE

• NFPA 90A-2015, STANDARD FOR THE INSTALLATION OF AIR CONDITIONING AND VENTING SYSTEMS.

• NFPA 99-2015, STANDARD FOR HEALTH CARE FACILITIES

• NFPA 241-2013, STANDARD FOR SAFEGUARDING CONSTRUCTION, ALTERATION AND DEMOLITION OPERATIONS.

• THE CONTRACTOR SHALL EXAMINE THE EXISTING CONDITIONS UNDER WHICH HE SHALL OPERATE AND VERIFY THE

EXTENT OF WORK REQUIRED TO COMPLETE THE WORK UNDER THIS CONTRACT.

• CONTRACTOR SHALL COORDINATE AND SEQUENCE DEMOLITION, CLEANING, AND CONSTRUCTION WORK.

• MAINTAIN THE INTEGRITY OF ALL FIRE AND SMOKE RATED WALLS, PARTITIONS, CEILINGS, AND FLOORS. SEAL ALL PENETRATIONS THROUGH RATED ASSEMBLIES WITH FIRESTOP MATERIAL IN ACCORDANCE WITH U.L. REQUIREMENTS

TO MAINTAIN THE ASSEMBLY RATING.

• CONTRACTOR SHALL REFER TO ALL DETAILS FOR PROPER GUIDANCE.

• THE CONTRACTOR SHALL SUBMIT 5 COPIES OF SHOP DRAWINGS AND EQUIPMENT SUBMITTALS FOR ALL PRODUCTS USED ON PROJECT. THE CONTRACTOR SHALL PROVIDE A COMPLETE SUBMITTAL REGISTER SPREADSHEET PRIOR IDENTIFYING ALL REQUIRED SUBMITTALS PRIOR TO START OF WORK. PROJECT MANAGEMENT SOFTWARE MUST BE APPROVED BY THE COR AND WILL BE CONSIDERED ON A CASE BY CASE BASIS. ALL REQUIREMENTS IN

SPECIFICATIONS SECTION 01 33 23 SHALL BE STRICTLY ADHERED TO.

• THE CONTRACTOR IS REQUIRED TO SUBMIT THREE COMPLETE O&M MANUALS IN THREE RING BINDERS AT SUBSTANTIAL COMPLETION. MANUALS SHALL INCLUDE INSTALLATION AND MAINTENANCE DATA ON ALL NEW EQUIPMENT AND MATERIALS, CERTIFIED TECHNICAL PRODUCT DATA, EQUIPMENT SHOP DRAWINGS, SPARE PARTS DATA, ETC. PROVIDE

AN INDEX AND ASSOCIATED DIVIDERS.

• THE CONTRACTOR IS TO MAINTAIN ONE SET OF CONSTRUCTION DRAWINGS ON SITE TO MARK UP AS-BUILT CONDITIONS RED LINE DRAWINGS SHALL BE SCANNED INTO PDF AND PROVIDED TO THE VA AT CLOSEOUT. THE CONSTRUCTION DRAWINGS WILL ALSO BE USED TO IDENTIFY EXISTING CRUSHED/DAMAGED DUCTWORK. PRIOR TO STARTING WORK, EACH AREA IS TO BE INSPECTED BY THE SUPERINTENDENT, VERIFIED BY THE COR AND ANNOTATED ON THE

CONSTRUCTION DRAWINGS.

• ALL PERMITS, FEES, TAXES, ETC SHALL BE PAID BY CONTRACTOR AS PART OF THE TOTAL PROJECT COST.

• THE CONTRACTOR SHALL MAINTAIN A COMPLETE PROJECT SCHEDULE AND SHALL UPDATE THIS SCHEDULE WEEKLY.

ANY CHANGES SHALL BE NOTED AND AN UPDATED SCHEDULE SHALL BE PROVIDED TO THE OWNER.

• CLOSE OUT DOCUMENTS: CONTRACTOR SHALL MAINTAIN A SET OF AS-BUILT DRAWINGS AND KEEP CURRENT DURING CONSTRUCTION OF THE PROJECT. THIS SET IS TO INCLUDE ALL CONTRACT CHANGES, MODIFICATIONS AND CLARIFICATIONS. THIS SET ALONG WITH ALL SHOP DRAWINGS SHALL BE TURNED OVER TO THE ENGINEER AFTER

CONSTRUCTION COMPLETION.

GENERAL NOTES

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

• CONTRACTOR IS RESPONSIBLE FOR VERIFICATION OF FIELD CONDITIONS PRIOR TO BEGINNING WORK AND ORDERING EQUIPMENT, AND COORDINATING NEW EQUIPMENT DIMENSIONS AND MEANS AND METHODS FOR

INSTALLATION WITH FIELD CONDITIONS.

• CONTRACTOR IS RESPONSIBLE TO COORDINATE WITH SUBMITTED EQUIPMENT TO ENSURE ALL INLET/OUTLET CONNECTIONS COORDINATE WITH FIELD INSTALLED DUCTWORK AND MAKE ANY NECESSARY DUCT MODIFICATIONS

TO ENSURE PROPER OPERATION OF MECHANICAL EQUIPMENT.

• SUBMITTALS SHALL MEET SCHEDULED DESIGN CHARACTERISTICS, INCLUDING BUT NOT LIMITED TO CFMS, EAT(DB/WB), ESP, CAPACITIES, VOLTAGES/PHASES, MCA/MOCP, SONES, ETC.

• ALL DUCT CONSTRUCTION, INSTALLATION, AND SUPPORTS ARE TO COMPLY WITH LATEST EDITION OF SMACNA'S

HVAC DUCT CONSTRUCTION STANDARDS METAL AND FLEXIBLE DUCT. SEE SPECIFICATIONS.

