Attachment 2 - Contract Progress Schedule (AF 3064) - DRAFT.xls
XLS spreadsheet 119 KB Posted
- Attached to
- Joint Base San Antonio Multiple Award Construction Contract (MACC) IDIQ Federal contract opportunity
- Solicitation number
- Not on record
About this file
This document contains a draft solicitation for a Joint Base San Antonio Multiple Award Construction Contract (MACC) Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The solicitation seeks industry feedback on the draft by 6 May 2021 for renovations and construction services at Joint Base San Antonio locations. The Air Force is the contracting agency seeking small business set-aside MACC IDIQ contracts for a one base year and four option years. The draft solicitation specifies an email response deadline for industry comments to the Contracting Officer and Contract Specialist provided. No proposals shall be submitted in response to the draft solicitation.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROGRESS SCHEDULE
| CONTRACT PROGRESS SCHEDULE | Form Approved | ||||||||||||||||||||
| (See Contractor's Instructions on Reverse) | OMB NO. 0704-0188 | ||||||||||||||||||||
| Public reporting burden for this collection of information is estimated to average 15 minutes per response. Including the time for reviewing instructions, searching existing data sources, gathering maintaining the data needed, and completing and reviewing | |||||||||||||||||||||
| the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department Defense of Washington Headquarters Services, Directorate for | |||||||||||||||||||||
| information, Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project 0704-0188. Washington DC 20503. Please DO NOT RETURN your | |||||||||||||||||||||
| (form questionnaire) to either of these addresses. Send your completed (form questionnaire) to: SAF AQCO. Washington DC 20330-1000. | |||||||||||||||||||||
| 1. CONTRACT NO. | 8. PROJECT TITLE | 10. APPROVAL RECOMMENDED BY: | |||||||||||||||||||
| DATE SIGNED | INSTALLATIONS ENGINEER'S SIGNATURE | ||||||||||||||||||||
| 2. STARTING DATE | 2 December 2015 | ||||||||||||||||||||
| 3. COMPLETION DATE | 19 July 2016 | 9. SUBMITTED BY: | |||||||||||||||||||
| 4. PURCHASE REQUEST NO. | DATE SIGNED | CONTRACTOR'S NAME & ADDRESS | CONTRACTOR'S SIGNATURE | 11. APPROVED BY: | |||||||||||||||||
| 5. PROJECT NO. | FA3047-16-C-0007 | DATE SIGNED | CONTRACTING OFFICER'S SIGNATURE | ||||||||||||||||||
| 6. ACTUAL STARTING DATE | |||||||||||||||||||||
| 7. ACTUAL COMPLETION DATE | |||||||||||||||||||||
| Line No. | Work Element | % | 1/15/22 | 1/30/22 | 2/15/22 | 2/28/22 | 3/15/22 | 3/31/22 | 4/15/22 | 4/30/22 | 5/15/22 | 5/31/22 | 6/15/22 | 6/30/22 | 7/15/22 | 7/31/22 | 8/15/22 | 8/31/22 | Actual | Scheduled | |
| 0.00% | |||||||||||||||||||||
| 1 | Final Inspection and Closeout | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 2 | Design | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 3 | PROGRESS CLEANING | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 4 | DUMPSTERS | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 5 | FINAL CLEANUP | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 6 | DEMOLITION AND DUST PARTITION | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 7 | CONCRETE | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 8 | WOOD FRAMING - BLOCKING WALLS | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 9 | MILLWORK/CASEWORK | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 10 | INSULATION | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 11 | SEALANTS - FIRE AND ACOUSTIC | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 12 | DOORS, FRAMES, & ACCESS CONTROL | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 13 | PASS THROUGH WINDOW , 36" X 36" | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 14 | METAL STUD WALL FRAMING | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 15 | DRYWALL | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 16 | ACOUSTICAL AND SHEETROCK CEILINGS | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 17 | PORCELAIN TILE REPAIRS | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 18 | FLOORING | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 19 | PAINTING | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 20 | RESTROOM SPECIALTIES | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 21 | FIRE EXTINGUISHER & SIGN SPECIALTIES | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 22 | AUDITORIUM SEATING | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 23 | FIRE SUPPRESSION SPRINKLER SYSTEM | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 24 | PLUMBING | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 25 | HVAC | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 26 | COMMISSIONING | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 27 | ELECTRICAL | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 28 | FIRE ALARM | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 29 | DATA/COMMUNICATIONS | 0.00% | |||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| 0.00% | |||||||||||||||||||||
