SECTION 01 42 00
RFERENCED SPECIFICATIONS AND STANDARDS
PART 1 - GENERAL
1.1 REFERENCED SPECIFICATIONS
A. Fort Sill adopts Chapters 200 through 800 of the Oklahoma Department of Transportation Special Provisions for any and all paving, sidewalks, roadwork or similar construction. Fort Sill further adopts Section 101 of Chapter 100.
1.2 REFERENCED STANDARDS
A. All work at Fort Sill must comply with the most current revision of the Unified Facilities Criteria (UFC). The UFC’s may be obtained at the following website:
http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4.
B. All roadwork must comply with the latest ASHTO Standard.
C. Fort Sill adopts all the International Building Codes unless specifically excluded by the UFC’s or in a specific task order statement of work.
D. Fort Sill adopts all the National Fire Protection Association Standards unless specifically excluded by the UFC’s or in a specific task order statement of work.
E. All drawings must comply with the latest versions of ERDC/ITL TR-12-6 A/E/C CAD Standard and ERDC/ITL TR-12-1 CAD Drafting Standard.
1.3 APPLICATION
A. The above referenced specifications and standards shall be a part of Fort Sill’s standard specifications.
B. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.
PART 2 - PRODUCTS - NOT APPLICABLE TO THIS SECTION
PART 3 - EXECUTION - NOT APPLICABLE TO THIS SECTION
END OF SECTION