This document provides details for a federal contract solicitation to renovate a cardiology cath lab at the Veterans Affairs Medical Center in Altoona, Pennsylvania. Solicitation number 36C26222B0003 seeks offers for the renovation of the 4N Cardiology Cath Lab II under project number 664-CSI-116. The work includes renovating an existing cath lab to improve patient care services. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22. Offerors should reference the provided solicitation number in any responses regarding the opportunity.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
METAL DECK SCHEDULE
SHEET
WIDTH
TOP SEAM WELD
SPACING
# OF SUPPORT WELDS PER
SHEET
36" 12" 4
NOTES:
1. METAL DECKING PER DET 3 THIS SHT
2. WHERE 3/4" DIAMETER PUDDLE WELD IS INDICATED, THE 3/4" INDICATES THE MINIMUM EFFECTIVE FUSION DIAMETER OF WELD METAL
ON FRAMING MEMBER
3. MINIMUM BEARING LENGTH = 2"
12" OC MAX, UON
SUPPORT WELDS
DECK ENDING AT
FRAMING MEMBER
DECK CONTINUOUS
OVER FRAMING MEMBER
SIDE SEAM WELDS MARGINAL WELDS
3/4" DIA PUDDLE WELDS
SPACED AS INDICATED
MARGINAL STEEL
FRMG MEMBER
OR SHEAR
TRANSFER MEMBER
PARALLEL
TO DECK SPAN
LENGTH OF TOP
SEAM WELD = 1 1/2"
TOP SEAM WELD
MUST ENGAGE
INNER LIP,
SPCG PER SCHED
3/4" PUDDLE WELDS
SPACED AS INDICATED
L
NOTE:
1. FOR DECK WELDING, SEE DET 1 THIS SHT
2. CORRUGATED VALLEY MUST OCCUR OVER BEAM OR SEPERATE DECK AS SHOWN
* PROVIDE MIN 2 1/2" BEARING AT DECK SPLICE
L /3 L /3
1" CL
R 1" CL
R
3"
MIN
CONCRETE TOPPING & DECK PER PLAN
#4 x 6'-0" @ 24" OC CTR'D OVER BM
3/4" x 4" AUTOMATIC END WELDED HEADED STUDS
@ 12" OC
CL BM & STUDS
CONCRETE TOPPING
& DECK PER PLAN
#4 @ 18" OC
3/4" x 4" AUTOMATIC END WELDED HEADED STUDS
@ 12" OC
NEW OR EXIST BM OR TRUSS, TYP
EXIST FURRING WHERE OCCURS, SEE ARCH
DWGS FOR DEMOLITION INFORMATION
CL BM & STUDS
COUPLING NUT
3/8" DIA x 1'-6" THR ROD
REINF PER DET 3 THIS SHT
DEMO & REMOVE EXIST CONC CURB
3/8" DIA THR ROD W/ 6" EMBED @ 24" OC IN DRILLED
HOLE FILLED W/ HILTI HIT-RE 500 V3 EPOXY
(E) BM OR TRUSS
3/8" BENT PL
MTL DECK PER PLAN
SLAB INFILL PER PLAN
EXIST REINF, TYP
EQ
EQ
4" 5"
3"
CHIP AWAY CONC (3/4" DEEP, DO NOT
DAMAGE EXIST REINF), PROVIDE LEVELING
GROUT AS REQD SO THAT TOP OF BENT PL
IS FLUSH W/ TOP OF EXIST CONC SLAB
EXIST 5" CONC SLAB
CLEAN, ROUGHENED SURFACE
EXIST CONC SLAB
DRILLED HOLE W/ HILTI HIT-HY-200
EPOXY
#4 CONT
#3 DOWELS @ 16" OC
3 1 /2"
EM
BE
D
WALL FRAMING PER ARCH DWGSCONCRETE CURB, SEE ARCH DWGS FOR
