Attachment 3 - Submittal Register.xls
XLS spreadsheet 239 KB Posted
- Attached to
- HVAC Repair Space Optimization & Renovation PNSY-B43 Federal contract opportunity
- Solicitation number
- N4008520B2557
About this file
This document is a submittal register for the HVAC repair, space optimization, and renovation project PNSY-43 at the Naval Facilities Engineering Command. The register outlines 184 submittal items required from the contractor organized by specification section. Key submittals include an accident prevention plan, hazardous material management plans, cleaning and abatement plans for asbestos and lead-based paint, mechanical and control system shop drawings and manuals, fire protection designs, and commissioning documents. The contractor must provide samples, test reports, certificates, and closeout documents as specified. The register identifies the paragraph requiring each submittal, its classification, required approvals, and timing. This will help the contractor plan and track required pre-construction, shop drawing, product data, test, and closeout submissions for the HVAC project to the Navy project team.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 6 - Draft Internal Service Requirement List.xlsx | XLSX spreadsheet | |
| Attachment 2 - Specifications.pdf | ||
| Attachment 7 - Furniture Scope of Work and Specifcation.pdf | ||
| N4008520B2557.pdf | ||
| Attachment 4 - Drawings.pdf | ||
| Attachment 9 - NAVFAC MIDLANT PWD-Maine - ICS Standard.pdf | ||
| Attachment 5 - Draft eOMSI Workbook.xlsx | XLSX spreadsheet | |
| Attachment 8 - Project Laydown and Construction Barrier Drawings.pdf | ||
| Attachment 1 - Bid Form.pdf | ||
| encl a - Scope of Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register
| TITLE: | Attachment 3 - Submittal Register | SUBMITTAL REGISTER | ||||||||||||||||||
| JOB NAME: | MM OH - HVAC Repair Space Optimization & Renovation PNSY-43 | |||||||||||||||||||
| LOCATION: | ||||||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |||
| Line | Activity # | Trans-mittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Revwr | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Revwr | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 11 00 | 01 | Preconstruction Submittals | Salvage Plan | 1.5 | |||||||||||||||
| 2 | 01 14 00.00 22 | 01 | Preconstruction Submittals | List of Contact Personnel | 1.4.1 | |||||||||||||||
| 3 | 01 20 00.00 22 | 01 | Preconstruction Submittals | Schedule of Prices | 1.3 | |||||||||||||||
| 4 | 01 30 00.00 22 | 01 | Preconstruction Submittals | NAVFAC Red Zone Checklist | 1.6 | G | ||||||||||||||
| 5 | 01 30 00.00 22 | 01 | Preconstruction Submittals | NAVFAC PWD ME Follow-on Services List | 1.6 | G | ||||||||||||||
| 6 | 01 31 23.13 22 | 01 | Preconstruction Submittals | List of Contractor's Personnel | 1.4.2 | |||||||||||||||
| 7 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Construction Schedule | 1.2 | G | ||||||||||||||
| 8 | 01 32 16.00 20 | 07 | Certificates | Monthly Updates | 1.4 | |||||||||||||||
| 9 | 01 33 00 | 01 | Preconstruction Submittals | Submittal Register | 1.7 | G | ||||||||||||||
| 10 | 01 33 10.05 20 | 01 | Preconstruction Submittals | Consolidated RFP Documents | 2.1 | G | ||||||||||||||
| 11 | 01 33 10.05 20 | 01 | Preconstruction Submittals | Submittal Register | 1.5.5 | G | ||||||||||||||
| 12 | 01 33 10.05 20 | 05 | Design Data | Design Drawings | 1.7 | G | ||||||||||||||
| 13 | 01 33 10.05 20 | 05 | Design Data | Specifications | 1.9 | G | ||||||||||||||
| 14 | 01 33 10.05 20 | 05 | Design Data | Design Analysis | 1.8 | G | ||||||||||||||
| 15 | 01 33 10.05 20 | 05 | Design Data | Design Submittals | 2.2 | G | ||||||||||||||
| 16 | 01 33 10.05 20 | 11 | Closeout Submittals | Record Documents | 1.8 | G | ||||||||||||||
| 17 | 01 33 10.05 20 | 11 | Closeout Submittals | DD Form 1354 | 1.8 | G | ||||||||||||||
| 18 | 01 35 26.00 22 | 01 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.7 | G | ||||||||||||||
| 19 | 01 35 26.00 22 | 06 | Test Reports | Monthly Exposure Reports | 1.4 | |||||||||||||||
| 20 | 01 35 26.00 22 | 06 | Test Reports | Notifications and Reports | 1.12 | |||||||||||||||
| 21 | 01 35 26.00 22 | 06 | Test Reports | Accident Reports | 1.12.2 | G | ||||||||||||||
| 22 | 01 35 26.00 22 | 06 | Test Reports | LHE Inspection Reports | 1.12.3 | |||||||||||||||
| 23 | 01 35 26.00 22 | 07 | Certificates | Crane Operators/Riggers | 1.6.1.5 | |||||||||||||||
| 24 | 01 35 26.00 22 | 07 | Certificates | Standard Lift Plan | 1.7.2.2 | G | ||||||||||||||
| 25 | 01 35 26.00 22 | 07 | Certificates | Critical Lift Plan | 1.7.2.3 | G | ||||||||||||||
| 26 | 01 35 26.00 22 | 07 | Certificates | Naval Architecture Analysis | 1.7.2.3 | G | ||||||||||||||
| 27 | 01 35 26.00 22 | 07 | Certificates | Activity Hazard Analysis (AHA) | 1.8 | |||||||||||||||
| 28 | 01 35 26.00 22 | 07 | Certificates | Confined Space Entry Permit | 1.9.1 | |||||||||||||||
| 29 | 01 35 26.00 22 | 07 | Certificates | Hot Work Permit | 1.9.1 | |||||||||||||||
| 30 | 01 35 26.00 22 | 07 | Certificates | Certificate of Compliance | 1.12.4 | |||||||||||||||
| 31 | 01 35 26.00 22 | 07 | Certificates | Barge Mounted Mobile Cranes | 1.7.2.3 | |||||||||||||||
| 32 | 01 35 26.00 22 | 07 | Certificates | License Certificates | 0 | |||||||||||||||
| 33 | 01 35 26.00 22 | 07 | Certificates | Radiography Operation Planning Work Sheet | 0 | G | ||||||||||||||
| 34 | 01 35 29.13 | 02 | Shop Drawings | Work Zones | 3.9.1 | G | ||||||||||||||
| 35 | 01 35 29.13 | 02 | Shop Drawings | Decontamination Facilities | 3.10.1 | G | ||||||||||||||
| 36 | 01 35 29.13 | 03 | Product Data | Amendments to the APP/SSHP | 1.4 | |||||||||||||||
| 37 | 01 35 29.13 | 03 | Product Data | Exposure Monitoring/Air Sampling Program | 3.5 | |||||||||||||||
| 38 | 01 35 29.13 | 03 | Product Data | Site Control Log | 3.9.2 | |||||||||||||||
| 39 | 01 35 29.13 | 03 | Product Data | SSHO's Daily Inspection Logs | 1.8 | |||||||||||||||
| 40 | 01 35 29.13 | 07 | Certificates | Certificate Of Worker/Visitor Acknowledgement | 1.7 | |||||||||||||||
| 41 | 01 35 29.13 | 11 | Closeout Submittals | Safety And Health Phase-Out Report | 1.9 | |||||||||||||||
| 42 | 01 44 00.22 | 01 | Preconstruction Submittals | Archaeologist Qualifications | 1.4 | G | ||||||||||||||
| 43 | 01 44 00.22 | 06 | Test Reports | Archaeological Monitoring Reports | 3.2 | |||||||||||||||
| 44 | 01 45 00.10 22 | 01 | Preconstruction Submittals | QC Plan | 1.6 | G | ||||||||||||||
| 45 | 01 50 00.00 22 | 01 | Preconstruction Submittals | Construction site plan | 1.4 | G | ||||||||||||||
| 46 | 01 50 00.00 22 | 01 | Preconstruction Submittals | Traffic control plan | 3.3.1 | G | ||||||||||||||
| 47 | 01 50 00.00 22 | 06 | Test Reports | Backflow Preventer Tests | 2.2.5 | G | ||||||||||||||
| 48 | 01 50 00.00 22 | 07 | Certificates | Backflow Tester | 1.5.1 | G | ||||||||||||||
| 49 | 01 50 00.00 22 | 07 | Certificates | Backflow Preventers | 1.5 | G | ||||||||||||||
| 50 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Preconstruction Survey | 1.5.1 | G | ||||||||||||||
| 51 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Solid Waste Management Plan | 3.4 | G | ||||||||||||||
| 52 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Regulatory Notifications | 1.5.2 | G | ||||||||||||||
| 53 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Environmental Management Plan (EMP) | 3.1 | G | ||||||||||||||
| 54 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Dirt and Dust Control Plan | 3.14.1 | G | ||||||||||||||
| 55 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Contractor Hazardous Material Inventory Log | 3.6 | G | ||||||||||||||