• INSULATE DUCTWORK PER SPECIFICATIONS.

• ALL WALL-MOUNTED THERMOSTATS AND/OR TEMPERATURE SENSORS SHALL BE INSTALLED AT AN ELEVATION OF 48" ABOVE FINISHED FLOOR TO THE TOP UNLESS OTHERWISE NOTED ON DRAWINGS. LOCATION OF WALL-MOUNTED THERMOSTATS SHALL BE COORDINATED WITH OTHER TRADES FOR A NEAT APPEARANCE. FINAL LOCATION OF THERMOSTATS SHALL BE COORDINATED WITH AND APPROVED BY THE COR. REPAIR WALL AREA AS NEEDED AFTER

EXISTING THERMOSTAT IS REMOVED AND NEW THERMOSTAT INSTALLED.

• DIFFUSERS/GRILLES SHALL NEVER BE INSTALLED ON SURFACE OF ACOUSTICAL LAY-IN TILE. ALL DIFFUSERS/GRILLES IN LAY-IN CEILINGS SHALL BE LAY-IN PANEL MOUNT. REFER TO SCHEDULE. GYPSUM BOARD

SURFACE MOUNT DIFFUSERS SHALL NOT BE BEVEL MOUNT.

• CONTRACTOR SHALL PROVIDE A COPY OF THE TEST AND BALANCE REPORT BY AN AABC OR NEBB CERTIFIED AGENCY. THIS REPORT MUST BE REVIEWED AND APPROVED BY THE ENGINEER PRIOR TO THE FINAL INSPECTION.

THE CONTRACTOR MUST ALSO PROVIDE ALL REPORTS REQUIRED BY SPECIFICATIONS. SUPPLY AIR AT UNIT DISCHARGE (DB/WB & CFM); RETURN AIR (DB/WB & CFM); DIFFUSER/GRILLE (CFM); EQUIPMENT (EAT/LAT);

EQUIPMENT (GPM); EQUIPMENT (PRESSURES).

• ALL DUCTWORK MUST BE INSTALLED 6" AWAY FROM ANY FIRE RATED WALL TO FACILITATE INSPECTION.

• THE GENERAL CONTRACTOR IS RESPONSIBLE FOR ALL TRADES INSTALLATION SCHEDULES.

• PROVIDE A FIRE DAMPER AT EVERY DUCT PENETRATION OF A FIRE-RATED WALL OR CEILING, WHETHER SHOWN ON

DRAWINGS OR NOT.

• INTENT OF MECHANICAL NOTES ON DRAWINGS IS TO CLARIFY THE SCOPE OF WORK AND ALERT CONTRACTOR OF EXISTING CONDITIONS. CONTRACTOR IS TO VISIT THE SITE AND VERIFY ALL CLEARANCES BEFORE ORDERING EQUIPMENT OR FABRICATION OF DUCTWORK, AND PROVIDE ADDITIONAL OFFSET AND/OR CHANGES IN SIZES TO MEET FIELD CONDITIONS, AND TO COORDINATE WITH ALL TRADES, BEFORE ANY CONSTRUCTION WORK.

• FLEXIBLE AND RIGID ROUND DUCT TAKE-OFFS FOR DIFFUSERS SHALL BE THE SAME SIZE AS DIFFUSER NECK.

MAXIMUM FLEXIBLE DUCT LENGTH SHALL BE 5'-0".

• CONTRACTOR SHALL PROVIDE ALL SUPPLEMENTARY STEEL REQUIRED TO SUSPEND/SUPPORT MECHANICAL

EQUIPMENT AND MATERIALS.

• IT IS THE RESPONSIBILITY OF THE MECHANICAL INSTALLER TO PATCH AND REPAIR ANY DUCT OPENINGS WHICH RESULT FROM THE RELOCATION OR ELIMINATION OF ANY EXISTING DEVICES. THE PATCH IS TO BE OF A SIMILAR MATERIAL TO THE REPAIRED DUCT AND TO BE SEALED IN ACCORDANCE WITH SMACNA STANDARDS.

• EQUIPMENT WARRANTIES SHALL BE EQUAL TO OR EXCEED WARRANTY OF SCHEDULED EQUIPMENT, UNLESS NOTED

OTHERWISE.

• PROVIDE ADDITIONAL DUCTWORK AND PIPING SUPPORTS ON BOTH SIDES AND WITHIN 18" OF EACH FIRE RATED

WALL. DUCTWORK OR PIPING SHALL NOT BE SUPPORTED FROM ANY FIRE RATED WALL.

• PROVIDE TURNING VANES IN ALL RECTANGULAR SUPPLY AIR DUCT ELBOWS WITH ANGLES FROM 45 DEGREES TO 90 DEGREES PER FIGURES 2-3, 2-4, 2-5 OF THE 1995 SMACNA DUCT CONSTRUCTION STANDARDS. PROVIDE SINGLE WALL VANE CONSTRUCTION FOR DUCTS UP TO 48" WIDE, AND DOUBLE WALL VANE CONSTRUCTION FOR LARGER

DIMENSIONS.

• DUCT DIMENSIONS SHOWN ON DRAWINGS ARE CLEAR INSIDE DIMENSIONS (FREE AREA).

• ALL HVAC EQUIPMENT SHALL BE INSTALLED PER MANUFACTURER'S RECOMMENDATIONS UNLESS INDICATED OTHERWISE. ALL HVAC CONTROL WIRING SHALL BE INSTALLED IN 3/4" EMT (BLUE COLOR); DEVIATIONS MUST

BE APPROVED BY THE COR.