INFORMATION NOT SPECIFIED
4"
MI
N 8"
MA
X
2" CL
R
EQ EQ
(E) WT PER PLAN
(E) CONCRETE SLAB
PER PLAN
WT TRIM AS REQ'D
1/2 " M
AX
1/2" MAX
12" EA
END, TYP 5/16" 4-12
12" EA
END, TYP 5/16" 4-12
COPE TOP FLG
1/4"
WT6x13
3 3/4" MIN
3/8" STIFF PL
L6 x 3 1/2 x 3/8
WT TRIM
(E) DIAGONAL / (E) VERTICAL
WT TRIM
TRIM FLANGE AS REQ'D @
(E) VERTICAL / (E) DIAGONAL
(E) WT
1/2" MAX 1/2" MAX
3/8" BENT PL x L3 x 0'-3" EA SIDE
WT PER PLAN, EXTEND AT LEAST
12" BEYOND NEXT ADJACENT
PANEL POINT IN EACH DIRECTION
(E) WT
1/2 " M
AX
6" M
AX
1/2" MAX
12" EA
END, TYP5/16" 4-12
TYP
5/16" 4
TYP
5/16"
TYP
5/16"
TYP
5/16"
5/16"
NOTE:
1. SEE DET 8 FOR CONNECTION AT
(E) VERTICAL / (E) DIAGONAL
2. SEE DET 7 FOR TOP CHORD
3. COPE FLANGE OF NEW 'T' SECTION TO AVOID (E) TRUSS DIAGONALS
TOP OF CHORD
BOTT OF CHORD
S-505
2 1 /2"
TOP OF
DECK
1"
3/8" PL EA SIDE
BRACE CONNECTION ANGLE
(4 REQUIRED)
MOUNTING PLATE PLAN
FOR EXTENDED HUB
GUSSET PLATE DETAIL
(6 REQUIRED)
5/16"
3/16"
3/16"
3/16"
3/16"
9" x 1 1/2"
NOTCH
5 3/4" TYP
1/2"
1/
2"
SQ
UA
RE
7 1 /2"
DIAGONAL BRACE
(6) GUSSET PLATE L3x3x1/4 x 2 1/2"
MOUNTING PLATE BY SKYTRON 1" ASTM A36 FY = 36 KSI
WITH (6) 1 1/4" ASTM A193 B7 BOLTS PROVIDED BY
SKYTRON (Fu = 125 KSI) ON A 10 5/8" BOLT CIRCLE. 500
FT-LBS INSTALLATION TORQUE
1/2" CLIP
PL 3/8"
6"
PIP
E
4" TYP
1/2" TYP
S-505
EQ
EQ
0"
CONC INFILL (f'c = 3000 PSI)
#4 DOWEL @ 16" OC, (3 BARS EA SIDE, MIN)
#4 DOWEL @ 16" OC EA SIDE OF INFILL, PROVIDE DOWEL AT 3" MAX FROM EACH
CORNER
1 1/2" CLR
TYP
4"
ROUGH CLEAN SURFACE, TYP
COMPLETE INFILL
EXIST CONC SLAB PER PLAN
1 1
/2" TY
P
3" TY
P
1/4
TYP EA FLANGE
3/16
TYP
3/8" PL, TYP
(3) 7/8" A325N BOLTS
1 1/2"
TYP
3"
MAX
CONDITION FOR
CONNECTING BM
CONDITION FOR NO
CONNECTING BM
1/4"
1/2" DIA WEDGE ANCHORS
@ 48" OC STAGGERED
INTERRUPT ANGLE
AT BM CONN
1"
CL
R
GALVANIZED METAL FLOOR DECK
6x6-W4.0xW4.0 WWF PROVIDED IN FLAT SHEETS, LAP SPLICE = 12"
LIGHTWEIGHT CONCRETE
TOPPING (107-113 PCF)
OMIT AT 3A
5"
DE
PT
H A S
NO
TE
D
METAL DECK PROPERTIES PER FOOT OF WIDTH
DECK TYPE PLB
DEPTH 1 1/2"
MIN GAGE 16 GA (G60 COATING)
MIN Ix 0.377 IN4
MIN Sx 0.411 IN3
MIN Fy 38,000 PSINOTE:
1. DECK CONNECTIONS:
A. DECK SUPPORT WELDS AT EACH FLUTE, SEE DETAIL 1 THIS SHEET
B. DECK MARGINAL WELDS, SEE DETAIL 4 THIS SHEET
C. SIDE SEAMS SHALL BE BUTTON PUNCHED AT 36" O.C. D. ALL WELDS PER AWS D1.3
2. METAL DECK SHALL HAVE MANUFACTURER'S STANDARD VENTED PUNCHED UP TABS IN THE BOTTOM FLUTE FOR POSITIVE VENTING OF BLEED
WATER FROM CONCRETE.
