Attachment 4 - Schedule of Submittals.docx

DOCX document 25 KB Posted

Attached to
Building 1055 Chiller Replacement
Solicitation number
W50S8G26BA003
Issued by

About this file

This is a Schedule of Submittals attachment that outlines the timeline and requirements for bidders to submit documentation and materials for the Building 1055 Chiller Replacement project at Kirtland Air Force Base, New Mexico.

The schedule establishes key submission deadlines and deliverables required throughout the procurement and construction process. Bidders must submit sealed bids in person at the specified bid opening location, with submissions accepted no earlier than one hour before the scheduled opening time and absolutely no later bids accepted. The deadline for submitting questions and requests for information (RFI) is 11:00 AM MDT on August 25, 2026. Prior to bid submission, bidders are required to attend a pre-bid conference and site visit to familiarize themselves with Building 1055 and the chiller replacement scope. The schedule likely details specific dates and times for the site visit, pre-bid conference, and bid opening, along with any required documentation needed to participate in these events. All submittals must comply with the sealed bid requirements—only hand-delivered, sealed envelopes will be accepted; electronic, mailed, or facsimile submissions are prohibited. The contract is structured as a Firm Fixed Price award for a Total Small Business Set-Aside under NAICS code 238220, with a project magnitude between $350,000 and $450,000, requiring replacement of chiller units with specified Carrier and Reliable Controls brand equipment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF MATERIAL SUBMITTALS

PROJECT NUMBER

MHMV262055

PROJECT TITLE

Building 1055 Chiller Replacement 2026

WORK ORDER NUMBER

202601396

TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACTING
Line Number
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL
NO. OF COPIES REQUIRED
REQUIRED SUBMISSION DATE
DATE RECEIVED IN CONTRACTING
DATE TO CIVIL ENGINEERING
RETURN SUSPENSE DATE
FOLLOW-UP
DATE

CONTRACTOR

NOTIFIED

CONTRACTOR RESUBMITTED
FINAL APPROVAL
REMARKS
APPROVED
DISAPPROVED
1
Project Schedule
3
Prior to work
2
Work certifications for Install of Chillers
37 Days
Prior to work
3
Chiller
3
Prior to work
4
Gauges
3
Prior to work
5
Valves
3
Prior to work
6
Deficiency Report
3
Prior to work
7
Flush and Fill report
3
Prior to work
8
Test and Balance Report
3
Prior to work
9
Manufacturer start up report
3
Prior to work
10
O&M’s & Warranties
3
Prior to work
11
As-built drawings
1
End of work

AF Fm 66

File details come from the government source that posted it. Updated .