• CONTRACTOR SHALL PROVIDE A PERMANENT/PROFESSIONAL LABEL FOR EACH PIECE OF EQUIPMENT, ASSOCIATED THERMOSTAT(S) AND/OR SENSOR(S). THE CONTRACTOR SHALL ALSO MAINTAIN A SPREADSHEET CONTAINING ALL VAV BOX IDENTIFIERS, LOCATION, MANUFACTURER, SERIAL #, DATE PLACED IN SERVICE, COMMISSIONING DATE AND VA ASSIGNED EQUIPMENT IDENTIFICATION NUMBER (EE#). COORDINATE WITH COR FOR ADDITIONAL INFORMATION.

• DUCTWORK, DIFFUSERS, REGISTERS, GRILLES, AND OTHER MECHANICAL SYSTEM COMPONENTS SHALL NOT BE

SUPPORTED BY THE CEILING OR CEILING SUSPENSION SYSTEM.

• PROVIDE COMMISSIONING FOR ALL MECHANICAL EQUIPMENT ACCORDING TO MECHANICAL SYSTEMS COMMISSIONING AND COMPLETION REQUIREMENTS OF FLORIDA ENERGY CODE 2014 SECTION C408, INCLUDING

BUT NOT LIMITED TO:

a. A COMMISSIONING PLAN IN COMPLIANCE WITH SECTION C408.2.1, FBC-EC-2014.

b. TESTING, ADJUSTING, AND BALANCING OF AIR DISTRIBUTION SYSTEMS ACCORDING TO C408.2.2, FBC-EC-2014.

c. CONDUCT FUNCTIONAL PERFORMANCE TESTING ACCORDING TO C408.2.3, FBC-EC-2014.

d. PRELIMINARY COMMISSIONING REPORT OF TEST PROCEDURES AND RESULTS PER C408.2.4, FBC-EC-2014.

e. PRIOR TO FINAL INSPECTION, PROVIDE RECORD DRAWINGS, OPERATING AND MAINTENANCE MANUALS, SYSTEM

BALANCING REPORT, AND FINAL COMMISSIONING REPORT TO THE OWNER ACCORDING TO C408.2.5, FBC-EC-2014.

MECHANICAL NOTES

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

ABBREVIATIONS

(E) EXISTING

AH AIR HANDLING UNIT

ATU AIR TERMINAL UNIT

BTU/H BRITISH THERMAL UNIT PER HOUR

CAV CONSTANT AIR VOLUME

CD CEILING SUPPLY AIR DIFFUSER

CFM CUBIC FEET PER MINUTE

CHWR CHILLED WATER RETURN

CHWS CHILLED WATER SUPPLY

COR CONTRACTING OFFICER'S REPRESENTATIVE

DCP DIRECT DIGITAL CONTROL PANEL

EA EXHAUST AIR

ECC ENGINEERING CONTROL CENTER

EF EXHAUST FAN

FBC FLORIDA BUILDING CODE

FPM FEET PER MINUTE

GPM GALLONS PER MINUTE

HHWR HEATING HOT WATER RETURN

HHWS HEATING HOT WATER SUPPLY

IBC INTERNATIONAL BUILDING CODE

IN INCH

NC NOISE CRITERIA

OA OUTSIDE AIR

OBD OPPOSED BLADE DAMPER

RA RETURN AIR

RG RETURN AIR GRILLE

SA SUPPLY AIR

SD SMOKE DAMPER

SF SQUARE FEET

TAB TEST AND BALANCE

VAV VARIABLE AIR VOLUME

WG WATER GAUGE

MECHANICAL LEGEND

DUCTWORK SYMBOLS

LIMIT OF DEMOLITION

(WALL TYPE)

(WALL TYPE)

DN

DN

UP

UP

SUPPLY DUCT (UP & DOWN)

EXHAUST DUCT (UP & DOWN)

SQUARE CEILING DIFFUSER

SUPPLY TOP REGISTER OR GRILLE (WALL TYPE)

EXHAUST OR RETURN CEILING REGISTER OR GRILLE

EXHAUST OR RETURN BOTTOM REGISTER OR GRILLE

EXHAUST OR RETURN REGISTER OR TOP GRILLE

VANED ELBOW & AIR SPLIT TYPE DUCT TAKE-OFF

CONNECT NEW DUCT TO EXISTING DUCT

D

INCLINED RISE, IN DIRECTION OF AIR FLOW

INCLINED DROP, IN DIRECTION OF AIR FLOW

R

DNUP RETURN DUCT (UP & DOWN)

10ø

FLEXIBLE CONNECTION, EQUIPMENT,

VANED ELBOW (PROVIDE ALL SQUARE OR

RECTANGULAR ELBOWS WITH VANES EVEN IF

SYMBOL IS MISSING)

STANDARD RADIUS ELBOW (LONG RADIUS)

NEW ROUND DUCT (INSIDE DIMENSIONS: DIAMETER)

EXISTING DUCT TO REMAIN

FLEXIBLE DUCTWORK (INSULATED)

MANUAL VOLUME DAMPER

EXISTING DUCT TO BE REMOVED

VIBRATION SUPPLY

RETURN45°

RETURN, NO SPLITTER (45° TAP)