| 56 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Storm Water Management/Erosion and Sedimentation Control Plan | 3.2.1 | |||||||||||||||
| 57 | 01 58 00 | 02 | Shop Drawings | Preliminary One Line | 0 | G | ||||||||||||||
| 58 | 01 58 00 | 02 | Shop Drawings | Preliminary Drawing Indicating Layout And Text Content | 0 | G | ||||||||||||||
| 59 | 01 58 00 | 02 | Shop Drawings | Sign Legend Orders | 0 | G | ||||||||||||||
| 60 | 01 58 00 | 04 | Samples | Final Rendering | 0 | G | ||||||||||||||
| 61 | 01 58 00 | 04 | Samples | Final Framed Rendering | 0 | G | ||||||||||||||
| 62 | 01 74 19.00 22 | 01 | Preconstruction Submittals | Waste Management Plan | 1.3 | G | ||||||||||||||
| 63 | 01 74 19.00 22 | 11 | Closeout Submittals | Records | 1.4 | G | ||||||||||||||
| 64 | 01 78 00.00 22 | 03 | Product Data | As-Built Record of Equipment and Materials | 1.3.2 | G | ||||||||||||||
| 65 | 01 78 00.00 22 | 03 | Product Data | Warranty Management Plan | 1.7.1 | G | ||||||||||||||
| 66 | 01 78 00.00 22 | 03 | Product Data | Warranty Tags | 1.7.4 | G | ||||||||||||||
| 67 | 01 78 00.00 22 | 03 | Product Data | Final Cleaning | 0 | G | ||||||||||||||
| 68 | 01 78 00.00 22 | 03 | Product Data | Spare Parts Data | 1.4 | G | ||||||||||||||
| 69 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Preventative Maintenance | 1.5 | G | ||||||||||||||
| 70 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Condition Monitoring (Predictive Testing) | 1.5 | G | ||||||||||||||
| 71 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Inspection | 1.5 | G | ||||||||||||||
| 72 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Instructions | 1.7.1 | G | ||||||||||||||
| 73 | 01 78 00.00 22 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 1.9 | G | ||||||||||||||
| 74 | 01 78 00.00 22 | 11 | Closeout Submittals | Record Drawings | 1.3.1 | G | ||||||||||||||
| 75 | 01 78 00.00 22 | 11 | Closeout Submittals | Certification of EPA Designated Items | 1.6 | G | ||||||||||||||
| 76 | 01 78 00.00 22 | 11 | Closeout Submittals | Certification of EPA Designated Items | 1.6 | G | ||||||||||||||
| 77 | 01 78 00.00 22 | 11 | Closeout Submittals | Red Zone Documents | 1.3.6 | G | ||||||||||||||
| 78 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 0 | G | ||||||||||||||
| 79 | 01 78 23 | 10 | Operation and Maintenance Data | Training Plan | 3.1.1 | G | ||||||||||||||
| 80 | 01 78 23 | 10 | Operation and Maintenance Data | Training Outline | 3.1.3 | G | ||||||||||||||
| 81 | 01 78 23 | 10 | Operation and Maintenance Data | Training Content | 3.1.2 | G | ||||||||||||||
| 82 | 01 78 23 | 11 | Closeout Submittals | Training Video Recording | 3.1.4 | G | ||||||||||||||
| 83 | 01 78 23 | 11 | Closeout Submittals | Validation of Training Completion | 3.1.6 | G | ||||||||||||||
| 84 | 01 78 24.00 22 | 11 | Closeout Submittals | eOMSI, Progress Submittal | 1.4.1 | G | ||||||||||||||
| 85 | 01 78 24.00 22 | 11 | Closeout Submittals | eOMSI, Prefinal Submittal | 1.4.2 | G | ||||||||||||||
| 86 | 01 78 24.00 22 | 11 | Closeout Submittals | eOMSI, Final Submittal | 1.4.3 | G | ||||||||||||||
| 87 | 01 91 00.15 | 01 | Preconstruction Submittals | Commissioning Firm | 1.7 | G | ||||||||||||||
| 88 | 01 91 00.15 | 01 | Preconstruction Submittals | Lead Commissioning Specialist | 1.7.1 | G | ||||||||||||||
| 89 | 01 91 00.15 | 01 | Preconstruction Submittals | Technical Commissioning Specialists | 1.7.2 | G | ||||||||||||||
| 90 | 01 91 00.15 | 01 | Preconstruction Submittals | Commissioning Firm's Contract | 1.7 | G | ||||||||||||||
| 91 | 01 91 00.15 | 06 | Test Reports | Design Review Report | 3.1.3 | G | ||||||||||||||
| 92 | 01 91 00.15 | 06 | Test Reports | Interim Construction Phase Commissioning Plan | 3.1.2.1 | G | ||||||||||||||
| 93 | 01 91 00.15 | 06 | Test Reports | Final Construction Phase Commissioning Plan | 3.1.2.2 | G | ||||||||||||||
| 94 | 01 91 00.15 | 06 | Test Reports | Pre-Functional Checklists | 3.1.5.2 | G | ||||||||||||||
| 95 | 01 91 00.15 | 06 | Test Reports | Issues Log | 1.10 | |||||||||||||||
| 96 | 01 91 00.15 | 06 | Test Reports | Commissioning Report | 3.2 | G | ||||||||||||||
| 97 | 01 91 00.15 | 06 | Test Reports | Post-Construction Trend Log Report | 3.3.1 | G | ||||||||||||||
| 98 | 01 91 00.15 | 07 | Certificates | Certificate of Readiness | 1.11 | G | ||||||||||||||
| 99 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Plan | 3.1.6 | G | ||||||||||||||
| 100 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Attendance Rosters | 3.1.6 | G | ||||||||||||||
| 101 | 01 91 00.15 | 10 | Operation and Maintenance Data | Systems Manual | 3.1.7 | G | ||||||||||||||
| 102 | 01 91 00.15 | 10 | Operation and Maintenance Data | Systems Manual | 3.1.7 | G | ||||||||||||||
| 103 | 01 91 00.15 | 11 | Closeout Submittals | Final Commissioning Report | 3.2 | S | ||||||||||||||
| 104 | 02 41 00 | 01 | Preconstruction Submittals | Demolition Plan | 1.2.2 | G | ||||||||||||||
| 105 | 02 41 00 | 01 | Preconstruction Submittals | Deconstruction Plan | 0 | G | ||||||||||||||
| 106 | 02 41 00 | 01 | Preconstruction Submittals | Existing Conditions | 1.10 | |||||||||||||||
| 107 | 02 41 00 | 07 | Certificates | Notification | 1.6 | G | ||||||||||||||
| 108 | 02 41 00 | 11 | Closeout Submittals | Receipts | 0 | |||||||||||||||
| 109 | 02 42 91 | 01 | Preconstruction Submittals | Work Plan | 1.2 | G | ||||||||||||||
| 110 | 02 81 00 | 03 | Product Data | Packaging Notifications | 2.1.1 | |||||||||||||||
| 111 | 02 81 00 | 03 | Product Data | Hazardous Waste Management Plan | 3.1 | G | ||||||||||||||
| 112 | 02 81 00 | 03 | Product Data | Onsite Hazardous Waste Management | 3.2 | G | ||||||||||||||
| 113 | 02 81 00 | 03 | Product Data | Notices of Non-Compliance and Notices of Violation | 3.3 | |||||||||||||||
| 114 | 02 81 00 | 06 | Test Reports | Recordkeeping | 3.7 | G | ||||||||||||||
| 115 | 02 81 00 | 06 | Test Reports | Exception Report | 3.7 | G | ||||||||||||||
| 116 | 02 81 00 | 06 | Test Reports | Spill Response | 3.8 | |||||||||||||||
| 117 | 02 81 00 | 07 | Certificates | Transportation and Disposal Coordinator | 1.4.1 | G | ||||||||||||||
| 118 | 02 81 00 | 07 | Certificates | Training | 1.4.2 | G | ||||||||||||||
| 119 | 02 81 00 | 07 | Certificates | Certification | 1.4.3 | |||||||||||||||
| 120 | 02 81 00 | 07 | Certificates | Shipping Documents and Packagings Certification | 3.3.3 | G | ||||||||||||||
| 121 | 02 81 00 | 07 | Certificates | Security Plan | 3.3.4 | |||||||||||||||
| 122 | 02 81 00 | 07 | Certificates | Certificates of Disposal | 3.3.5 | |||||||||||||||
| 123 | 02 81 00 | 07 | Certificates | Waste Minimization | 3.6 | |||||||||||||||
| 124 | 02 82 00.00 22 | 03 | Product Data | Amended Water | 1.2.2 | G | ||||||||||||||
| 125 | 02 82 00.00 22 | 03 | Product Data | Safety Data Sheets (SDS) for All Materials | 1.3.9 | G | ||||||||||||||
| 126 | 02 82 00.00 22 | 03 | Product Data | Encapsulants | 2.1 | G | ||||||||||||||
| 127 | 02 82 00.00 22 | 03 | Product Data | Respirators | 3.1.2.1 | G | ||||||||||||||
| 128 | 02 82 00.00 22 | 03 | Product Data | Local Exhaust Equipment | 3.1.7 | G | ||||||||||||||
| 129 | 02 82 00.00 22 | 03 | Product Data | Pressure Differential Automatic Recording Instrument | 3.1.7 | G | ||||||||||||||
| 130 | 02 82 00.00 22 | 03 | Product Data | Vacuums | 3.1.8 | G | ||||||||||||||
| 131 | 02 82 00.00 22 | 03 | Product Data | Glovebags | 3.1.10 | G | ||||||||||||||
| 132 | 02 82 00.00 22 | 06 | Test Reports | Air Sampling Results | 1.5.5 | G | ||||||||||||||
| 133 | 02 82 00.00 22 | 06 | Test Reports | Pressure Differential Recordings for Local Exhaust System | 1.5.6 | G | ||||||||||||||
| 134 | 02 82 00.00 22 | 06 | Test Reports | Clearance Sampling | 3.2.13.5 | G | ||||||||||||||
