Attachment_2_-_Specifications_VRCG_Septic_System_FINAL.pdf

PDF 519 KB Posted

Attached to
VIRGIN RIVER CAMPGROUND SEPTIC SYSTEM REPLACEMENT Federal contract opportunity
Solicitation number
140L0624R0007
Issued by
Department of the Interior Bureau of Land Management National Office

About this file

This document is the technical specifications for the Virgin River Campground Septic System Replacement project for the Bureau of Land Management Arizona Strip Field Office. The project involves replacing three existing concrete septic tanks and associated wastewater leach fields and piping for three campground restrooms. Key requirements include excavating and disposing of the existing tanks; installing new precast concrete or fiberglass septic tanks; installing new perforated and solid PVC piping between the buildings and distribution boxes; installing new gravel trenches, filter fabric, and diversion valves for the new leach fields; and testing the completed system. The specifications provide construction and material requirements for the site work, earthwork, utilities, tanks and cleanouts to ensure code and regulatory compliance.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF LAND MANAGEMENT

VIRGIN RIVER CAMPGROUND

SEPTIC SYSTEM REPLACEMENT

US BLM – ARIZONA STRIP FIELD OFFICE

345 E RIVERSIDE DR

ST. GEORGE, UT 84790

TECHNICAL SPECIFICATIONS

Vol. 1 OF 1

GLHN JOB No.20049.20

JANUARY 13, 2023

GLHN Architects & Engineers, Inc. | 2939 E Broadway Blvd, Tucson, AZ 85716 T 520.881.4546 | F 520.795.1822 | GLHN.com

Bureau of Land Management Virgin River Campground

TOC - 1

GLHN #20049.20

Table of Contents

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

011000 Summary of Work 011500 Measurement and Payment 012000 Project Meetings 013200 Construction Progress Documentation 013233 Photographic Documentation 013300 Submittal Procedures 014000 Quality Control/Quality Assurance 017000 Contract Closeout 017419 Construction Waste Management and Disposal 017839 Project Record Documents

DIVISION 02 – EXISTING CONDITIONS

024119 Selective Demolition

DIVISION 31 – EARTHWORK

311000 Site Clearing 312000 Earth Moving 315000 Excavation Support and Protection

DIVISION 33 – UTILITIES

333113 Sanitary Sewer Systems

APPENDICES

Appendix A – Bid Schedule

Appendix B – Submittal Schedule

011000 - 1

GLHN #20049.20

Summary of Work

SECTION 011000 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Access to site.

4. Protection of existing structures.

5. Field check of existing structures.

6. Site Access.

7. Field office and sheds.

1.3 PROJECT INFORMATION

A. Owner: Bureau of Land Management – Virgin River Campground, Septic System Replacement Project.

1. Project Location: Southwest of Interstate 15, 20 miles from St. George, Utah, Cedar Pocket

Road, Exit 18, Mohave County, Arizona.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of the Project is defined by the Contract Documents and consists of the following:

1. Pump dry and excavate for disposal three existing concrete septic tanks for three restrooms; work to be done in sequence to maintain open restrooms onsite.

2. Excavated tanks may be broken up and stockpiled onsite until removed. Contractor shall prevent wastewater contamination of ground with the use of tarp or approved barrier.

Solid waste to be hauled to the St. George UT landfill, follow all landfill procedures and regulations.

3. New 2,500 gallon concrete septic tank for each Restroom in the same location of former tanks.

4. New wastewater leachate fields with gravel trenches, filter fabric and diversion valves to existing fields at each restroom to accommodate demand.

5. New 4” Solid PVC piping from building connection to distribution boxes.

6. New 4” Perforated PVC piping for disposing wastewater, set level.

7. Associated piping, valves and fittings as required.

011000 - 2

GLHN #20049.20

1.5 ACCESS TO SITE

A. Contractor shall have limited use of Project site for construction operations.

B. Confine operations to the site of the proposed Work or within the areas approved by the CO.

Construction camps and staging areas outside the construction area must be approved by the Contracting Officer (CO). Obtain advance approval from the CO of all staging areas, material stockpile and waste areas and camp areas.