STANDARD BRANCH SUPPLY OR

45°

AIR TERMINAL SYMBOLS

AIR TERMINAL UNIT

WITH REHEAT COIL

PIPING SYMBOLS

HOT WATER HEATING SUPPLY

CHILLED WATER SUPPLY

CHILLED WATER RETURN

DRAIN LINE

HOT WATER HEATING RETURN

HHWS

HHWR

CHWR

CHWS

D

X EXISTING PIPE TO BE REMOVED

GENERAL PIPING SYMBOLS

REDUCER OR INCREASER

DIRECTION OF FLOW

SIDE CONNECTION

ECCENTRIC REDUCER

BOTTOM CONNECTION, 45° OR 90°

TOP CONNECTION, 45° OR 90°

UNION

RISE OR DROP IN PIPE

CAPPED OUTLET

PRESSURE GAGE

THERMOMETER

PIPE UP

PIPE DOWN

VALVE SYMBOLS

DUCTWORK SYMBOLS

MOTORIZED CONTROL DAMPER

M

EQUIPMENT ANNOTATIONS

1-ATU27-1

BUILDING NO. WHERE EQUIPMENT IS LOCATED

ITEM (AIR TERMINAL UNIT SHOWN)

ITEM NUMBER (TERMINAL UNIT NO. 1)

SERVED BY AIR HANDLING UNIT NO. 27

10x8 NEW RECTANGULAR DUCT (INSIDE DIMENSIONS: WIDTH x DEPTH)

10x8ø NEW OVAL DUCT (INSIDE DIMENSIONS: WIDTH x DEPTH)

BALL VALVE

CHECK VALVE

BUTTERFLY VALVE

MODULATING CONTROL VALVE

GATE VALVE

FLEXIBLE CONNECTION

THREE-WAY CONTROL VALVE

GATE VALVE WITH 3/4" HOSE ADAPTER

WYE STRAINER (WITH BALL VALVE & HOSE

CONNECTION)

AUTOMATIC FLOW CONTROL VALVE

CALIBRATED BALANCING VALVE

GLOBE VALVE

(E)10ø EXISTING ROUND DUCT (INSIDE DIMENSIONS: DIAMETER)

(E)10x8 EXISTING RECTANGULAR DUCT (INSIDE DIMENSIONS: WIDTH x DEPTH)

(E)10x8ø EXISTING OVAL DUCT (INSIDE DIMENSIONS: WIDTH x DEPTH)

AIR TERMINAL UNIT

WITHOUT REHEAT COIL

CONTROLS DEVICE SYMBOLS

SPACE THERMOSTAT - WALL MOUNTT

SPACE TEMPERATURE SENSOR - WALL MOUNTT

SPACE HUMIDITY SENSOR - WALL MOUNTH

SPACE PRESSURE CONTROLLER & DISPLAY - WALL MOUNT

SPACE PRESSURE SENSOR - WALL MOUNTPS

PC

DRAWING SYMBOLS

DRAWING MATCHLINE

HVAC DESIGN DATA

DESIGN CONDITIONS

SUMMER WINTER

TEMPERATURE RELATIVE

HUMIDITY TEMP RELATIVE

HUMIDITY

°Fdb °Fwb % °Fdb %

OUTDOOR DESIGN

CONDITIONS 92 78 54 41 NA

OUTDOOR

DEHUMIDIFICATION

DESIGN CONDITION

87 80 72 41 NA

INDOOR AREA TEMPERATURE/HUMIDITY SETPOINTS

EXAM ROOMS 75 63 50 70 30

LABORATORIES 75 63 50 70 30

OPERATING ROOMS 66 56 55 75 30

PATIENT ROOMS 75 63 50 70 30

PROCEDURE ROOMS 75 63 50 70 30

SPECIAL PROCEDURE

ROOMS 73 61 50 68 30

CLASSROOMS /

CONFERENCE ROOMS 75 63 50 70 30

CORRIDORS 75 63 50 70 30

COMMUNICATION

ROOMS 77 64 50 - -

LOUNGES 75 63 50 70 30

ELECTRICAL ROOMS 86 66 50 - -

OFFICES 75 63 50 70 30

TOILETS 77 64 50 70 30

WAITING AREAS 75 63 50 70 30

ALL OTHER SPACES 75 63 50 70 30

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. of

CONSULTANTS: ARCHITECT/ENGINEERS:

group mes

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

550 North Reo Street Suite 203 Tampa, FL 33609 813.289.4700

COA # 8304

DALE A. BACIK, P.E.

FULLY SPRINKLERED

8/

/2

8:

:0

AM

REPLACE VAV BOXES AND

UPGRADE TO DIRECT DIGITAL

CONTROLS

NOTES & LEGEND - HVAC

WEST PALM BEACH, FLORIDA

08/20/2018 CJF/REM REM

548-16-612

01, 03

MH001

AIR DEVICE SCHEDULE (SUPPLY)

MARK TYPE

AIRFLOW PANEL SIZE

(IN.)

NECK SIZE

(IN.) NOTES

MIN. MAX.

CD-21 PERFORATED FACE 30 CFM 160 CFM 24x24 6ø 1,2,3 CD-22 PERFORATED FACE 90 CFM 240 CFM 24x24 8ø 1,2,3 CD-24 PERFORATED FACE 330 CFM 400 CFM 24x24 12ø 1,2,3 CD-25 PERFORATED FACE 410 CFM 640 CFM 24x24 14ø 1,2,3

NOTES:

1. RUNOUT BRANCH DUCT SHALL BE SAME SIZE AS INDICATED NECK SIZE.

2. PROVIDE VOLUME DAMPER INSTALLED IN BRANCH DUCT SERVING EACH DIFFUSER.

3. PROVIDE ALL REQUIRED ACCESSORIES FOR A COMPLETE INSTALLATION.

Revisions: Date

CONTRACTOR SHALL KEEP A RECORD (IN THE FORM OF A SPREADSHEET) OF ALL VAV LOCATIONS, VAV #, MANUFACTURER, MODEL NUMBER, SERIAL NUMBER, INSTALLATION DATE, COMMISSIONING DATE, WARRANTY DATE

AND VA PROVIDED EE#.

•14.