| 135 | 02 82 00.00 22 | 06 | Test Reports | Asbestos Disposal Quantity Report | 3.3.3.2 | G | ||||||||||||||
| 136 | 02 82 00.00 22 | 07 | Certificates | Employee Training | 1.3.4 | G | ||||||||||||||
| 137 | 02 82 00.00 22 | 07 | Certificates | Notifications | 1.3.5 | G | ||||||||||||||
| 138 | 02 82 00.00 22 | 07 | Certificates | Respiratory Protection Program | 1.3.7 | G | ||||||||||||||
| 139 | 02 82 00.00 22 | 07 | Certificates | Asbestos Hazard Abatement Plan | 1.3.10 | G | ||||||||||||||
| 140 | 02 82 00.00 22 | 07 | Certificates | Testing Laboratory | 1.3.11 | G | ||||||||||||||
| 141 | 02 82 00.00 22 | 07 | Certificates | Medical Certification | 1.3.14 | G | ||||||||||||||
| 142 | 02 82 00.00 22 | 07 | Certificates | Private Qualified Person Documentation | 1.5.1 | G | ||||||||||||||
| 143 | 02 82 00.00 22 | 07 | Certificates | Competent Person | 1.5.2 | G | ||||||||||||||
| 144 | 02 82 00.00 22 | 07 | Certificates | Worker's License | 1.5.3 | G | ||||||||||||||
| 145 | 02 82 00.00 22 | 07 | Certificates | Contractor's License | 1.5.4 | G | ||||||||||||||
| 146 | 02 82 00.00 22 | 07 | Certificates | Federal, State or Local Citations on Previous Projects | 1.5.7 | G | ||||||||||||||
| 147 | 02 82 00.00 22 | 07 | Certificates | Encapsulants | 2.1 | G | ||||||||||||||
| 148 | 02 82 00.00 22 | 07 | Certificates | Equipment Used to Contain Airborne Asbestos Fibers | 3.1 | G | ||||||||||||||
| 149 | 02 82 00.00 22 | 07 | Certificates | Water Filtration Equipment | 3.1.3.3 | G | ||||||||||||||
| 150 | 02 82 00.00 22 | 07 | Certificates | Vacuums | 3.1.8 | G | ||||||||||||||
| 151 | 02 82 00.00 22 | 07 | Certificates | Ventilation Systems | 3.1.8 | G | ||||||||||||||
| 152 | 02 82 00.00 22 | 11 | Closeout Submittals | Permits | 1.3.5 | |||||||||||||||
| 153 | 02 82 00.00 22 | 11 | Closeout Submittals | Licenses | 1.3.5 | G | ||||||||||||||
| 154 | 02 82 00.00 22 | 11 | Closeout Submittals | Notifications | 1.3.5 | G | ||||||||||||||
| 155 | 02 82 00.00 22 | 11 | Closeout Submittals | Respirator Program Records | 1.3.7.1 | G | ||||||||||||||
| 156 | 02 82 00.00 22 | 11 | Closeout Submittals | Rental Equipment | 1.7.1 | G | ||||||||||||||
| 157 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Competent Person | 1.5.1.1 | G | ||||||||||||||
| 158 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Training Certification | 1.5.1.2 | G | ||||||||||||||
| 159 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Occupational and Environmental Assessment Data Report | 1.5.2.3 | G | ||||||||||||||
| 160 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Medical Examinations | 1.5.2.4 | G | ||||||||||||||
| 161 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Lead, Cadmium, and Chromium Waste Management Plan | 1.5.2.8 | G | ||||||||||||||
| 162 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Licenses, Permits and Notifications | 1.5.4 | G | ||||||||||||||
| 163 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Occupant Protection Plan | 1.5.2.1 | G | ||||||||||||||
| 164 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Occupant Protection Plan | 1.5.5 | G | ||||||||||||||
| 165 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Lead, Cadmium, and Chromium Compliance Plan | 1.5.2.2 | G | ||||||||||||||
| 166 | 02 83 00.00 22 | 01 | Preconstruction Submittals | Initial Sample Results | 3.4.1.1 | G | ||||||||||||||
| 167 | 02 83 00.00 22 | 03 | Product Data | Respirators | 1.6.1 | G | ||||||||||||||
| 168 | 02 83 00.00 22 | 03 | Product Data | Vacuum Filters | 1.6.4 | G | ||||||||||||||
| 169 | 02 83 00.00 22 | 03 | Product Data | Negative Air Pressure System | 1.6.7 | G | ||||||||||||||
| 170 | 02 83 00.00 22 | 03 | Product Data | Materials and Equipment | 2.1 | G | ||||||||||||||
| 171 | 02 83 00.00 22 | 03 | Product Data | Expendable Supplies | 2.1.1 | G | ||||||||||||||
| 172 | 02 83 00.00 22 | 03 | Product Data | Local Exhaust Equipment | 3.1.1.5 | G | ||||||||||||||
| 173 | 02 83 00.00 22 | 03 | Product Data | Pressure Differential Automatic Recording Instrument | 3.1.1.5 | G | ||||||||||||||
| 174 | 02 83 00.00 22 | 03 | Product Data | Pressure Differential Log | 3.1.1.6 | G | ||||||||||||||
| 175 | 02 83 00.00 22 | 06 | Test Reports | Sampling and Analysis | 1.3.3 | G | ||||||||||||||
| 176 | 02 83 00.00 22 | 06 | Test Reports | Occupational and Environmental Assessment Data Report | 1.5.2.3 | G | ||||||||||||||
| 177 | 02 83 00.00 22 | 06 | Test Reports | Sampling Results | 1.5.2.3 | G | ||||||||||||||
| 178 | 02 83 00.00 22 | 06 | Test Reports | Pressure Differential Recordings For Local Exhaust System | 1.5.3 | G | ||||||||||||||
| 179 | 02 83 00.00 22 | 07 | Certificates | Testing Laboratory | 1.5.1.3 | G | ||||||||||||||
| 180 | 02 83 00.00 22 | 07 | Certificates | Third Party Consultant Qualifications | 1.5.1.4 | G | ||||||||||||||
| 181 | 02 83 00.00 22 | 07 | Certificates | Occupant Notification | 3.1.1.1 | G | ||||||||||||||
| 182 | 02 83 00.00 22 | 07 | Certificates | Notification of the Commencement of Hazard Abatement | 0 | G | ||||||||||||||
| 183 | 02 83 00.00 22 | 07 | Certificates | Clearance Certification | 3.5.1.1 | G | ||||||||||||||
| 184 | 02 83 00.00 22 | 11 | Closeout Submittals | Turn-In Documents or Weight Tickets | 3.5.2.1 | G | ||||||||||||||
| 185 | 03 30 00 | 01 | Preconstruction Submittals | Concrete Curing Plan | 1.6.3.1 | |||||||||||||||
| 186 | 03 30 00 | 01 | Preconstruction Submittals | Quality Control Plan | 1.6.6 | G | ||||||||||||||
| 187 | 03 30 00 | 01 | Preconstruction Submittals | Quality Control Personnel Certifications | 1.6.7 | G | ||||||||||||||
| 188 | 03 30 00 | 01 | Preconstruction Submittals | Quality Control Organizational Chart | 1.6.7 | |||||||||||||||
| 189 | 03 30 00 | 01 | Preconstruction Submittals | Laboratory Accreditation | 1.6.9 | G | ||||||||||||||
| 190 | 03 30 00 | 01 | Preconstruction Submittals | Form Removal Schedule | 1.6.2.1 | G | ||||||||||||||
| 191 | 03 30 00 | 01 | Preconstruction Submittals | Maturity Method Data | 3.3.10 | |||||||||||||||
| 192 | 03 30 00 | 02 | Shop Drawings | Formwork | 1.6.2.1 | |||||||||||||||
| 193 | 03 30 00 | 02 | Shop Drawings | Reinforcing Steel | 1.6.2.2 | G | ||||||||||||||
| 194 | 03 30 00 | 03 | Product Data | Joint Sealants | 2.4.4 | |||||||||||||||
| 195 | 03 30 00 | 03 | Product Data | Joint Filler | 0 | |||||||||||||||
| 196 | 03 30 00 | 03 | Product Data | Formwork Materials | 2.1 | |||||||||||||||
| 197 | 03 30 00 | 03 | Product Data | Recycled Aggregate Materials | 0 | |||||||||||||||
| 198 | 03 30 00 | 03 | Product Data | Cementitious Materials | 2.3.1 | |||||||||||||||
| 199 | 03 30 00 | 03 | Product Data | Vapor Retarder and Vapor Barrier | 0 | |||||||||||||||
| 200 | 03 30 00 | 03 | Product Data | Concrete Curing Materials | 2.4.1 | |||||||||||||||
| 201 | 03 30 00 | 03 | Product Data | Reinforcement | 2.6 | |||||||||||||||
| 202 | 03 30 00 | 03 | Product Data | Liquid Chemical Floor Hardeners and Sealers | 2.4.3.1 | |||||||||||||||
| 203 | 03 30 00 | 03 | Product Data | Admixtures | 2.3.4 | |||||||||||||||
| 204 | 03 30 00 | 03 | Product Data | Reinforcing Fibers | 0 | |||||||||||||||
| 205 | 03 30 00 | 03 | Product Data | Mechanical Reinforcing Bar Connectors | 2.6.2 | |||||||||||||||
| 206 | 03 30 00 | 03 | Product Data | Waterstops | 2.2.2 | |||||||||||||||
| 207 | 03 30 00 | 03 | Product Data | Local/Regional Materials | 1.8.1 | |||||||||||||||
| 208 | 03 30 00 | 03 | Product Data | Biodegradable Form Release Agent | 2.2.3 | |||||||||||||||
| 209 | 03 30 00 | 03 | Product Data | Pumping Concrete | 1.6.3.2 | |||||||||||||||
| 210 | 03 30 00 | 03 | Product Data | Finishing Plan | 1.6.3.4 | |||||||||||||||