3. DECK SHALL BE INSTALLED IN MIN. 2 SPAN LENGTHS.
4. TOTAL SECTION SHALL HAVE A 2 HOUR FIRE RATING AS VALIDATED BY ICC EVALUATION REPORT.
STANDING SIDE
SEAM JOINT
CLG PL (BY MFR)
PL PER DET 9 THIS SHT
LIGHT (PER MFR)
CLG PER ARCH DWGS
"D " P
ER
DE
T 2
3 / S5
-50
DBL NUTS, TYP
DBL NUTS, TYP
1870 Cordell Court, Suite 202 El Cajon, CA 92020 tel 619 312 6336 aarkengineering.com
R
Exp. 6/30/2022
NE
TA
S
T
FO
ACOF LI
R R
AI
L
OSOR FE SI
T I
EG
S
DE
ER
P
No. 4948
J
NA
GI
E
RE
N
EN
TS
U C
A A
RO
N
AMES STEELE
T U RAL
ASDAVY.074.00 SP
A R C H I T E C T
EXP I RES A UGUS T 3 1 , 2
0 2
1#C 14152
STATE
OF CA L I FORN
I A
ER
IC H . DAVY
OFFICE OF
CONSTRUCTION AND
FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
ENGINEER OF RECORD SHEET TITLE
F
E
D
C
B
A
VA FORM
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10
ARCHITECT OF RECORD
APPROVED PROJECT DIRECTOR
PROJECT PHASE
BUILDING CONSTRUCTION
PROJECT TITLE
PROJECT LOCATION
ISSUE DATE CHECK BY DRAWN BY
PROJECT NUMBER
BUILDING NUMBER
DRAWING NUMBER
08 - 6231
REVISIONS: DATE:NO.
664-CSI-116
BLDG #1
VA MEDICAL CENTER SAN DIEGO, 3350 LA JOLLA
VILLAGE DR., SAN DIEGO, CA 92161
100% CONSTRUCTION DOCUMENTS
FULLY SPRINKLEREDMICHAEL DEGNAN - VA DESIGN PROJECT MANAGER
06/11/2019 07/16/2019 08/23/2019 12/24/2020
35% SCHEMATIC DESIGN
35% SCHEMATIC DESIGN- RESUBMITTAL
65% DESIGN DEVELOPMENT
REVISED 65% DESIGN DEVELOPMENT
MAY 10, 2021
02/18/202195% CONSTRUCTION DOCUMENTS
04/09/2021100% CONSTRUCTION DOCUMENTS
REVIEWED IN
ACCORDANCE WITH THE
REQUIRMENTS OF CFM
BY:___________________
DATE:________________
U.S. DEPARTMENT OF
VETERANS AFFAIRS
ENGINEERING SERVICES
APPROVED05/10/2021IFC DOCUMENTS 4TH FLOOR 4N CARDIOLOGY CATH LAB 2
S-503
STRUCTURAL DETAILS
1 DETAIL
1 1/2" = 1'-0"
2 DETAIL
1 1/2" = 1'-0"
4 DETAIL
1 1/2" = 1'-0"
5 DETAIL
1 1/2" = 1'-0"
7 TOP CHORD CONNECTION DETAIL
3" = 1'-0"
8 BOTTOM CHORD @ (E) DIAGONAL / (E) VERTICAL
3" = 1'-0"
10 BOTTOM CONNECTION CHORD
3" = 1'-0"
9 EQUIPMENT SUPPORT PLATE DETAIL
3" = 1'-0" 6 SLAB INFILL DETAIL
NTS
11 TYPICAL ECCENTRIC SHEAR CONNECTION
1 1/2" = 1'-0"
12 TOP CHORD SECTION
3" = 1'-0" 3A DETAIL
1 1/2" = 1'-0"3
13 EQUIPMENT SUPPORT PLATE SECTION DETAIL
1 1/2" = 1'-0"
P:
\D
AV
Y
- D av y Ar ch ite ct ur e\ D
AV
Y.