REVISION 1: UPDATED BY WEST PALM BEACH VAMC 10/01/2021

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. of

CONSULTANTS: ARCHITECT/ENGINEERS:

group mes

Office of Construction and Facilities Management on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

550 North Reo Street Suite 203 Tampa, FL 33609 813.289.4700

COA # 8304

DALE A. BACIK, P.E.

FULLY SPRINKLERED

8/

/2

8:

:1

AM

REPLACE VAV BOXES AND

UPGRADE TO DIRECT DIGITAL

CONTROLS

SCHEDULES - HVAC

WEST PALM BEACH, FLORIDA

08/20/2018 CJF/REM NPS

548-16-612

MH002

• BASIS OF DESIGN EQUIPMENT WITH REQUIRED PERFORMANCE CHARACTERISTICS IS SCHEDULED. OTHER MANUFACTURERS ARE ACCEPTABLE; HOWEVER EQUIPMENT NOT MEETING EQUIVALENT PERFORMANCE CRITERIA

CANNOT BE CONSIDERED.

• HOT WATER REHEAT COIL SHALL HAVE A MAXIMUM WATER PRESSURE DROP OF 3.0 FT. WG.

• UNIT SERVES CRITICAL AREA.

• PROVIDE TERMINAL UNIT WITH PRE-PROGRAMMED CONTROLS AND SENSORS, AND PREASSEMBLED PIPING ACCESSORIES. REMOVAL OF EXISTING AND INSTALLATION OF NEW TERMINAL UNIT, CONTROLLER AND

COMPONENTS SHALL BE COMPLETED AND RUNNING 100% WITH SHORTEST DOWNTIME POSSIBLE.

• UNIT SERVES NON-CRITICAL AREA.

• CONTRACTOR'S OPTION TO PROVIDE TERMINAL UNIT WITH PREASSEMBLED OR FIELD-INSTALLED COMPONENTS

FOR NON-CRITICAL ZONE.

• PROVIDE SPACE PRESSURE CONTROLLER AND DISPLAY, PRESSURE DIFFERENTIAL SENSORS, AND INTERLOCKS

TO MAINTAIN REQUIRED SPACE PRESSURE DIFFERENTIAL. SEE CONTROLS, SHEET MH601.

AIR TERMINAL UNIT SCHEDULE NOTES

AIR TERMINAL UNIT SCHEDULE - LEVEL 0 - 1-AH2 (21)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU2-1 10 740 CFM 740 CFM 0.35 in-wg 35 740 CFM 56.5 °F 180 °F 160 °F 1.5 GPM 14,900 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-2 10 740 CFM 740 CFM 0.35 in-wg 35 740 CFM 56.5 °F 180 °F 160 °F 1.5 GPM 14,900 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-3 6 270 CFM 270 CFM 0.20 in-wg 35 270 CFM 56.5 °F 180 °F 160 °F 1.0 GPM 5,700 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU2-4 8 570 CFM 570 CFM 0.35 in-wg 35 570 CFM 56.5 °F 180 °F 160 °F 1.5 GPM 11,400 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU2-5 7 325 CFM 325 CFM 0.25 in-wg 35 325 CFM 56.5 °F 180 °F 160 °F 1.0 GPM 6,500 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-07 1,2,3,4 1-ATU2-6 6 150 CFM 150 CFM 0.20 in-wg 35 150 CFM 56.5 °F 180 °F 160 °F 0.5 GPM 3,800 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU2-7 8 600 CFM 600 CFM 0.25 in-wg 35 600 CFM 56.5 °F 180 °F 160 °F 1.5 GPM 12,000 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU2-8 10 740 CFM 740 CFM 0.35 in-wg 35 740 CFM 56.5 °F 180 °F 160 °F 1.5 GPM 14,900 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-9 10 800 CFM 800 CFM 0.25 in-wg 35 800 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 16,100 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4

1-ATU2-10 8 500 CFM 500 CFM 0.20 in-wg 35 500 CFM 56.5 °F 180 °F 160 °F 1.0 GPM 10,000 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU2-11 10 800 CFM 800 CFM 0.35 in-wg 35 800 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 16,100 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-12 10 900 CFM 900 CFM 0.25 in-wg 35 900 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 18,100 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-13 10 1200 CFM 1200 CFM 0.30 in-wg 35 1200 CFM 56.5 °F 180 °F 160 °F 3.0 GPM 24,100 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-14 10 680 CFM 680 CFM 0.30 in-wg 35 680 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 17,500 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-15 10 900 CFM 900 CFM 0.25 in-wg 35 900 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 18,100 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-16 10 900 CFM 900 CFM 0.25 in-wg 35 900 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 18,100 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-17 8 500 CFM 500 CFM 0.20 in-wg 35 500 CFM 56.5 °F 180 °F 160 °F 1.0 GPM 10,000 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU2-18 7 490 CFM 490 CFM 0.20 in-wg 35 490 CFM 56.5 °F 180 °F 160 °F 1.0 GPM 9,800 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-07 1,2,3,4 1-ATU2-19 7 460 CFM 460 CFM 0.20 in-wg 35 460 CFM 56.5 °F 180 °F 160 °F 1.0 GPM 9,200 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-07 1,2,3,4 1-ATU2-20 10 920 CFM 920 CFM 0.30 in-wg 35 920 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 18,500 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU2-21 10 920 CFM 920 CFM 0.30 in-wg 35 920 CFM 56.5 °F 180 °F 160 °F 2.0 GPM 18,500 Btu/h 3/4" CAV PRICE INDUSTRIES SDV-10 1,2,3,4