| 211 | 03 30 00 | 03 | Product Data | Nonshrink Grout | 2.4.2 | |||||||||||||||
| 212 | 03 30 00 | 04 | Samples | Slab Finish Sample | 0 | |||||||||||||||
| 213 | 03 30 00 | 04 | Samples | Surface Finish Samples | 0 | |||||||||||||||
| 214 | 03 30 00 | 05 | Design Data | Concrete Mix Design | 1.6.1.2 | |||||||||||||||
| 215 | 03 30 00 | 05 | Design Data | Formwork Calculations | 1.6.1.1 | |||||||||||||||
| 216 | 03 30 00 | 06 | Test Reports | Concrete Mix Design | 1.6.1.2 | |||||||||||||||
| 217 | 03 30 00 | 06 | Test Reports | Fly Ash | 1.6.4.1 | |||||||||||||||
| 218 | 03 30 00 | 06 | Test Reports | Pozzolan | 1.6.4.1 | |||||||||||||||
| 219 | 03 30 00 | 06 | Test Reports | Slag Cement | 1.6.4.2 | |||||||||||||||
| 220 | 03 30 00 | 06 | Test Reports | Aggregates | 1.6.4.3 | |||||||||||||||
| 221 | 03 30 00 | 06 | Test Reports | Fiber-Reinforced Concrete | 1.6.4.4 | |||||||||||||||
| 222 | 03 30 00 | 06 | Test Reports | Tolerance Report | 3.9.2.1 | |||||||||||||||
| 223 | 03 30 00 | 06 | Test Reports | Compressive Strength Tests | 3.13.2.3 | |||||||||||||||
| 224 | 03 30 00 | 06 | Test Reports | Unit Weight of Structural Concrete | 3.13.2.5 | |||||||||||||||
| 225 | 03 30 00 | 06 | Test Reports | Chloride Ion Concentration | 3.13.2.6 | |||||||||||||||
| 226 | 03 30 00 | 06 | Test Reports | Air Content | 3.13.2.4 | |||||||||||||||
| 227 | 03 30 00 | 06 | Test Reports | Slump Tests | 3.13.2.1 | |||||||||||||||
| 228 | 03 30 00 | 06 | Test Reports | Water | 2.3.2 | |||||||||||||||
| 229 | 03 30 00 | 07 | Certificates | Reinforcing Bars | 2.6.1 | |||||||||||||||
| 230 | 03 30 00 | 07 | Certificates | Welder Qualifications | 1.9 | |||||||||||||||
| 231 | 03 30 00 | 07 | Certificates | Silica Fume Manufacturer's Representative | 1.6.3.3 | |||||||||||||||
| 232 | 03 30 00 | 07 | Certificates | VOC Content for Form Release Agents, Curing Compounds, and Concrete Penetrating Sealers | 1.6.3.5 | |||||||||||||||
| 233 | 03 30 00 | 07 | Certificates | Safety Data Sheets | 1.6.3.6 | |||||||||||||||
| 234 | 03 30 00 | 07 | Certificates | Forest Stewardship Council (FSC) Certification | 1.8.2 | |||||||||||||||
| 235 | 03 30 00 | 07 | Certificates | Field Testing Technician and Testing Agency | 1.6.7.2 | |||||||||||||||
| 236 | 03 30 00 | 08 | Manufacturer’s Instructions | Liquid Chemical Floor Hardeners and Sealers | 2.4.3.1 | |||||||||||||||
| 237 | 03 30 00 | 08 | Manufacturer’s Instructions | Joint Sealants | 2.4.4 | |||||||||||||||
| 238 | 03 30 00 | 08 | Manufacturer’s Instructions | Curing Compound | 2.4.1 | |||||||||||||||
| 239 | 06 10 00 | 02 | Shop Drawings | Structural Glued Laminated | 0 | G | ||||||||||||||
| 240 | 06 10 00 | 02 | Shop Drawings | Trussed Rafters | 0 | G | ||||||||||||||
| 241 | 06 10 00 | 02 | Shop Drawings | Trussed Joists | 0 | G | ||||||||||||||
| 242 | 06 10 00 | 02 | Shop Drawings | Fabricated Structural Members | 1.8.1 | G | ||||||||||||||
| 243 | 06 10 00 | 02 | Shop Drawings | Modifications of Structural Members | 1.8.2 | G | ||||||||||||||
| 244 | 06 10 00 | 02 | Shop Drawings | Nailing Strips | 2.2.2 | G | ||||||||||||||
| 245 | 06 10 00 | 03 | Product Data | Salvaged Lumber | 2.1.2 | |||||||||||||||
| 246 | 06 10 00 | 03 | Product Data | Recovered Lumber | 2.1.3 | |||||||||||||||
| 247 | 06 10 00 | 03 | Product Data | Underlayment | 0 | |||||||||||||||
| 248 | 06 10 00 | 03 | Product Data | Plastic Lumber | 0 | |||||||||||||||
| 249 | 06 10 00 | 03 | Product Data | Fiberboard Wall Sheathing | 0 | |||||||||||||||
| 250 | 06 10 00 | 03 | Product Data | Cellulose Honeycomb Panels | 0 | |||||||||||||||
| 251 | 06 10 00 | 03 | Product Data | Fire-retardant Treatment | 0 | |||||||||||||||
| 252 | 06 10 00 | 03 | Product Data | Structural-use and OSB Panels | 1.4.4 | |||||||||||||||
| 253 | 06 10 00 | 03 | Product Data | Oriented Strand Board | 2.3 | |||||||||||||||
| 254 | 06 10 00 | 03 | Product Data | Adhesives | 2.4.5 | |||||||||||||||
| 255 | 06 10 00 | 05 | Design Data | Modifications of Structural Members | 1.8.2 | G | ||||||||||||||
| 256 | 06 10 00 | 06 | Test Reports | Preservative-treated | 1.4.5 | |||||||||||||||
| 257 | 06 10 00 | 07 | Certificates | Preservative Treatment | 1.7 | |||||||||||||||
| 258 | 06 10 00 | 10 | Operation and Maintenance Data | Plastic | 1.4.8 | |||||||||||||||
| 259 | 06 10 00 | 10 | Operation and Maintenance Data | Take-back Program | 0 | |||||||||||||||
| 260 | 07 84 00 | 02 | Shop Drawings | Firestopping System | 2.1 | G | ||||||||||||||
| 261 | 07 84 00 | 03 | Product Data | Firestopping Materials | 2.2 | G | ||||||||||||||
| 262 | 07 84 00 | 06 | Test Reports | Inspection | 3.3 | G | ||||||||||||||
| 263 | 07 84 00 | 07 | Certificates | Inspector Qualifications | 1.5.2 | |||||||||||||||
| 264 | 07 84 00 | 07 | Certificates | Firestopping Materials | 2.2 | |||||||||||||||
| 265 | 07 84 00 | 07 | Certificates | Installer Qualifications | 1.5.1 | G | ||||||||||||||
| 266 | 08 11 13 | 02 | Shop Drawings | Doors | 2.1 | G | ||||||||||||||
| 267 | 08 11 13 | 02 | Shop Drawings | Doors | 2.1 | G | ||||||||||||||
| 268 | 08 11 13 | 02 | Shop Drawings | Recycled Content for Steel Door Product | 2.1 | S | ||||||||||||||
| 269 | 08 11 13 | 02 | Shop Drawings | Frames | 2.7 | G | ||||||||||||||
| 270 | 08 11 13 | 02 | Shop Drawings | Frames | 2.7 | G | ||||||||||||||
| 271 | 08 11 13 | 02 | Shop Drawings | Recycled Content for Steel Frame Product | 2.7 | S | ||||||||||||||
| 272 | 08 11 13 | 02 | Shop Drawings | Accessories | 2.5 | |||||||||||||||
| 273 | 08 11 13 | 02 | Shop Drawings | Weatherstripping | 2.9 | |||||||||||||||
| 274 | 08 11 13 | 03 | Product Data | Doors | 2.1 | G | ||||||||||||||
| 275 | 08 11 13 | 03 | Product Data | Frames | 2.7 | G | ||||||||||||||
| 276 | 08 11 13 | 03 | Product Data | Accessories | 2.5 | |||||||||||||||
| 277 | 08 11 13 | 03 | Product Data | Weatherstripping | 2.9 | |||||||||||||||
| 278 | 08 11 16 | 02 | Shop Drawings | Door and Frame Assembly | 1.4.1 | G | ||||||||||||||
| 279 | 08 11 16 | 03 | Product Data | Door and Frame Assembly | 1.4.1 | G | ||||||||||||||
| 280 | 08 11 16 | 03 | Product Data | Recycled Content of Aluminum Material | 2.2.3 | S | ||||||||||||||
| 281 | 08 11 16 | 04 | Samples | Finish Samples | 1.4.2 | G | ||||||||||||||
| 282 | 08 11 16 | 05 | Design Data | NFRC Project Label Certificates for Fenestration | 0 | G | ||||||||||||||
| 283 | 08 11 16 | 08 | Manufacturer’s Instructions | Door and Frame Assembly | 1.4.1 | G | ||||||||||||||
| 284 | 08 11 16 | 08 | Manufacturer’s Instructions | Adjustments, Cleaning, and Maintenance | 1.4.4 | G | ||||||||||||||
| 285 | 08 11 16 | 08 | Manufacturer’s Instructions | NFRC Project Label Certificates for Fenestration | 0 | G | ||||||||||||||
| 286 | 09 51 00 | 02 | Shop Drawings | Approved Detail Drawings | 2.1 | G | ||||||||||||||
| 287 | 09 51 00 | 03 | Product Data | Acoustical Ceiling Systems | 2.1.1 | G | ||||||||||||||
| 288 | 09 51 00 | 04 | Samples | Acoustical Units | 2.2 | G | ||||||||||||||
| 289 | 09 51 00 | 04 | Samples | Acoustical Ceiling Tiles | 2.2.1.1 | G | ||||||||||||||
| 290 | 09 51 00 | 06 | Test Reports | Fire Resistive Ceilings | 2.1.1 | G | ||||||||||||||
| 291 | 09 51 00 | 06 | Test Reports | Ceiling Attenuation Class and Test | 2.1.2 | G | ||||||||||||||
| 292 | 09 65 00 | 02 | Shop Drawings | Resilient Flooring and Accessories | 2.8 | G | ||||||||||||||
| 293 | 09 65 00 | 03 | Product Data | Resilient Flooring and Accessories | 2.8 | G | ||||||||||||||
| 294 | 09 65 00 | 03 | Product Data | Adhesives | 2.4 | |||||||||||||||
| 295 | 09 65 00 | 03 | Product Data | Vinyl Composition Tile | 0 | |||||||||||||||
| 296 | 09 65 00 | 03 | Product Data | Sheet Vinyl Flooring | 0 | |||||||||||||||