C. It shall be understood the responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the CONTRACTOR and that no claim shall be made against the GOVERNMENT by reason of any act of an employee or trespasser whether GOVERNMENT has paid CONTRACTOR for equipment or materials in storage or not. It shall be further understood should any occasion arise necessitating access by the GOVERNMENT to the sites occupied by these stored materials and equipment, the CONTRACTOR owning or responsible for the stored materials or equipment shall immediately provide same. No materials or equipment may be placed upon the property of the GOVERNMENT until the CO has agreed to the location proposed by the CONTRACTOR to be used for storage. CONTRACTOR is solely responsible for obtaining and shall pay all costs in connection with any additional work area, storage sites, access to the site, or temporary right-of-way, which may be required for proper completion of the Work.

D. Confine operations to normal government business days and hours, exclusive of Federal holidays, unless provided written permission from the GOVERNMENT to work on the site outside of those days and hours.

1.6 PROTECTION OF EXISTING STRUCTURES

A. Where excavation will be required adjacent to existing structures, the CONTRACTOR is solely responsible to maintain the structural integrity of the existing structures. Take whatever means necessary to ensure the existing structures are not damaged. Repair all damage to the existing structures at CONTRACTOR's expense. Repair any fences, posts or signs damaged during construction to the satisfaction of the owner. Unless otherwise noted on the Construction Drawings, restore all existing drainageways disturbed by construction to their original size, line, and grade.

B. The paved road, signage and culverts shall also be protected during construction. Immediately sweep away any spilled soil, rock or gravel material. Restore or repair to original condition roads, culverts, cattle guards and fences or any other structures damaged by the CONTRACTOR’s activities and access to the sites at no additional cost to the project.

1.7 FIELD CHECK OF EXISTING STRUCTURES

A. Dimensions and elevations of existing structures and locations of existing fences, pipelines, and vegetation shown on the drawings were taken from available records and are not guaranteed for accuracy. No survey data is available for this project. Check all dimensions and elevations of existing structures or other existing items, both above and below ground, affected by or affecting the Work under this contract, prior to the start of construction or ordering materials and equipment affected thereby.

011000 - 3

GLHN #20049.20

1.8 SITE ACCESS

A. Determine the adequacy of all roads, culverts, cattle guards, and bridges used in moving or gaining access for equipment and materials to the construction site. Provide alternative methods of access, such as a temporary crossing for any equipment that exceeds the structural limits of existing facilities. Improvements for road access including fill, culverts, and fencing to remain after project completion as approved by CO.

1.9 FIELD OFFICES AND SHEDS

A. Provide field office and storage areas or sheds as required for completion of the work. Locate these temporary structures in areas approved by the CO. All expenses for telephone, utilities, security and waste disposal are the responsibility of the CONTRACTOR. Provide the name and phone number of a representative who may be contacted after hours in case of emergency.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011010

011500 - 1

GLHN #20049.20

Measurement and Payment

SECTION 011500 – MEASUREMENT AND PAYMENT

B. The appended SUBMITTALS SCHEDULE for this project applies to this Section.

C. The appended BID SCHEDULE for this project applies to this Section.

D. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance

1.2 SCOPE

A. The method of measurement and basis of payment is described in this section.

1.3 GENERAL

A. Bid price for each item of the Contract covers all Work shown on the Drawings and required by the specifications and other Contract Documents.

B. All costs are included in the unit and lump-sum prices bid including all materials, equipment, supplies and appurtenances; all construction plant, equipment, and tools; and all labor and supervision necessary to fully complete the Work.

C. No item that is required by the Contract Documents, for the proper and successful completion of the Work, will be paid for outside of or in addition to the prices submitted in the Bid.

D. All work not specifically set forth as a pay item in the Bid Form is considered an incidental obligation of the CONTRACTOR, and all costs in connection therewith shall be included in the unit prices bid.

1.4 ESTIMATED QUANTITIES

A. All quantities in the Pricing Worksheet or other contract documents are approximate only. The contractor is responsible for determining quantities required for the execution of the project.

B. Actual work performed, and materials furnished under the unit-price items for those items to be field measured may differ from the estimated quantities.

C. Pricing shall be inclusive of testing.

011500 - 2

GLHN #20049.20

Measurement and Payment

1.5 SCHEDULE OF VALUES

A. A schedule of values or “allocation of contract price” is required for all lump sum items.

B. The schedule of values is used only to help assess the intermediate value of work completed for the purpose of making progress payments. The schedule of values is not considered as a commitment to prices in the event of later negotiations.

1.6 MEASUREMENT AND PAYMENT ITEMS

A. Items #1 and #12 – Mobilization & Preparatory Work

1. Consists of preparatory work and operations performed by the CONTRACTOR, including but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of offices and other facilities necessary for all work on the project; for premium on bonds and insurance for the Contract; and for other work and operations that must be performed or costs incurred before beginning work on the various items on the project site.