AIR TERMINAL UNIT SCHEDULE - LEVEL 0 - 1-AH3 (27)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU3-1 7 390 CFM 195 CFM 0.15 in-wg 35 290 CFM 50.1 °F 180 °F 160 °F 1.5 GPM 12,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU3-2 8 700 CFM 350 CFM 0.30 in-wg 35 350 CFM 50.1 °F 180 °F 160 °F 2.0 GPM 15,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-3 6 330 CFM 165 CFM 0.20 in-wg 35 230 CFM 50.1 °F 180 °F 160 °F 1.0 GPM 10,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-4 6 320 CFM 160 CFM 0.20 in-wg 35 220 CFM 50.1 °F 180 °F 160 °F 1.0 GPM 9,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-5 8 470 CFM 235 CFM 0.20 in-wg 35 350 CFM 50.1 °F 180 °F 160 °F 2.0 GPM 15,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-6 6 300 CFM 150 CFM 0.20 in-wg 35 150 CFM 50.1 °F 180 °F 160 °F 1.0 GPM 6,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-7 10 840 CFM 420 CFM 0.25 in-wg 35 460 CFM 50.1 °F 180 °F 160 °F 2.0 GPM 20,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,5,6 1-ATU3-8 6 260 CFM 130 CFM 0.15 in-wg 35 130 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 5,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-9 8 450 CFM 225 CFM 0.20 in-wg 35 225 CFM 50.1 °F 180 °F 160 °F 1.0 GPM 9,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-10 6 330 CFM 165 CFM 0.25 in-wg 35 165 CFM 50.1 °F 180 °F 160 °F 1.0 GPM 7,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-11 6 290 CFM 145 CFM 0.20 in-wg 35 145 CFM 50.1 °F 180 °F 160 °F 1.0 GPM 6,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-12 8 470 CFM 235 CFM 0.20 in-wg 35 235 CFM 50.1 °F 180 °F 160 °F 1.5 GPM 10,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-13 5 180 CFM 90 CFM 0.15 in-wg 35 90 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 3,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-05 1,2,5,6 1-ATU3-14 6 230 CFM 115 CFM 0.15 in-wg 35 115 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 4,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-15 8 580 CFM 290 CFM 0.25 in-wg 35 320 CFM 50.1 °F 180 °F 160 °F 1.5 GPM 13,900 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-16 6 180 CFM 90 CFM 0.15 in-wg 35 90 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 3,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-17 6 240 CFM 120 CFM 0.15 in-wg 35 140 CFM 50.1 °F 180 °F 160 °F 1.0 GPM 6,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-18 8 690 CFM 345 CFM 0.30 in-wg 35 500 CFM 50.1 °F 180 °F 160 °F 3.0 GPM 21,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-19 8 580 CFM 290 CFM 0.20 in-wg 35 350 CFM 50.1 °F 180 °F 160 °F 2.0 GPM 15,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-20 8 540 CFM 270 CFM 0.25 in-wg 35 380 CFM 50.1 °F 180 °F 160 °F 2.0 GPM 16,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-21 8 520 CFM 260 CFM 0.20 in-wg 35 410 CFM 50.1 °F 180 °F 160 °F 2.0 GPM 17,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-22 6 180 CFM 90 CFM 0.10 in-wg 35 90 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 3,900 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-23 6 240 CFM 120 CFM 0.15 in-wg 35 120 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 5,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-24 6 170 CFM 85 CFM 0.10 in-wg 35 85 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 3,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-25 8 490 CFM 245 CFM 0.20 in-wg 35 245 CFM 50.1 °F 180 °F 160 °F 1.5 GPM 10,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU3-26 6 240 CFM 120 CFM 0.15 in-wg 35 120 CFM 50.1 °F 180 °F 160 °F 0.5 GPM 4,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU3-27 8 480 CFM 240 CFM 0.15 in-wg 35 260 CFM 50.1 °F 180 °F 160 °F 1.5 GPM 11,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6

AIR TERMINAL UNIT SCHEDULE - LEVEL 0 - 1-AH5 (16)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU5-1 6 320 CFM 160 CFM 0.20 in-wg 35 175 CFM 56.7 °F 180 °F 160 °F 1.0 GPM 6,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-2 6 280 CFM 140 CFM 0.15 in-wg 35 140 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 3,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-3 7 390 CFM 200 CFM 0.15 in-wg 35 200 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 5,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,3,4 1-ATU5-4 8 570 CFM 290 CFM 0.30 in-wg 35 290 CFM 56.7 °F 180 °F 160 °F 1.0 GPM 7,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU5-5 7 430 CFM 220 CFM 0.20 in-wg 35 220 CFM 56.7 °F 180 °F 160 °F 1.0 GPM 6,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,3,4 1-ATU5-6 6 280 CFM 140 CFM 0.20 in-wg 35 140 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 4,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-7 6 240 CFM 120 CFM 0.15 in-wg 35 120 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 3,400 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-8 6 230 CFM 120 CFM 0.15 in-wg 35 120 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 3,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-9 6 280 CFM 140 CFM 0.20 in-wg 35 0 CFM 0.0 °F 180 °F 160 °F 0.0 GPM 0 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-10 5 90 CFM 50 CFM 0.10 in-wg 35 50 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 2,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-05 1,2,3,4 1-ATU5-11 10 810 CFM 410 CFM 0.25 in-wg 35 0 CFM 0.0 °F 180 °F 160 °F 0.0 GPM 0 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU5-12 10 720 CFM 360 CFM 0.30 in-wg 35 720 CFM 56.7 °F 180 °F 160 °F 3.0 GPM 28,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU5-13 8 450 CFM 225 CFM 0.20 in-wg 35 225 CFM 56.7 °F 180 °F 160 °F 1.0 GPM 8,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU5-14 6 240 CFM 125 CFM 0.15 in-wg 35 125 CFM 56.7 °F 180 °F 0.5 GPM 4,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-15 6 310 CFM 160 CFM 0.20 in-wg 35 160 CFM 56.7 °F 180 °F 1.0 GPM 5,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-16 8 690 CFM 350 CFM 0.30 in-wg 35 350 CFM 56.7 °F 180 °F 1.0 GPM 8,800 Btu/h 3/4" VAV-HD PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU5-17 6 300 CFM 150 CFM 0.20 in-wg 35 150 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 4,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU5-18 5 160 CFM 80 CFM 0.10 in-wg 35 80 CFM 56.7 °F 180 °F 160 °F 0.5 GPM 2,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-05 1,2,3,4 1-ATU5-19 6 300 CFM 150 CFM 0.20 in-wg 35 150 CFM 56.7 °F 180 °F 160 °F 1.0 GPM 5,400 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4