| 297 | 09 65 00 | 03 | Product Data | Luxury Vinyl Tile | 0 | |||||||||||||||
| 298 | 09 65 00 | 03 | Product Data | Rubber Tile | 0 | |||||||||||||||
| 299 | 09 65 00 | 03 | Product Data | Rubber Sheet Flooring | 0 | |||||||||||||||
| 300 | 09 65 00 | 03 | Product Data | Solid Vinyl Tile | 0 | |||||||||||||||
| 301 | 09 65 00 | 03 | Product Data | Cement-Fiber Board | 0 | |||||||||||||||
| 302 | 09 65 00 | 03 | Product Data | Wall Base | 2.1 | |||||||||||||||
| 303 | 09 65 00 | 03 | Product Data | Stair Treads, Risers and Stringers | 0 | |||||||||||||||
| 304 | 09 65 00 | 03 | Product Data | Linoleum Tile | 0 | |||||||||||||||
| 305 | 09 65 00 | 03 | Product Data | Cork Flooring | 0 | |||||||||||||||
| 306 | 09 65 00 | 04 | Samples | Resilient Flooring and Accessories | 2.8 | G | ||||||||||||||
| 307 | 09 65 00 | 06 | Test Reports | Moisture, Alkalinity and Bond Tests | 3.3 | G | ||||||||||||||
| 308 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Vinyl Composition Tile | 0 | S | ||||||||||||||
| 309 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Sheet Vinyl Flooring | 0 | S | ||||||||||||||
| 310 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Luxury Vinyl Tile | 0 | S | ||||||||||||||
| 311 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Solid Vinyl Tile | 0 | S | ||||||||||||||
| 312 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Cork Flooring | 0 | S | ||||||||||||||
| 313 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Wall Base | 2.1 | S | ||||||||||||||
| 314 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Adhesives | 2.4 | S | ||||||||||||||
| 315 | 09 65 00 | 08 | Manufacturer’s Instructions | Surface Preparation | 3.2 | G | ||||||||||||||
| 316 | 09 65 00 | 08 | Manufacturer’s Instructions | Installation | 3.1 | G | ||||||||||||||
| 317 | 09 65 00 | 10 | Operation and Maintenance Data | Resilient Flooring and Accessories | 2.8 | G | ||||||||||||||
| 318 | 09 90 00 | 02 | Shop Drawings | Piping Identification | 0 | |||||||||||||||
| 319 | 09 90 00 | 03 | Product Data | Coating | 2.1 | G | ||||||||||||||
| 320 | 09 90 00 | 03 | Product Data | Sealant | 0 | |||||||||||||||
| 321 | 09 90 00 | 04 | Samples | Color | 1.11 | G | ||||||||||||||
| 322 | 09 90 00 | 04 | Samples | Textured Wall Coating System | 1.5.2 | G | ||||||||||||||
| 323 | 09 90 00 | 07 | Certificates | Applicator's Qualifications | 1.4 | |||||||||||||||
| 324 | 09 90 00 | 07 | Certificates | Qualification Testing | 1.5.1.2 | G | ||||||||||||||
| 325 | 09 90 00 | 07 | Certificates | Indoor Air Quality for Paints and Primers | 2.1 | |||||||||||||||
| 326 | 09 90 00 | 07 | Certificates | Indoor Air Quality for Consolidated Latex Paints | 2.1 | |||||||||||||||
| 327 | 09 90 00 | 08 | Manufacturer’s Instructions | Application Instructions | 3.3.1 | |||||||||||||||
| 328 | 09 90 00 | 08 | Manufacturer’s Instructions | Mixing | 3.7.2 | |||||||||||||||
| 329 | 09 90 00 | 08 | Manufacturer’s Instructions | Manufacturer's Safety Data Sheets | 1.8.2 | |||||||||||||||
| 330 | 09 90 00 | 10 | Operation and Maintenance Data | Coatings | 2.1 | G | ||||||||||||||
| 331 | 21 13 13.00 20 | 02 | Shop Drawings | Shop Drawings | 1.5.2 | G | ||||||||||||||
| 332 | 21 13 13.00 20 | 03 | Product Data | Pipe | 2.1.1 | G | ||||||||||||||
| 333 | 21 13 13.00 20 | 03 | Product Data | Fittings | 2.1.1 | G | ||||||||||||||
| 334 | 21 13 13.00 20 | 03 | Product Data | Sprinklers | 2.1.4 | G | ||||||||||||||
| 335 | 21 13 13.00 20 | 03 | Product Data | Pipe hangers and supports | 2.1.5 | G | ||||||||||||||
| 336 | 21 13 13.00 20 | 03 | Product Data | Mechanical couplings | 2.1.1 | G | ||||||||||||||
| 337 | 21 13 13.00 20 | 05 | Design Data | Hydraulic Calculations | 0 | G | ||||||||||||||
| 338 | 21 13 13.00 20 | 06 | Test Reports | request to schedule Preliminary Tests | 3.5 | G | ||||||||||||||
| 339 | 21 13 13.00 20 | 06 | Test Reports | Preliminary Test Report | 3.5 | G | ||||||||||||||
| 340 | 21 13 13.00 20 | 06 | Test Reports | request to schedule Final Acceptance Test | 3.6 | G | ||||||||||||||
| 341 | 21 13 13.00 20 | 06 | Test Reports | Final Acceptance Test Report | 3.6 | G | ||||||||||||||
| 342 | 21 13 13.00 20 | 07 | Certificates | Inspection by Fire Protection Engineer | 3.1 | G | ||||||||||||||
| 343 | 21 13 13.00 20 | 07 | Certificates | Fire Protection Engineer | 1.5.1 | G | ||||||||||||||
| 344 | 21 13 13.00 20 | 07 | Certificates | Sprinkler System Installer | 1.5.2 | G | ||||||||||||||
| 345 | 21 13 13.00 20 | 10 | Operation and Maintenance Data | Operating and Maintenance Instructions | 0 | |||||||||||||||
| 346 | 21 13 13.00 20 | 11 | Closeout Submittals | As-built drawings | 3.6 | |||||||||||||||
| 347 | 21 13 13.00 20 | 11 | Closeout Submittals | On-site training | 0 | |||||||||||||||
| 348 | 23 00 00 | 02 | Shop Drawings | Detail Drawings | 1.4.4 | G | ||||||||||||||
| 349 | 23 00 00 | 03 | Product Data | Metallic Flexible Duct | 2.9.1.1 | |||||||||||||||
| 350 | 23 00 00 | 03 | Product Data | Insulated Nonmetallic Flexible Duct Runouts | 2.9.1.2 | |||||||||||||||
| 351 | 23 00 00 | 03 | Product Data | Duct Connectors | 2.9.1.2 | |||||||||||||||
| 352 | 23 00 00 | 03 | Product Data | Duct Access Doors | 2.9.2 | G | ||||||||||||||
| 353 | 23 00 00 | 03 | Product Data | Fire Dampers | 0 | |||||||||||||||
| 354 | 23 00 00 | 03 | Product Data | Manual Balancing Dampers | 2.9.3 | G | ||||||||||||||
| 355 | 23 00 00 | 03 | Product Data | Automatic Smoke-Fire Dampers | 2.9.5 | |||||||||||||||
| 356 | 23 00 00 | 03 | Product Data | Automatic Smoke Dampers | 2.9.6 | |||||||||||||||
| 357 | 23 00 00 | 03 | Product Data | Sound Attenuation Equipment | 0 | |||||||||||||||
| 358 | 23 00 00 | 03 | Product Data | Acoustical Duct Liner | 0 | |||||||||||||||
| 359 | 23 00 00 | 03 | Product Data | Diffusers | 2.9.7.1 | |||||||||||||||
| 360 | 23 00 00 | 03 | Product Data | Registers and Grilles | 2.9.7.2 | |||||||||||||||
| 361 | 23 00 00 | 03 | Product Data | Louvers | 0 | |||||||||||||||
| 362 | 23 00 00 | 03 | Product Data | Air Vents, Penthouses, and Goosenecks | 0 | |||||||||||||||
| 363 | 23 00 00 | 03 | Product Data | Centrifugal Fans | 2.10.1.1 | |||||||||||||||
| 364 | 23 00 00 | 03 | Product Data | In-Line Centrifugal Fans | 2.10.1.2 | |||||||||||||||
| 365 | 23 00 00 | 03 | Product Data | Axial Flow Fans | 0 | |||||||||||||||
| 366 | 23 00 00 | 03 | Product Data | Panel Type Power Wall Ventilators | 0 | |||||||||||||||
| 367 | 23 00 00 | 03 | Product Data | Centrifugal Type Power Wall Ventilators | 2.10.1.3 | |||||||||||||||
| 368 | 23 00 00 | 03 | Product Data | Centrifugal Type Power Roof Ventilators | 0 | |||||||||||||||
| 369 | 23 00 00 | 03 | Product Data | Propeller Type Power Roof Ventilators | 0 | |||||||||||||||
| 370 | 23 00 00 | 03 | Product Data | Air-Curtain Fans | 0 | |||||||||||||||
| 371 | 23 00 00 | 03 | Product Data | Ceiling Exhaust Fans | 0 | |||||||||||||||
| 372 | 23 00 00 | 03 | Product Data | Energy Star label for ceiling exhaust fan product | 0 | S | ||||||||||||||
| 373 | 23 00 00 | 03 | Product Data | Air Handling Units | 0 | G | ||||||||||||||
| 374 | 23 00 00 | 03 | Product Data | Room Fan-Coil Units | 0 | G | ||||||||||||||
| 375 | 23 00 00 | 03 | Product Data | Coil Induction Units | 0 | G | ||||||||||||||
| 376 | 23 00 00 | 03 | Product Data | Constant Volume, Single Duct Terminal Units | 0 | G | ||||||||||||||
| 377 | 23 00 00 | 03 | Product Data | Variable Volume, Single Duct Terminal Units | 0 | G | ||||||||||||||
| 378 | 23 00 00 | 03 | Product Data | Variable Volume, Single Duct, Fan-Powered Terminal Units | 0 | G | ||||||||||||||
| 379 | 23 00 00 | 03 | Product Data | Dual Duct Terminal Units | 0 | G | ||||||||||||||
| 380 | 23 00 00 | 03 | Product Data | Ceiling Induction Terminal Units | 0 | G | ||||||||||||||
