Attachment 01 Pricing spreadsheet.pdf
PDF 111 KB Posted
- Attached to
- CSC-20103 Preventative Maintenance Circuit Breaker, Switchboard, Switchgear, Motor Control PM, Bldg. 23
- Solicitation number
- SP4702-20-R-0022
- Issued by
-
Defense Logistics Agency
About this file
This document includes a pricing spreadsheet and solicitation for a preventative maintenance service contract for circuit breakers, switchboards, switchgear, and motor control equipment in Building 23. The contract is a firm fixed price award with one base year and two option years.
Level 1 services include regularly scheduled annual, two-year, and three-year maintenance. Level 2 involves repair of unexpected breakdowns, which are invoiced separately. Offerors must visit the site, obtain a DBIDS code to access the facility, and submit a visit authorization request. Questions are due by August 25th and should be sent to the contracting officer. The successful bidder must coordinate services with building security and operations managers by requesting approved service interruptions at least 45 days in advance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Bid Form Sheet 1 Project: CSC-20103 Circuit Breaker, Switchboard, Switchgear, & Motor Control PM
Estimator: Date:
Location: Building 23 Checked
UFGS
Division Number Division Description
Year of Contract Unit Bu ld in g
Sub Contractor Expense (M+L)
Sub Contractor Overhead
Sub Contractor Profit
Total Sub Contractor
Prime Contractor Bonding
Prime Contractor Cost
Division Cost by Building
1 General Conditions Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
2 Existing Conditions Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
3 Concrete Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
4 Masonry Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
5 Metals Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
6 Wood, Plastic, and Composites Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
7 Thermal and Mosture Protedtion Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
8 Openings Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
9 Finishes Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
10 Spedialites Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
11 Equipment Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
12 Furnishings Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23 Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23 Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
Total
Contractor Bid Form Sheet 2 Project: CSC-20103 Circuit Breaker, Switchboard, Switchgear, & Motor Control PM
Estimator: Date:
Location: Building 23 Checked
UFGS
Division Number Division Description
Year of Contract Unit Bu ld in g
Sub Contractor Expense (M+L)
Sub Contractor Overhead
Sub Contractor Profit
Total Sub Contractor
Prime Contractor Bonding
Prime Contractor Cost
Division Cost by Building
13 Special Construction Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
14 Conveying Equipment Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
21 Fire Suppression Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
22 Plumbing Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
23 Heating, Ventilation, & Air Conditioning Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
26 Electrical Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
27 Communications Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
28 Electronic Safety and Security Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
31 Earthwork Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
32 Exterior Improvements Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
33 Utilities Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
34 Transportation Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23 Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23 Yr=1st LS 23 Yr=2nd 23 Yr=3rd 23
Total
| C-CSC-20103 Contract Bid Form S1 |
| Sheet1 |
| C-CSC-20103 Contract Bid Form S2 |
| Sheet2 |
File details come from the government source that posted it. Updated .