AIR TERMINAL UNIT SCHEDULE - LEVEL 0 - 1-AH6 (18)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU6-1 8 530 CFM 265 CFM 0.15 in-wg 35 360 CFM 63.9 °F 180 °F 160 °F 1.5 GPM 10,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-2 8 750 CFM 375 CFM 0.35 in-wg 35 375 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-3 8 750 CFM 375 CFM 0.35 in-wg 35 375 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-4 6 380 CFM 190 CFM 0.30 in-wg 35 190 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 3,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU6-5 8 640 CFM 320 CFM 0.25 in-wg 35 320 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-6 6 280 CFM 140 CFM 0.20 in-wg 35 140 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 3,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU6-7 8 740 CFM 370 CFM 0.35 in-wg 35 370 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-8 8 740 CFM 370 CFM 0.35 in-wg 35 370 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-9 8 740 CFM 370 CFM 0.35 in-wg 35 370 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-10 8 420 CFM 210 CFM 0.15 in-wg 35 210 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 3,900 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-11 7 390 CFM 195 CFM 0.15 in-wg 35 195 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 2,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU6-12 8 750 CFM 375 CFM 0.35 in-wg 35 375 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 4,900 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-13 8 760 CFM 380 CFM 0.35 in-wg 35 380 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 5,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-14 6 380 CFM 190 CFM 0.30 in-wg 35 190 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 2,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU6-15 8 460 CFM 230 CFM 0.20 in-wg 35 230 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 4,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU6-16 6 250 CFM 125 CFM 0.15 in-wg 35 200 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 5,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU6-17 7 410 CFM 205 CFM 0.15 in-wg 35 300 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 8,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU6-18 6 200 CFM 200 CFM 0.10 in-wg 35 200 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 3,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6

AIR TERMINAL UNIT SCHEDULE - LEVEL 0 - 1-AH7 (21)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU7-1 8 520 CFM 260 CFM 0.20 in-wg 35 310 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 8,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU7-2 7 410 CFM 205 CFM 0.15 in-wg 35 300 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 8,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU7-3 6 380 CFM 190 CFM 0.30 in-wg 35 270 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 7,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-4 7 440 CFM 220 CFM 0.20 in-wg 35 220 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU7-5 8 610 CFM 305 CFM 0.20 in-wg 35 305 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 6,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU7-6 6 260 CFM 130 CFM 0.10 in-wg 35 130 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 2,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-7 7 490 CFM 245 CFM 0.20 in-wg 35 245 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 5,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU7-8 8 520 CFM 260 CFM 0.20 in-wg 35 260 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 5,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU7-9 8 660 CFM 330 CFM 0.30 in-wg 35 330 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 9,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU7-10 6 370 CFM 185 CFM 0.20 in-wg 35 185 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 4,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-11 6 340 CFM 170 CFM 0.25 in-wg 35 170 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 3,900 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-12 7 470 CFM 235 CFM 0.20 in-wg 35 235 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 5,900 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU7-13 6 290 CFM 145 CFM 0.20 in-wg 35 145 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 2,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-14 8 480 CFM 240 CFM 0.30 in-wg 35 250 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 7,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU7-15 7 460 CFM 230 CFM 0.20 in-wg 35 230 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 5,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU7-16 10 740 CFM 370 CFM 0.25 in-wg 35 460 CFM 63.9 °F 180 °F 160 °F 1.5 GPM 13,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,5,6 1-ATU7-17 6 320 CFM 160 CFM 0.20 in-wg 35 200 CFM 63.9 °F 180 °F 160 °F 1.0 GPM 5,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-18 6 360 CFM 180 CFM 0.30 in-wg 35 180 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 4,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-19 6 310 CFM 155 CFM 0.20 in-wg 35 155 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 3,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-20 6 290 CFM 145 CFM 0.20 in-wg 35 145 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 3,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU7-21 6 360 CFM 180 CFM 0.30 in-wg 35 180 CFM 63.9 °F 180 °F 160 °F 0.5 GPM 5,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6