| PERCENTAGE OF COMPLETION (CUMULATIVE) | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |||||
| SCHEDULED COMPLETION | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | ||||
| ACTUAL COMPLETION | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | ||||
| ACTUAL COMPLETION (CUMULATIVE) | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |||||
| FORM NO. AF 3064 |
Page &P of &N
ENTER HERE FOR GRAPH
| Tejas Premier | |||
| Actual | Scheduled | ||
| Jan | 0.00% | 0.00% | USE LINE PERCENTAGE OF COMPLETION (CUMULATIVE) |
| Feb | 0.00% | 0.00% | |
| Mar | 0.00% | 0.00% | |
| Apr | 0.00% | 0.00% | |
| May | 0.00% | 0.00% | |
| Jun | 0.00% | 0.00% | |
| Jul | 0.00% | 0.00% | |
| Aug | 0.00% | 0.00% | |
| Sep | 0.00% | 0.00% | |
| Oct | 0.00% | 0.00% | |
| Nov | 0.00% | 0.00% | |
| Dec | 0.00% | 0.00% |
GRAPH
| Line No. | Work Element | % | 12/31/99 | 0 | 44576 | 44591 | 44607 | 44620 | 44635 | 44651 | 44666 | 44681 | Actual | Scheduled |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 1 | Final Inspection and Closeout | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 2 | Design | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 3 | PROGRESS CLEANING | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 4 | DUMPSTERS | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 5 | FINAL CLEANUP | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 6 | DEMOLITION AND DUST PARTITION | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 7 | CONCRETE | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 8 | WOOD FRAMING - BLOCKING WALLS | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 9 | MILLWORK/CASEWORK | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 10 | INSULATION | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 11 | SEALANTS - FIRE AND ACOUSTIC | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 12 | DOORS, FRAMES, & ACCESS CONTROL | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 13 | PASS THROUGH WINDOW , 36" X 36" | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 14 | METAL STUD WALL FRAMING | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 15 | DRYWALL | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 16 | ACOUSTICAL AND SHEETROCK CEILINGS | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 17 | PORCELAIN TILE REPAIRS | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 18 | FLOORING | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 19 | PAINTING | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 20 | RESTROOM SPECIALTIES | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 21 | FIRE EXTINGUISHER & SIGN SPECIALTIES | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 22 | AUDITORIUM SEATING | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 23 | FIRE SUPPRESSION SPRINKLER SYSTEM | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 24 | PLUMBING | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 25 | HVAC | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 26 | COMMISSIONING | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 27 | ELECTRICAL | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 28 | FIRE ALARM | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | |
| 29 | DATA/COMMUNICATIONS | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0 | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| 0 | 0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| PERCENTAGE OF COMPLETION (CUMULATIVE) | 0.0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| SCHEDULED COMPLETION | 0.0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| ACTUAL COMPLETION | 0.0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
| ACTUAL COMPLETION (CUMULATIVE) | 0.0 | 0.00% | 0 | 0.0 | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% |
&LRenovations to Bldg. 743&CProgress Schedule
FA3047-16-C-0007&R&D
GRAPH
| Jan | Jan |
| Feb | Feb |
| Mar | Mar |
| Apr | Apr |
| May | May |
| Jun | Jun |
| Jul | Jul |
| Aug | Aug |
| Sep | Sep |
| Oct | Oct |
| Nov | Nov |
| Dec | Dec |
&LBMT Chapel HVAC Replacement&CProgress Schedule Period 24 Oct 07 - 18 Sep 08 FA3047-07-C-0044&RNovember 19, 2007
ACTUAL
SCHEDULED