| 381 | 23 00 00 | 03 | Product Data | Reheat Units | 0 | G | ||||||||||||||
| 382 | 23 00 00 | 03 | Product Data | Unit Ventilators | 2.11.1 | |||||||||||||||
| 383 | 23 00 00 | 03 | Product Data | Energy Recovery Devices | 0 | G | ||||||||||||||
| 384 | 23 00 00 | 03 | Product Data | Hydronic Modular Panels | 0 | G | ||||||||||||||
| 385 | 23 00 00 | 03 | Product Data | Prefabricated Radiant-Heating Electric Panels | 0 | G | ||||||||||||||
| 386 | 23 00 00 | 03 | Product Data | Test Procedures | 1.4.5 | |||||||||||||||
| 387 | 23 00 00 | 03 | Product Data | Diagrams | 1.2.1.2 | G | ||||||||||||||
| 388 | 23 00 00 | 03 | Product Data | Indoor Air Quality for Duct Sealants | 2.9.1 | S | ||||||||||||||
| 389 | 23 00 00 | 06 | Test Reports | Performance Tests | 3.11 | G | ||||||||||||||
| 390 | 23 00 00 | 06 | Test Reports | Damper Acceptance Test | 0 | G | ||||||||||||||
| 391 | 23 00 00 | 07 | Certificates | Bolts | 1.4.1 | |||||||||||||||
| 392 | 23 00 00 | 07 | Certificates | Ozone Depleting Substances Technician Certification | 1.4.3 | |||||||||||||||
| 393 | 23 00 00 | 08 | Manufacturer’s Instructions | Manufacturer's Installation Instructions | 3.2 | |||||||||||||||
| 394 | 23 00 00 | 08 | Manufacturer’s Instructions | Operation and Maintenance Training | 3.13.2 | |||||||||||||||
| 395 | 23 00 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.13.1 | G | ||||||||||||||
| 396 | 23 00 00 | 10 | Operation and Maintenance Data | Fire Dampers | 0 | G | ||||||||||||||
| 397 | 23 00 00 | 10 | Operation and Maintenance Data | Manual Balancing Dampers | 2.9.3 | G | ||||||||||||||
| 398 | 23 00 00 | 10 | Operation and Maintenance Data | Automatic Smoke-Fire Dampers | 2.9.5 | G | ||||||||||||||
| 399 | 23 00 00 | 10 | Operation and Maintenance Data | Automatic Smoke Dampers | 2.9.6 | G | ||||||||||||||
| 400 | 23 00 00 | 10 | Operation and Maintenance Data | Centrifugal Fans | 2.10.1.1 | G | ||||||||||||||
| 401 | 23 00 00 | 10 | Operation and Maintenance Data | In-Line Centrifugal Fans | 2.10.1.2 | G | ||||||||||||||
| 402 | 23 00 00 | 10 | Operation and Maintenance Data | Axial Flow Fans | 0 | G | ||||||||||||||
| 403 | 23 00 00 | 10 | Operation and Maintenance Data | Panel Type Power Wall Ventilators | 0 | G | ||||||||||||||
| 404 | 23 00 00 | 10 | Operation and Maintenance Data | Centrifugal Type Power Wall Ventilators | 2.10.1.3 | G | ||||||||||||||
| 405 | 23 00 00 | 10 | Operation and Maintenance Data | Centrifugal Type Power Roof Ventilators | 0 | G | ||||||||||||||
| 406 | 23 00 00 | 10 | Operation and Maintenance Data | Propeller Type Power Roof Ventilators | 0 | G | ||||||||||||||
| 407 | 23 00 00 | 10 | Operation and Maintenance Data | Air-Curtain Fans | 0 | G | ||||||||||||||
| 408 | 23 00 00 | 10 | Operation and Maintenance Data | Ceiling Exhaust Fans | 0 | G | ||||||||||||||
| 409 | 23 00 00 | 10 | Operation and Maintenance Data | Air Handling Units | 0 | G | ||||||||||||||
| 410 | 23 00 00 | 10 | Operation and Maintenance Data | Room Fan-Coil Units | 0 | G | ||||||||||||||
| 411 | 23 00 00 | 10 | Operation and Maintenance Data | Coil Induction Units | 0 | G | ||||||||||||||
| 412 | 23 00 00 | 10 | Operation and Maintenance Data | Constant Volume, Single Duct Terminal Units | 0 | G | ||||||||||||||
| 413 | 23 00 00 | 10 | Operation and Maintenance Data | Variable Volume, Single Duct Terminal Units | 0 | G | ||||||||||||||
| 414 | 23 00 00 | 10 | Operation and Maintenance Data | Variable Volume, Single Duct, Fan-Powered Terminal Units | 0 | G | ||||||||||||||
| 415 | 23 00 00 | 10 | Operation and Maintenance Data | Dual Duct Terminal Units | 0 | G | ||||||||||||||
| 416 | 23 00 00 | 10 | Operation and Maintenance Data | Ceiling Induction Terminal Units | 0 | G | ||||||||||||||
| 417 | 23 00 00 | 10 | Operation and Maintenance Data | Reheat Units | 0 | G | ||||||||||||||
| 418 | 23 00 00 | 10 | Operation and Maintenance Data | Unit Ventilators | 2.11.1 | G | ||||||||||||||
| 419 | 23 00 00 | 10 | Operation and Maintenance Data | Energy Recovery Devices | 0 | G | ||||||||||||||
| 420 | 23 00 00 | 10 | Operation and Maintenance Data | Hydronic Modular Panels | 0 | G | ||||||||||||||
| 421 | 23 00 00 | 10 | Operation and Maintenance Data | Prefabricated Radiant-Heating Electric Panels | 0 | G | ||||||||||||||
| 422 | 23 00 00 | 11 | Closeout Submittals | Indoor Air Quality During Construction | 3.12 | S | ||||||||||||||
| 423 | 23 01 30.41 | 01 | Preconstruction Submittals | Record of Existing Conditions | 3.1.1.1 | G | ||||||||||||||
| 424 | 23 01 30.41 | 01 | Preconstruction Submittals | Coordination Plan | 3.1.1.2 | G | ||||||||||||||
| 425 | 23 01 30.41 | 01 | Preconstruction Submittals | NADCA Firm | 1.4.1 | |||||||||||||||
| 426 | 23 01 30.41 | 01 | Preconstruction Submittals | NADCA Team Assistants | 1.4.1 | |||||||||||||||
| 427 | 23 01 30.41 | 01 | Preconstruction Submittals | NADCA Air System Cleaning Specialist (ASCS) | 1.4.1 | |||||||||||||||
| 428 | 23 01 30.41 | 01 | Preconstruction Submittals | NADCA Supervisor Qualifications | 1.4.1 | G | ||||||||||||||
| 429 | 23 01 30.41 | 01 | Preconstruction Submittals | Records of Experience in the Field of HVAC System Cleaning | 1.4.2 | G | ||||||||||||||
| 430 | 23 01 30.41 | 01 | Preconstruction Submittals | NADCA Work Execution Schedule | 1.5.1 | G | ||||||||||||||
| 431 | 23 01 30.41 | 03 | Product Data | Safety Data Sheets (SDS) | 1.4.3 | |||||||||||||||
| 432 | 23 01 30.41 | 06 | Test Reports | Testing Procedures Summary | 3.3.2 | |||||||||||||||
| 433 | 23 01 30.41 | 06 | Test Reports | Gravimetric Analysis | 3.3.1.3 | |||||||||||||||
| 434 | 23 01 30.41 | 06 | Test Reports | Post-Project Report | 3.3.2 | G | ||||||||||||||
| 435 | 23 05 15 | 01 | Preconstruction Submittals | Material, Equipment, and Fixture Lists | 1.2 | G | ||||||||||||||
| 436 | 23 05 15 | 02 | Shop Drawings | Record Drawings | 1.2 | G | ||||||||||||||
| 437 | 23 05 15 | 02 | Shop Drawings | Connection Diagrams | 1.2 | G | ||||||||||||||
| 438 | 23 05 15 | 02 | Shop Drawings | Coordination Drawings | 1.2 | G | ||||||||||||||
| 439 | 23 05 15 | 02 | Shop Drawings | Fabrication Drawings | 1.2 | G | ||||||||||||||
| 440 | 23 05 15 | 02 | Shop Drawings | Installation Drawings | 3.1 | G | ||||||||||||||
| 441 | 23 05 15 | 03 | Product Data | Pipe and Fittings | 2.1 | G | ||||||||||||||
| 442 | 23 05 15 | 03 | Product Data | Piping Specialties | 2.2 | G | ||||||||||||||
| 443 | 23 05 15 | 03 | Product Data | Valves | 2.3 | G | ||||||||||||||
| 444 | 23 05 15 | 03 | Product Data | Miscellaneous Materials | 2.4 | G | ||||||||||||||
| 445 | 23 05 15 | 03 | Product Data | Supporting Elements | 2.5 | G | ||||||||||||||
| 446 | 23 05 15 | 03 | Product Data | Equipment Foundation Data | 1.2 | G | ||||||||||||||
| 447 | 23 05 15 | 04 | Samples | Manufacturer's Standard Color Charts | 1.2 | G | ||||||||||||||
| 448 | 23 05 15 | 05 | Design Data | Pipe and Fittings | 2.1 | G | ||||||||||||||
| 449 | 23 05 15 | 05 | Design Data | Piping Specialties | 2.2 | G | ||||||||||||||
| 450 | 23 05 15 | 05 | Design Data | Valves | 2.3 | G | ||||||||||||||
| 451 | 23 05 15 | 06 | Test Reports | Hydrostatic Tests | 3.1 | G | ||||||||||||||
| 452 | 23 05 15 | 06 | Test Reports | Air Tests | 3.1 | G | ||||||||||||||
| 453 | 23 05 15 | 06 | Test Reports | Valve-Operating Tests | 3.1 | G | ||||||||||||||
| 454 | 23 05 15 | 06 | Test Reports | Drainage Tests | 3.1 | G | ||||||||||||||
| 455 | 23 05 15 | 06 | Test Reports | Pneumatic Tests | 3.1 | G | ||||||||||||||
| 456 | 23 05 15 | 06 | Test Reports | Non-Destructive Electric Tests | 3.1 | G | ||||||||||||||
| 457 | 23 05 15 | 06 | Test Reports | System Operation Tests | 3.1 | G | ||||||||||||||