AIR TERMINAL UNIT SCHEDULE - LEVEL 0 - 1-AH8 (23)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU8-1 7 580 CFM 290 CFM 0.25 in-wg 35 360 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 12,900 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU8-2 7 520 CFM 260 CFM 0.20 in-wg 35 350 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 12,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU8-3 10 760 CFM 380 CFM 0.35 in-wg 35 480 CFM 57.0 °F 180 °F 160 °F 2.0 GPM 17,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,5,6 1-ATU8-4 7 370 CFM 185 CFM 0.15 in-wg 35 210 CFM 57.0 °F 180 °F 160 °F 1.0 GPM 7,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU8-5 5 130 CFM 65 CFM 0.10 in-wg 35 100 CFM 57.0 °F 180 °F 160 °F 0.5 GPM 3,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-05 1,2,5,6 1-ATU8-6 10 750 CFM 375 CFM 0.25 in-wg 35 420 CFM 57.0 °F 180 °F 160 °F 2.0 GPM 15,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,5,6 1-ATU8-7 6 280 CFM 140 CFM 0.15 in-wg 35 150 CFM 57.0 °F 180 °F 160 °F 0.5 GPM 5,400 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU8-8 8 560 CFM 280 CFM 0.20 in-wg 35 320 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 11,500 Btu/h 3/4" VAV-HD PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-9 8 560 CFM 280 CFM 0.20 in-wg 35 320 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 11,500 Btu/h 3/4" VAV-HD PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-10 6 340 CFM 170 CFM 0.25 in-wg 35 200 CFM 57.0 °F 180 °F 160 °F 1.0 GPM 7,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU8-11 6 280 CFM 140 CFM 0.20 in-wg 35 170 CFM 57.0 °F 180 °F 160 °F 1.0 GPM 6,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU8-12 8 560 CFM 280 CFM 0.20 in-wg 35 340 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 12,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-13 8 560 CFM 280 CFM 0.20 in-wg 35 340 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 12,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-14 7 370 CFM 185 CFM 0.15 in-wg 35 210 CFM 57.0 °F 180 °F 160 °F 1.0 GPM 7,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6 1-ATU8-15 10 840 CFM 420 CFM 0.25 in-wg 35 420 CFM 57.0 °F 180 °F 160 °F 2.0 GPM 15,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,5,6 1-ATU8-16 8 550 CFM 275 CFM 0.20 in-wg 35 275 CFM 57.0 °F 180 °F 160 °F 1.0 GPM 9,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-17 8 750 CFM 375 CFM 0.30 in-wg 35 380 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 13,600 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-18 8 690 CFM 345 CFM 0.20 in-wg 35 345 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 12,400 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-19 10 750 CFM 375 CFM 0.25 in-wg 35 420 CFM 57.0 °F 180 °F 160 °F 2.0 GPM 15,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,5,6 1-ATU8-20 6 370 CFM 185 CFM 0.25 in-wg 35 210 CFM 57.0 °F 180 °F 160 °F 1.0 GPM 7,500 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,5,6 1-ATU8-21 8 560 CFM 280 CFM 0.20 in-wg 35 330 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 11,800 Btu/h 3/4" VAV-HD PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-22 8 560 CFM 280 CFM 0.20 in-wg 35 330 CFM 57.0 °F 180 °F 160 °F 1.5 GPM 11,800 Btu/h 3/4" VAV-HD PRICE INDUSTRIES SDV-08 1,2,5,6 1-ATU8-23 7 400 CFM 200 CFM 0.15 in-wg 35 270 CFM 57.0 °F 180 °F 160 °F 1.0 GPM 9,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,5,6

AIR TERMINAL UNIT SCHEDULE - LEVEL 1 - 1-AH9 (9)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU9-4 10 940 CFM 470 CFM 0.25 in-wg 35 470 CFM 56.1 °F 180 °F 160 °F 2.0 GPM 17,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-10 1,2,3,4 1-ATU9-6 6 310 CFM 155 CFM 0.20 in-wg 35 155 CFM 56.1 °F 180 °F 160 °F 1.0 GPM 5,700 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU9-7 6 230 CFM 115 CFM 0.10 in-wg 35 115 CFM 56.1 °F 180 °F 160 °F 0.5 GPM 4,200 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU9-8 6 170 CFM 85 CFM 0.20 in-wg 35 85 CFM 56.1 °F 180 °F 160 °F 0.5 GPM 3,100 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU9-9 7 340 CFM 170 CFM 0.20 in-wg 35 170 CFM 56.1 °F 180 °F 160 °F 1.0 GPM 6,300 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-07 1,2,3,4 1-ATU9-20 6 380 CFM 190 CFM 0.30 in-wg 35 190 CFM 56.1 °F 180 °F 160 °F 1.0 GPM 7,000 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU9-26 6 200 CFM 100 CFM 0.10 in-wg 35 130 CFM 56.1 °F 180 °F 160 °F 0.5 GPM 4,800 Btu/h 3/4" VAV PRICE INDUSTRIES SDV-06 1,2,3,4 1-ATU9-28 8 0 CFM 440 CFM 0.25 in-wg 35 610 CFM 61.6 °F 180 °F 160 °F 1.3 GPM 12,093 Btu/h 3/4" PRICE INDUSTRIES SDV-08 1,2,3,4 1-ATU9-29 8 0 CFM 440 CFM 0.25 in-wg 35 610 CFM 61.6 °F 180 °F 160 °F 1.2 GPM 12,093 Btu/h 3/4" PRICE INDUSTRIES SDV-08 1,2,3,4

AIR TERMINAL UNIT SCHEDULE - LEVEL 1 - 1-AH10 (25)

MARK NOMINAL

SIZE

AIRFLOW

MAX. TOTAL

UNIT

PRESSURE

DROP

SPACE

NOISE

CRITERIA

(NC)

HOT WATER HEATING COIL

CONTROL

TYPE

BASIS OF DESIGN

NOTES

MAXIMUM MINIMUM HEATING

AIRFLOW

ENTERING

AIR TEMP.

ENTERING

WATER

TEMP.

LEAVING

WATER

TEMP.

HEATING

WATER

FLOW

COIL

CAPACITY

HOT

WATER

PIPING

RUNOUT

SIZE

MANUFACTURER MODEL

NUMBER

1-ATU10-1 10 840 CFM 420 CFM 0.25 in-wg 35 420 CFM 59.8…