2. Mobilization costs for subcontracted work are also considered included.

3. Demolition and disposal of all existing structures designated for removal in the Contract

Documents but not specifically included in other payment items are included in this payment item.

4. Measurement and payment for mobilization and preparatory work will be made at the Contract lump sum price. Progress payments for mobilization and preparatory work will be as follows:

a. When 5 percent of the total original Contract amount is earned from other Contract items, 50 percent of the amount bid for mobilization will be included in the progress payment estimate.

b. When 40 percent of the total original Contract amount is earned from other schedule items, the balance of the amount bid for mobilization and preparatory work will be included in the progress payment estimate.

B. Item #11 – Schedule.

END OF SECTION 011060

012000 - 1

GLHN #20049.20

Project Meetings

SECTION 012000 – PROJECT MEETINGS

1.2 PRE-CONSTRUCTION MEETING

A. A virtual (online) pre-construction conference will be held prior to the start of work. CONTRACTOR will be notified in advance of meeting time, date and platform. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

B. The CONTRACTOR, subcontractors and the persons responsible for coordination of the work are required to be present at the meeting.

C. The CONTRACTOR is required to be prepared to summarize and explain procedures planned for the project and to present the pre-construction submittals required.

END OF SECTION 012000

013200 - 1

GLHN #20049.20

Construction Progress Documentation

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

Conditions and other Division 01 Specification Sections, apply to this Section.

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Startup construction schedule.

2. Contractor's Construction Schedule.

3. Construction schedule updating reports.

4. Daily construction reports.

5. Material location reports.

6. Site condition reports.

7. Unusual event reports.

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.

1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled.

The sum of costs for all activities must equal the total Contract Sum.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Event: The starting or ending point of an activity.

F. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either Government or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

013200 - 2

GLHN #20049.20

1. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

2. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

G. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.

1.4 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

1. Working electronic copy of schedule file, where indicated.

2. PDF file.

3. 3 paper copies of sufficient size to display entire period or schedule, as required.

B. Startup construction schedule.

1. Submittal of cost-loaded, startup construction schedule will not constitute approval of schedule of values for cost-loaded activities.

C. Startup Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities.

D. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

1. Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals.

E. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of preceding and succeeding activities for each activity, sorted in ascending order by activity number and then by early start date, or actual start date if known.

3. Total Float Report: List of activities sorted in ascending order of total float.

4. Earnings Report: Compilation of Contractor's total earnings from commencement of the

Work until most recent Application for Payment.

F. Construction Schedule Updating Reports: Submit with Applications for Payment.

G. Daily Construction Reports: Submit at weekly intervals.

H. Material location Reports: Submit at weekly intervals.

I. Site Condition Reports: Submit at time of discovery of differing conditions.

J. Unusual Event Reports: Submit at time of unusual event.

K. Qualification Data: For scheduling consultant.

013200 - 3

GLHN #20049.20

1.5 QUALITY ASSURANCE

A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Government's request.

1.6 COORDINATION

A. Coordinate Contractor's Construction Schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.

1. Use Microsoft Project, Scheduling component of Project website software for current

Windows operating system.

B. Scheduling Consultant: Engage a consultant to provide planning, evaluation, and reporting using CPM scheduling.

1. In-House Option: Government may waive requirement to retain a consultant if Contractor employs skilled personnel with experience in CPM scheduling and reporting techniques.

Submit qualifications.

2. Meetings: Scheduling consultant shall attend all meetings related to Project progress, alleged delays, and time impact.

C. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

END OF SECTION 013200

013233 - 1

GLHN #20049.20

Photographic Documentation

SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION

PART 1 – GENERAL

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

A. Section includes administrative and procedural requirements for the following:

1. Preconstruction photographs.

2. Periodic construction photographs.

3. Final completion construction photographs.

4. Preconstruction video recordings.

5. Periodic construction video recordings.

6. Construction webcam.

1.3 INFORMATIONAL SUBMITTALS

A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Include same information as corresponding photographic documentation.

B. Digital Photographs: Submit image files within 3 calendar days of taking photographs.

1. Submit photos electronically via MS Teams site or email (email must not exceed 20MB).

Include copy of key plan indicating each photograph's location and direction.

