This is a Permit Information document for the Honore Avenue Reclaimed Water Main Extension Phase 2B project managed by Sarasota County, Florida. The project involves the installation of approximately 5,500 linear feet of reclaimed water transmission main, including 20-inch and 8-inch Horizontal Directional Drill (HDD) installations and a 20-inch Jack & Bore in a 36-inch casing. The CIP Project Number is 88058, and the contract is anticipated to run for 300 calendar days. The bid submission deadline is December 3, 2025. Contractors must demonstrate specific experience, including installation of at least 1,000 linear feet of 16-inch or larger diameter pressure pipe and experience with pipeline work involving lane closures and specialized drilling methods. The work is located in Osprey, Florida, in Section 07, Township 38S, Range 19E, and will require coordination with multiple regulatory bodies including the Florida Department of Transportation.
The project requires several permits including a Utility Permit (UTIL-REVIEW-25-00038), a Temporary Traffic Control Plan (TTCP), and a Lane Closure Permit from FDOT for any lane closures on SR 681, as detailed on the referenced plan sheets. The project is funded through a Southwest Florida Water Management District (SWFWMD) grant, which imposes requirements for United States-produced iron and steel products and reporting on minority and small business participation for projects receiving over $100,000 in cooperative funding. Liquidated damages are assessed at $400 per day for substantial completion delays and $100 per day for final acceptance delays. Comprehensive insurance requirements include workers' compensation, commercial general liability, automobile liability, and umbrella/excess liability coverage. A bid bond or letter of bondability is required, with performance and payment bonds mandatory for the contract. The procurement will select the lowest responsive and responsible bidder, and local or American business preferences will not apply due to grant funding requirements.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERMIT
INFORMATION
Honore Avenue Reclaimed Water Main Extension, Ph. 2B
CIP Project No. 88058
List of Permits
• Utility Permit – See Note on Plan Sheet C-02 (Utility Review Permit number UTIL-REVIEW-25-00038)
• Temporary Traffic Control Plan (TTCP) – See Note on Plan Sheet C-02
• Lane Closure Permit from FDOT (Permit will be needed anytime there is a lane closure on SR 681). – See Notes on Plan Sheet T-1 through T-5.