| 458 | 23 05 15 | 07 | Certificates | Record of Satisfactory Field Operation | 1.4.2 | G | ||||||||||||||
| 459 | 23 05 15 | 07 | Certificates | List of Qualified Permanent Service Organizations | 1.4.3 | G | ||||||||||||||
| 460 | 23 05 15 | 07 | Certificates | Listing of Product Installations | 1.2 | G | ||||||||||||||
| 461 | 23 05 15 | 07 | Certificates | Records of Existing Conditions | 1.2 | G | ||||||||||||||
| 462 | 23 05 15 | 07 | Certificates | Surface Resistance | 3.1 | G | ||||||||||||||
| 463 | 23 05 15 | 07 | Certificates | Shear and Tensile Strengths | 3.1 | G | ||||||||||||||
| 464 | 23 05 15 | 07 | Certificates | Temperature Ratings | 3.1 | G | ||||||||||||||
| 465 | 23 05 15 | 07 | Certificates | Bending Tests | 3.1 | G | ||||||||||||||
| 466 | 23 05 15 | 07 | Certificates | Flattening Tests | 3.1 | G | ||||||||||||||
| 467 | 23 05 15 | 07 | Certificates | Transverse Guided Weld Bend Tests | 3.1 | G | ||||||||||||||
| 468 | 23 05 15 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.8 | G | ||||||||||||||
| 469 | 23 05 48.00 40 | 02 | Shop Drawings | Installation Drawings | 1.2 | G | ||||||||||||||
| 470 | 23 05 48.00 40 | 02 | Shop Drawings | Outline Drawings | 1.2 | G | ||||||||||||||
| 471 | 23 05 48.00 40 | 03 | Product Data | Equipment and Performance Data | 1.2 | G | ||||||||||||||
| 472 | 23 05 48.00 40 | 03 | Product Data | Isolators | 2.2.3 | G | ||||||||||||||
| 473 | 23 05 48.00 40 | 06 | Test Reports | Type of Isolator | 2.4 | G | ||||||||||||||
| 474 | 23 05 48.00 40 | 06 | Test Reports | Type of Base | 2.4 | G | ||||||||||||||
| 475 | 23 05 48.00 40 | 06 | Test Reports | Allowable Deflection | 2.4 | G | ||||||||||||||
| 476 | 23 05 48.00 40 | 06 | Test Reports | Measured Deflection | 2.4 | G | ||||||||||||||
| 477 | 23 05 93 | 01 | Preconstruction Submittals | Records of Existing Conditions | 1.3.3 | G | ||||||||||||||
| 478 | 23 05 93 | 01 | Preconstruction Submittals | Independent TAB Agency and Personnel Qualifications | 1.5.1 | G | ||||||||||||||
| 479 | 23 05 93 | 01 | Preconstruction Submittals | TAB Design Review Report | 1.5.3.2 | G | ||||||||||||||
| 480 | 23 05 93 | 02 | Shop Drawings | TAB Schematic Drawings and Report Forms | 1.3.3 | G | ||||||||||||||
| 481 | 23 05 93 | 03 | Product Data | Equipment and Performance Data | 1.3 | G | ||||||||||||||
| 482 | 23 05 93 | 03 | Product Data | TAB Related HVAC Submittals | 1.5.1.3 | G | ||||||||||||||
| 483 | 23 05 93 | 06 | Test Reports | Completed Pre-Final DALT Report | 3.3.5 | G | ||||||||||||||
| 484 | 23 05 93 | 06 | Test Reports | Certified Final DALT Report | 3.3.8 | G | ||||||||||||||
| 485 | 23 05 93 | 06 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.3 | G | ||||||||||||||
| 486 | 23 05 93 | 06 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.3 | G | ||||||||||||||
| 487 | 23 05 93 | 06 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.3 | G | ||||||||||||||
| 488 | 23 05 93 | 06 | Test Reports | Proportional Balancing | 3.7 | G | ||||||||||||||
| 489 | 23 05 93 | 06 | Test Reports | Season 1 | 3.7 | G | ||||||||||||||
| 490 | 23 05 93 | 06 | Test Reports | Season 2 | 3.7 | G | ||||||||||||||
| 491 | 23 05 93 | 07 | Certificates | Independent TAB Agency and Personnel Qualifications | 1.5.1 | G | ||||||||||||||
| 492 | 23 05 93 | 07 | Certificates | DALT and TAB Submittal and Work Schedule | 1.5.3.2 | G | ||||||||||||||
| 493 | 23 05 93 | 07 | Certificates | TAB Pre-Field Engineering Report | 1.5.3.3 | G | ||||||||||||||
| 494 | 23 05 93 | 07 | Certificates | Instrument Calibration Certificates | 1.5.5 | G | ||||||||||||||
| 495 | 23 05 93 | 07 | Certificates | DALT and TAB Procedures Summary | 3.7 | G | ||||||||||||||
| 496 | 23 05 93 | 07 | Certificates | Completed Pre-Final DALT Work Checklist | 3.7 | G | ||||||||||||||
| 497 | 23 05 93 | 07 | Certificates | Advance Notice of Pre-Final DALT Field Work | 3.3.2 | G | ||||||||||||||
| 498 | 23 05 93 | 07 | Certificates | Proportional Balancing | 3.7 | G | ||||||||||||||
| 499 | 23 05 93 | 07 | Certificates | Season 1 | 3.7 | G | ||||||||||||||
| 500 | 23 05 93 | 07 | Certificates | Season 2 | 3.7 | G | ||||||||||||||
| 501 | 23 07 00 | 02 | Shop Drawings | MICA Plates | 3.2.2.4 | G | ||||||||||||||
| 502 | 23 07 00 | 02 | Shop Drawings | Pipe Insulation Systems | 2.3 | |||||||||||||||
| 503 | 23 07 00 | 02 | Shop Drawings | Pipe Insulation Systems | 3.2 | |||||||||||||||
| 504 | 23 07 00 | 02 | Shop Drawings | Duct Insulation Systems | 3.3 | |||||||||||||||
| 505 | 23 07 00 | 02 | Shop Drawings | Equipment Insulation Systems | 3.4 | |||||||||||||||
| 506 | 23 07 00 | 02 | Shop Drawings | Recycled content for insulation materials | 2.3.1 | S | ||||||||||||||
| 507 | 23 07 00 | 03 | Product Data | Pipe Insulation Systems | 2.3 | G | ||||||||||||||
| 508 | 23 07 00 | 03 | Product Data | Pipe Insulation Systems | 3.2 | G | ||||||||||||||
| 509 | 23 07 00 | 03 | Product Data | Duct Insulation Systems | 3.3 | G | ||||||||||||||
| 510 | 23 07 00 | 03 | Product Data | Equipment Insulation Systems | 3.4 | G | ||||||||||||||
| 511 | 23 07 00 | 04 | Samples | Thermal Insulation | 2.2.1.2 | G | ||||||||||||||
| 512 | 23 07 00 | 04 | Samples | Display Samples | 3.1.1 | G | ||||||||||||||
| 513 | 23 07 00 | 07 | Certificates | Indoor air quality for adhesives | 2.2.1 | S | ||||||||||||||
| 514 | 23 07 00 | 08 | Manufacturer’s Instructions | Pipe Insulation Systems | 2.3 | G | ||||||||||||||
| 515 | 23 07 00 | 08 | Manufacturer’s Instructions | Pipe Insulation Systems | 3.2 | G | ||||||||||||||
| 516 | 23 07 00 | 08 | Manufacturer’s Instructions | Duct Insulation Systems | 3.3 | G | ||||||||||||||
| 517 | 23 07 00 | 08 | Manufacturer’s Instructions | Equipment Insulation Systems | 3.4 | G | ||||||||||||||
| 518 | 23 09 00 | 02 | Shop Drawings | DDC Contractor Design Drawings | 3.3 | G | ||||||||||||||
| 519 | 23 09 00 | 02 | Shop Drawings | Draft As-Built Drawings | 3.3 | G | ||||||||||||||
| 520 | 23 09 00 | 02 | Shop Drawings | Final As-Built Drawings | 3.3 | G | ||||||||||||||
| 521 | 23 09 00 | 03 | Product Data | Programming Software | 1.8.3 | G | ||||||||||||||
| 522 | 23 09 00 | 03 | Product Data | Controller Application Programs | 1.8.4 | G | ||||||||||||||
| 523 | 23 09 00 | 03 | Product Data | Configuration Software | 1.8.1 | G | ||||||||||||||
| 524 | 23 09 00 | 03 | Product Data | Controller Configuration Settings | 1.8.2 | G | ||||||||||||||
| 525 | 23 09 00 | 03 | Product Data | Manufacturer's Product Data | 2.2 | G | ||||||||||||||
| 526 | 23 09 00 | 03 | Product Data | Niagara Framework Supervisory Gateway Backups | 1.8.5 | G | ||||||||||||||
| 527 | 23 09 00 | 03 | Product Data | Niagara Framework Engineering Tool | 1.8.6 | G | ||||||||||||||
| 528 | 23 09 00 | 03 | Product Data | Niagara Framework Wizards | 0 | G | ||||||||||||||
| 529 | 23 09 00 | 05 | Design Data | Boiler Or Chiller Plant Gateway Request | 1.9 | |||||||||||||||
| 530 | 23 09 00 | 06 | Test Reports | Existing Conditions Report | 3.1.1 | |||||||||||||||
| 531 | 23 09 00 | 06 | Test Reports | Start-Up Testing Report | 3.5.2 | G | ||||||||||||||
| 532 | 23 09 00 | 06 | Test Reports | PVT Procedures | 0 | G | ||||||||||||||
| 533 | 23 09 00 | 06 | Test Reports | PVT Report | 0 | G | ||||||||||||||
| 534 | 23 09 00 | 06 | Test Reports | Pre-Construction Quality Control (QC) Checklist | 1.10.1 | G | ||||||||||||||
| 535 | 23 09 00 | 06 | Test Reports | Post-Construction Quality Control (QC) Checklist | 1.10.2 | G | ||||||||||||||
| 536 | 23 09 00 | 06 | Test Reports | Control Contractor’s Performance Verification Testing Plan | 3.6.5 | G | ||||||||||||||
| 537 | 23 09 00 | 06 | Test Reports | Equipment Supplier’s Performance Verification Testing Plan | 3.6.3.1 | G | ||||||||||||||