2. Identification: Provide the following information with each image description in file metadata tag:

a. Name of Project.

b. Name and contact information for photographer.

c. Name of Government.

d. Name of Contractor.

e. Date photograph was taken.

f. Description of location, vantage point, and direction.

g. Unique sequential identifier keyed to accompanying key plan.

C. Video Recordings: Submit video recordings within 7 calendar days of recording.

1. Submit video recordings electronically via MS Teams site or email (email must not exceed

20MB). Include copy of key plan indicating each video's location and direction.

2. Identification: With each submittal, provide the following information in file metadata tag:

a. Name of Project.

b. Name and address of photographer.

c. Name of Government.

d. Name of Contractor.

e. Date video recording was recorded.

f. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

013233 - 2

GLHN #20049.20

Photographic Documentation

1.4 FORMATS AND MEDIA

A. Digital Photographs: Provide color images in JPG format, produced by a digital camera with minimum sensor size of twelve (12) megapixels, and at an image resolution of not less than 3200 by 2400 pixels, and with vibration-reduction technology. Use flash in low light levels or backlit conditions.

B. Digital Video Recordings: Provide high-resolution, digital video in MPEG format, produced by a digital camera with minimum sensor resolution of 12 megapixels and capable of recording in full high-definition model with vibration-reduction technology. Provide supplemental lighting in low light levels or backlit conditions.

C. Digital Images: Submit digital media as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.

D. Metadata: Record accurate date and time and GPS location data from camera.

E. File Names: Name media files with date and Project area and sequential numbering suffix.

1.5 CONSTRUCTION PHOTOGRAPHS

A. Photographer: Engage a qualified photographer to take construction photographs.

B. General: Take photographs with maximum depth of field and in focus.

1. Maintain key plan with each set of construction photographs that identifies each photographic location.

C. Preconstruction Photographs: Before starting construction, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Government.

1. Flag construction limits before taking construction photographs.

2. Take 20 photographs to show existing conditions adjacent to property before starting the

Work.

3. Take 20 photographs of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.

4. Take additional photographs as required to record settlement or cracking of adjacent structures, pavements, and improvements.

D. Periodic Construction Photographs: Take 20 photographs weekly coinciding with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last photographs were taken.

E. Final Completion Construction Photographs: Take 20 photographs after date of Substantial

Completion for submission as Project Record Documents. Government will inform photographer of desired vantage points.

END OF SECTION 013233

013300 - 1

GLHN #20049.20

Submittal Procedures

SECTION 013300 - SUBMITTAL PROCEDURES

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

B. Related Requirements:

1. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.

2. Section 013233 "Photographic Documentation" for submitting preconstruction photographs, periodic construction photographs, and final completion construction photographs.

3. Section 014000 "Quality Assurance" for submitting test and inspection reports, and schedule of tests and inspections.

4. Section 017000 "Contract Closeout" for submitting closeout submittals and maintenance material submittals.

5. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

A. Action Submittals: Written and graphic information and physical samples that require Government’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Government’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

013300 - 2

GLHN #20049.20

1.4 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Government and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and

Contractor's construction schedule.

2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 calendar days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal Category: Action; informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Government’s final release or approval.

g. Scheduled dates for purchasing.

h. Scheduled date of fabrication.

i. Scheduled dates for installation.

j. Activity or event number.

1.5 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Government.

4. Name of Contractor.

5. Name of firm or entity that prepared submittal.

6. Names of subcontractor, manufacturer, and supplier.

7. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier, and alphanumeric suffix for resubmittals.

8. Category and type of submittal.

9. Submittal purpose and description.

10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

11. Drawing number and detail references, as appropriate.

12. Indication of full or partial submittal.

13. Location(s) where product is to be installed, as appropriate.

013300 - 3

GLHN #20049.20

Submittal Procedures

14. Other necessary identification.

15. Remarks.

16. Signature of transmitter.

B. Options: Identify options requiring selection by Government.

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Government on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

E. Submittals for Web-Based Project Software: Prepare submittals as PDF files, or other format indicated by Project software website.

1.6 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package and transmit to Government. By sending via email. Include PDF transmittal form. Include information in email subject line as requested by Government.

a. Government will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification

Section as separate packages under separate transmittals.

4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Government reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

013300 - 4

GLHN #20049.20

Submittal Procedures

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Government’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Government will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.

4. Sequential Review: Where sequential review of submittals by Government’s consultants, Government, or other parties is indicated, allow 21 calendar days for initial review of each submittal.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Government’s action stamp.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Government’s action stamp.

