Attachment 12 - Material Submittals Schedule-MSS_15 June 2021.xls

XLS spreadsheet 51 KB Posted

Attached to
Fiber Optic Cable Installation to Various Facilities Federal contract opportunity
Solicitation number
FA301021R0013
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document contains a material submittals schedule template and details of a federal contract opportunity for fiber optic cable installation to various facilities. The schedule template lists items or descriptions of items, contract references, types of submittals including certificates of compliance and shop drawings, required submission dates, dates received and reviewed by the contracting and civil engineering teams, submittal numbers, approval dates, and other fields.

The solicitation is for fiber optic cable installation services valued between $500,000 and $1,000,000 as a 100% small business set-aside. An organized site visit is scheduled for 12 July 2021 at Keesler Air Force Base, where contractors must have valid identification and follow current health protection conditions regarding masks and distancing. Proposals are due as outlined in Section L and will be evaluated as specified in Section M. The solicitation was issued by the Department of the Air Force Air Education and Training Command.

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
MAHG-2020-00004-00001 / MAHG-2018-00005-00001 / MAHG-2020-00003-00001Project Title:
FOC to Support Connectivity to Various BuildingsSolicitation / Contract Number:

[ enter here ]

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission DateDate Received in ContractingDate to Civil EngineeringReturn Suspense DateSubmittal NumbersDate Contractor
NotifiedContractor ResubmittalFinal Approval
ApprovedDisapproved
1
13
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24

&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).

&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)

File details come from the government source that posted it. Updated .