| 538 | 23 09 00 | 06 | Test Reports | Endurance Testing Results | 3.6.8.3 | G | ||||||||||||||
| 539 | 23 09 00 | 06 | Test Reports | Performance Verification Test Report | 3.6.9 | G | ||||||||||||||
| 540 | 23 09 00 | 10 | Operation and Maintenance Data | Operation and Maintenance (O&M) Instructions | 3.7 | G | ||||||||||||||
| 541 | 23 09 00 | 10 | Operation and Maintenance Data | Training Documentation | 3.9.1 | G | ||||||||||||||
| 542 | 23 09 00 | 11 | Closeout Submittals | Enclosure Keys | 2.5 | G | ||||||||||||||
| 543 | 23 09 00 | 11 | Closeout Submittals | Password Summary Report | 3.2.6.1 | G | ||||||||||||||
| 544 | 23 09 00 | 11 | Closeout Submittals | Closeout Quality Control (QC) Checklist | 1.10.3 | G | ||||||||||||||
| 545 | 23 23 00 | 02 | Shop Drawings | Refrigerant Piping System | 2.3 | G | ||||||||||||||
| 546 | 23 23 00 | 03 | Product Data | Refrigerant Piping System | 2.3 | |||||||||||||||
| 547 | 23 23 00 | 03 | Product Data | Spare Parts | 1.5.2 | |||||||||||||||
| 548 | 23 23 00 | 03 | Product Data | Qualifications | 1.3.1 | |||||||||||||||
| 549 | 23 23 00 | 03 | Product Data | Refrigerant Piping Tests | 3.5 | |||||||||||||||
| 550 | 23 23 00 | 03 | Product Data | Verification of Dimensions | 3.1 | |||||||||||||||
| 551 | 23 23 00 | 06 | Test Reports | Refrigerant Piping Tests | 3.5 | |||||||||||||||
| 552 | 23 23 00 | 07 | Certificates | Service Organization | 2.1 | |||||||||||||||
| 553 | 23 23 00 | 10 | Operation and Maintenance Data | Maintenance | 1.5 | G | ||||||||||||||
| 554 | 23 23 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.4 | G | ||||||||||||||
| 555 | 23 23 00 | 10 | Operation and Maintenance Data | Demonstrations | 3.4 | G | ||||||||||||||
| 556 | 23 81 00 | 03 | Product Data | Spare Parts | 3.7.1 | |||||||||||||||
| 557 | 23 81 00 | 03 | Product Data | Posted Instructions | 3.4 | |||||||||||||||
| 558 | 23 81 00 | 03 | Product Data | Coil Corrosion Protection | 2.6.1 | |||||||||||||||
| 559 | 23 81 00 | 03 | Product Data | System Performance Tests | 3.6 | |||||||||||||||
| 560 | 23 81 00 | 03 | Product Data | Training | 3.4 | G | ||||||||||||||
| 561 | 23 81 00 | 03 | Product Data | Inventory | 1.5 | |||||||||||||||
| 562 | 23 81 00 | 03 | Product Data | Environmental Data | 2.2.2.5 | |||||||||||||||
| 563 | 23 81 00 | 03 | Product Data | Supplied Products | 2.1 | |||||||||||||||
| 564 | 23 81 00 | 03 | Product Data | Manufacturer's Standard Catalog Data | 2.2 | |||||||||||||||
| 565 | 23 81 00 | 03 | Product Data | Computer Room Humidifier | 0 | |||||||||||||||
| 566 | 23 81 00 | 03 | Product Data | Humidifier | 0 | |||||||||||||||
| 567 | 23 81 00 | 06 | Test Reports | Refrigerant Tests, Charging, and Start-Up | 3.5 | G | ||||||||||||||
| 568 | 23 81 00 | 06 | Test Reports | System Performance Tests | 3.6 | G | ||||||||||||||
| 569 | 23 81 00 | 07 | Certificates | Service Organizations | 3.7.2 | |||||||||||||||
| 570 | 23 81 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.4 | G | ||||||||||||||
| 571 | 23 81 00 | 11 | Closeout Submittals | Ozone Depleting Substances | 2.2.2.3 | |||||||||||||||
| 572 | 25 08 10 | 01 | Preconstruction Submittals | Factory Test | 3.4 | G | ||||||||||||||
| 573 | 25 08 10 | 06 | Test Reports | UMCS and Building Level DDC Testing Sequence | 3.1 | |||||||||||||||
| 574 | 25 08 10 | 06 | Test Reports | Performance Verification Test | 3.6 | G | ||||||||||||||
| 575 | 25 08 10 | 06 | Test Reports | Endurance Testing | 3.7 | |||||||||||||||
| 576 | 25 10 10 | 02 | Shop Drawings | UMCS Contractor Design Drawings | 3.3.2 | |||||||||||||||
| 577 | 25 10 10 | 02 | Shop Drawings | Draft As-Built Drawings | 3.3.3 | |||||||||||||||
| 578 | 25 10 10 | 02 | Shop Drawings | Final As-Built Drawings | 3.3.3 | |||||||||||||||
| 579 | 25 10 10 | 03 | Product Data | Product Data Sheets | 2.1.5 | |||||||||||||||
| 580 | 25 10 10 | 03 | Product Data | Computer Software | 2.4 | |||||||||||||||
| 581 | 25 10 10 | 03 | Product Data | Enclosure Keys | 2.5.1 | |||||||||||||||
| 582 | 25 10 10 | 05 | Design Data | UMCS IP Network Bandwidth Usage Estimate | 3.3.1 | |||||||||||||||
| 583 | 25 10 10 | 06 | Test Reports | Pre-Construction QC Checklist | 1.6 | |||||||||||||||
| 584 | 25 10 10 | 06 | Test Reports | Post-Construction QC Checklist | 1.6 | |||||||||||||||
| 585 | 25 10 10 | 06 | Test Reports | Factory Test Procedures | 3.1 | |||||||||||||||
| 586 | 25 10 10 | 06 | Test Reports | Factory Test Report | 3.1 | |||||||||||||||
| 587 | 25 10 10 | 06 | Test Reports | Existing Conditions Report | 3.2 | |||||||||||||||
| 588 | 25 10 10 | 06 | Test Reports | Start-Up and Start-Up Testing Report | 3.7 | G | ||||||||||||||
| 589 | 25 10 10 | 06 | Test Reports | PVT Phase I Procedures | 3.8.1 | |||||||||||||||
| 590 | 25 10 10 | 06 | Test Reports | PVT Phase I Report | 3.8.2 | G | ||||||||||||||
| 591 | 25 10 10 | 06 | Test Reports | PVT Phase II Report | 3.8.3 | G | ||||||||||||||
| 592 | 25 10 10 | 10 | Operation and Maintenance Data | Operation and Maintenance (O&M) Instructions | 1.7 | |||||||||||||||
| 593 | 25 10 10 | 10 | Operation and Maintenance Data | Preventive Maintenance Work Plan | 3.9.8.1 | |||||||||||||||
| 594 | 25 10 10 | 10 | Operation and Maintenance Data | Basic Training Documentation | 3.10.1 | |||||||||||||||
| 595 | 25 10 10 | 10 | Operation and Maintenance Data | Advanced Training Documentation | 3.10.1 | |||||||||||||||
| 596 | 25 10 10 | 10 | Operation and Maintenance Data | Refresher Training Documentation | 3.10.1 | |||||||||||||||
| 597 | 25 10 10 | 11 | Closeout Submittals | Closeout QC Checklist | 1.6 | |||||||||||||||
| 598 | 26 05 00.00 40 | 01 | Preconstruction Submittals | Material, Equipment, and Fixture Lists | 2.1 | |||||||||||||||
| 599 | 26 05 00.00 40 | 03 | Product Data | Conduits and Raceways | 2.1.1 | G | ||||||||||||||
| 600 | 26 05 00.00 40 | 03 | Product Data | Wire and Cable | 2.1.3 | G | ||||||||||||||
| 601 | 26 05 00.00 40 | 03 | Product Data | Splices and Connectors | 3.2.1.9 | G | ||||||||||||||
| 602 | 26 05 00.00 40 | 03 | Product Data | Switches | 2.1.4 | G | ||||||||||||||
| 603 | 26 05 00.00 40 | 03 | Product Data | Receptacles | 2.1.5 | G | ||||||||||||||
| 604 | 26 05 00.00 40 | 03 | Product Data | Outlet Boxes, Pull Boxes and Junction Boxes | 2.1.6 | G | ||||||||||||||
| 605 | 26 05 00.00 40 | 03 | Product Data | Circuit Breakers | 2.1.8 | G | ||||||||||||||
| 606 | 26 05 00.00 40 | 03 | Product Data | Panelboards | 2.1.7 | G | ||||||||||||||
| 607 | 26 05 00.00 40 | 03 | Product Data | Lamps and Lighting Fixtures | 2.1.9 | G | ||||||||||||||
| 608 | 26 05 00.00 40 | 03 | Product Data | Dry-Type Distribution Transformers | 2.1.12 | G | ||||||||||||||
| 609 | 26 05 00.00 40 | 06 | Test Reports | Continuity Test | 3.3 | G | ||||||||||||||
| 610 | 26 05 00.00 40 | 06 | Test Reports | Phase-Rotation Tests | 3.3 | G | ||||||||||||||
| 611 | 26 05 00.00 40 | 06 | Test Reports | Insulation Resistance Test | 3.3 | G | ||||||||||||||
| 612 | 26 05 00.00 40 | 08 | Manufacturer’s Instructions | Manufacturer's Instructions | 3.1 | |||||||||||||||
| 613 | 26 05 71.00 40 | 02 | Shop Drawings | Connection Diagrams | 2.1 | G | ||||||||||||||
| 614 | 26 05 71.00 40 | 02 | Shop Drawings | Fabrication Drawings | 2.1 | G | ||||||||||||||
| 615 | 26 05 71.00 40 | 02 | Shop Drawings | Control Devices | 3.1 | G | ||||||||||||||
| 616 | 26 05 71.00 40 | 02 | Shop Drawings | Protective Devices | 3.1 | G | ||||||||||||||
| 617 | 26 05 71.00 40 | 03 | Product Data | Fuses | 2.2.3 | G | ||||||||||||||
| 618 | 26 05 71.00 40 | 03 | Product Data | Motor Controllers | 2.2.1 | G | ||||||||||||||
| 619 | 26 05 71.00 40 | 03 | Product Data | Instrument Transformers | 2.3.1 | G |