1.7 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams that show factory-installed wiring.

013300 - 5

GLHN #20049.20

Submittal Procedures

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying Shop

Drawings.

5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional government if specified.

2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop

Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 11 by 17 inches.

a. Two opaque (bond) copies of each submittal. Government will return one copy.

b. Three opaque copies of each submittal. Government will retain two copies;

remainder will be returned.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:

a. Project name and submittal number.

b. Generic description of Sample.

c. Product name and name of manufacturer.

d. Sample source.

e. Number and title of applicable Specification Section.

f. Specification paragraph number and generic name of each item.

3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.

4. Web-Based Project Software: Prepare submittals in PDF form, and upload to web- based

Project software website. Enter required data in web-based software site to fully identify submittal.

5. Paper Transmittal: Include paper transmittal including complete submittal information indicated.

6. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

013300 - 6

GLHN #20049.20

Submittal Procedures

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Government's property, are the property of Contractor.

7. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Government will return submittal with options selected.

8. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract

Documents or assigned by Contractor if none is indicated.

2. Manufacturer and product name, and model number if applicable.

3. Number and name of room or space.

4. Location within room or space.

E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of governments, and other information specified.

F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.

G. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

Provide a notarized signature where indicated.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

013300 - 7

GLHN #20049.20

Submittal Procedures

6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

H. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

a. Name of evaluation organization.

b. Date of evaluation.

c. Time period when report is in effect.

d. Product and manufacturers' names.

e. Description of product.

f. Test procedures and results.

g. Limitations of use.

1.8 DELEGATED-DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Government.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file and three paper copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the

Contract Documents. Include list of codes, loads, and other factors used in performing these services.

013300 - 8

GLHN #20049.20

1.9 CONTRACTOR'S REVIEW

A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.

Note corrections and field dimensions. Mark with approval stamp before submitting to Government.

B. Contractor's Approval: Indicate Contractor's approval for each submittal. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

1. Government will not review submittals received from Contractor that do not have

Contractor's review and approval.

1.10 GOVERNMENT’S REVIEW

A. Action Submittals: Government will review each submittal, indicate corrections or revisions required, and return it.

1. PDF Submittals: Government will indicate, via markup on each submittal, the appropriate action.

2. Paper Submittals: Government will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.

B. Informational Submittals: Government will review each submittal and will not return it or will return it if it does not comply with requirements. Government will forward each submittal to appropriate party.

C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Government.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Government will return without review submittals received from sources other than Contractor.

F. Submittals not required by the Contract Documents will be returned by Government without action.

END OF SECTION 013300

014000 - 9

GLHN #20049.20

Quality Assurance

SECTION 014000 – QUALITY CONTROL/QUALITY ASSURANCE

1.1 DEFINITIONS

A. Quality Control - planned and specific actions or operations necessary to produce a product that complies with the contract documents. Quality control consists of actions, inspections, sampling and testing necessary to ensure the work is in compliance with the contract documents and to control production and construction processes. Quality control is keyed to the construction sequence to quickly determine when the work is out of compliance with the contract documents and to respond to correct the situation and bring the work into compliance.

Quality control is the responsibility of the CONTRACTOR.

B. Quality Assurance – planned and systematic observations, testing and actions to verify the work complies with the contract documents. Quality assurance includes oversight of the CONTRACTOR’s quality control, verifying the results of the CONTRACTOR’s testing and additional assurance sampling and testing. The Government will provide quality assurance at a level determined necessary by the Contracting Officer.

C. Verification/Compliance Testing – sampling and testing which is carried out independent of the

CONTRACTOR’s quality control testing to confirm/verify the work complies with the contract documents. The frequency of verification/compliance testing will be determined by the Contracting Officer. Verification/compliance testing will not be used to determine construction procedures or operations (i.e. rolling patterns, lift thickness, etc.). Verification/compliance testing will be provided by the Contracting Officer.

1.2 SUBMITTALS

A. Conduct testing and prepare submittals according to the SUBMITTALS SCHEDULE.

B. Submit records of all CONTRACTOR tests to the Contracting Officer within 24 hours of the testing.

The Quality Control laboratory is to notify the CONTRACTOR and Contracting Officer promptly of irregularities or deficiencies observed in the Work during performance of the Quality Control Testing.

PART 3 - EXECUTION

A. Assure the GOVERNMENT and Contracting Officer have access to all work areas at all times work is in progress. Provide any special facilities or equipment to access work areas at CONTRACTOR expense.

B. Notify the Contracting Officer when the work is ready for quality assurance/quality control testing. Establish and update the construction schedule to provide the Contracting Officer estimated sampling/testing dates and times. Contracting Officer may choose to obtain a split and comparison test of any samples collected for quality control testing. Provide adequate notice of testing plans to coordinate collection of samples.

END OF SECTION 014000

017000 - 1

GLHN #20049.20

Contract Closeout

SECTION 017000 – CONTRACT CLOSEOUT

1.1 DESCRIPTION

A. The work covered under this section includes items required in final closeout of this Project.

Included are items such as post-construction inspection, acceptance of the work, closeout records and Project record drawings.

1.2 SUBMITTALS

A. Provide closeout submittals for approval prior to final payment. Items to be submitted are:

1. Project Record Documents - See Item 3.B.1 for requirements.

A. Cleaning:

1. Remove all tools, equipment, surplus materials, and rubbish. Repair all marred surfaces, and remove grease, dirt, stains and foreign materials from finished surfaces.

B. Project Record Drawings/Documents:

1. Using red colored ink, CONTRACTOR shall mark changes on a set of clean prints. Indicate all changes and revisions to the original design that affect the permanent structures and that exist in the completed work. Reference all underground facilities to permanent physical objects. Reference elevation of all existing lines on profile sheets or call out elevations in plan if no profile exists. Keep record drawings current during construction activities. Certification of accuracy and completeness is required on monthly payment requisitions.

C. Post-Construction Inspection:

1. Prior to expiration of the one-year correction period, the GOVERNMENT will inspect the

Project to determine whether corrective work is required. The CONTRACTOR will be advised 14 days prior to inspection and notified in writing of all deficiencies. CONTRACTOR shall attend the post- construction inspection.

END OF SECTION 017000

017419 - 1

GLHN #20049.20

Construction Waste Management and Disposal

SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for the following:

1. Salvaging nonhazardous demolition and constructionwaste.

2. Recycling nonhazardous demolition and construction waste.

3. Disposing of nonhazardous demolition and construction waste.

1.2 DEFINITIONS

A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.

B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.

C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Government’s property.

D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.

E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.

PART 2 - PRODUCTS Not Used

3.1 DISPOSAL OF WASTE

A. General: All demolition and construction becomes the property of the Contractor. Remove waste materials from Project site and legally dispose of them at a recycling facility, in a landfill or incinerator acceptable to authorities having jurisdiction.

1. Existing concrete septic tanks to be removed shall be emptied completely and rinsed prior to demolition/ removal. Liquid waste shall be hauled offsite and disposed of legally.

017419 - 2

GLHN #20049.20

Construction Waste Management and Disposal

2. Solid Materials that have come into contact with human waste; i.e., septic tanks, sewage piping, fittings, contaminated rock, soil or gravel, shall be hauled to the St. George UT landfill for disposal. Follow landfill procedures precisely.

• Contractor shall create a free account at www.republicservices.com/

3. Materials may be stockpiled onsite until a full load is ready but must be placed on a surface to prevent contamination of the soil, covered, and protected from contact with visitors by fencing or other approved barrier.

4. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.

5. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn waste materials.

END OF SECTION 017419

http://www.republicservices.com/

017839 - 1

GLHN #20049.20

Project Record Documents

SECTION 017839 - PROJECT RECORD DOCUMENTS

1.2

SUMMARY

A. Section includes administrative and procedural requirements for project record documents, including the following:

1. Record Drawings.

2. Record Specifications.

3. Record Product Data.

4. Miscellaneous record submittals.

B. Related Requirements

1. Section 017700 "Closeout Procedures" for general closeout procedures.

1.3

CLOSEOUT SUBMITTALS

A. Record Drawings: Comply with the following:

1. Number of Copies: Submit one set of marked-up record prints.

2. Number of Copies: Submit copies of record Drawings as follows:

a. Initial Submittal:

1) Submit one paper-copy set of marked-up record prints.

2) Submit PDF electronic files of scanned record prints and one of file prints.

3) Submit record digital data files and one set of plots.

4) Government will indicate whether general scope of changes, additional information recorded, and quality of drafting are acceptable.

b. Final Submittal:

1) Submit three paper-copy sets of marked-up record prints.

2) Submit PDF electronic files of scanned record prints and three sets of prints.