- V A
La Jo lla C at h
La b\
D ra w in gs \S tru ct ur al
\D
AV
Y0
-S
3.
dw g, /6
/2
4:
:3
PM
, D W
G To
P D
F.
pc
2"
TY
P16
7"
8" TYP
11" TYP
CGCL TABLE PIVOT
(10) M20 (GRADE 5)
THROUGH BOLTS (HOLES
TO BE 1/16" LARGER)
BASE PL PER MFR
RECOMMENDATIONS (PT TABLE)
CL TABLE & GANTRY
PATIENT TABLE PER
SCHEDULE ON SHT S101
(8) M20 (GRADE 5)
THROUGH BOLTS (HOLES
TO BE 1/16" LARGER) FOR
PATIENT TABLE MOUNT
'-1
CMS PIVOT AXIS
22.4"
CL
UN
IT
CM
S P
IVO
T A
XIS
(4) M20 (GRADE 5)
THROUGH BOLTS (HOLES
TO BE 1/16" LARGER)
BASE PL PER MFR
RECOMMENDATIONS (CMS)
GANTRY PER SCHEDULE
ON SHT S101
17"
.62
5"
1 1/2" MIN
TYP
1 1 /2"
M
IN
TY
P
CG
" M
AX
EQUIP PER SCHED ON SHT S101
(E) SLAB PER PLAN
SLAB RECESS (1" MAX), BASE PL
FLUSH WITH TOP OF EXIST SLAB
STL BM PER PLANSTL BM PER PLAN
23.6
CG
8"
TY
P 1 1
/2" M
IN
8" TYP1 1/2" MIN 4"
5/8" DIA THRU BOLT WITH PL
WSHR ON THE UNDERSIDE
OF THE DECK, TYP OF (8)
1/2" THK PL (GR. 50 KSI), VFCI
FRONT ELEVATION
11"
.9"
CG
12.3"
(E) COMPOSITE
DECK PER PLAN
EQUIP PER SCHED
ON SHT S101
23.3"
SECTION A-A
11" 12.3"
" M
AX
1" TY
P
CG
8"
(4) 1/2" THR RODS
(2) STL BRACKETS (10 GA) W/
1/4" TEK SCWS EA BRACKET
#12 SMS, TYP OF (3)
EA BENT PL
'H'
" M
AX
EQUIP PER SCHED
ON SHT S101
51"
.4"
'H'
.9"
M
AX CG
24.6" 26.4"
.5"
39.4"
18.8" 20.6"
WALL BRACKET W/
(8) 1/4" TEK SCWS
'P1000' UNISTRUT x 18" MIN
(E) COMPOSITE
DECK PER PLAN
CHANNEL NUT
(WHERE OCCURS)
EQUIP PER SCHED
ON SHT S101
BACKING PL PER DTL 1
ON SHT S001
CG
1 1/2"
MIN
(2) #12 SMS TO (E) STUD, MIN (3) STUD
(2) 1/4" TEK SCWS EA END
12 GA BENT PL, FV DIMS
FRONT ELEVATION SECTION A-A
16"
5.6"7.8"
(2) 1/2" THR RODS,
(4) TOTAL
STL BRACKET
W/ (3) M12 M SCWS EA BRACKET
(E) STUD WALL PER
ARCH DWGS
H/2
6" MAX
2"
MI
N
TY
P
" M
IN
1'-2" MIN
EQ EQ
2" MIN
TYP
8" MAX
(2) 3/8" CHANNEL NUT
AND BOLT T&B, TYP OF
(4) PER CABINET
P1000 STRUT TO SPAN (2) STUDS
MIN, ATTACH TO METAL STUDS
W/ 1/4" SS OR HDG SMS, ICC
ESR-1976, MIN OF (2) PER STUD
STRUT TO SPAN (3) STUDS WHERE 8"
MAX DISTANCE FROM EDGE OF
CABINET TO CENTERLINE OF
ATTACHMENT TO STUD OCCURS
" M
AX
CG
ELEVATION
SECTION
Y Z
H1 H2
" M
AX
EQ EQ
CG
(4) 1/2" THR RODS
1'- 3"
3'-10 9/16"
CG
EQ EQ
EQ
EQ
EQUIP PER SCHED
ON SHT S101
EXIST CONC SLAB
PER PLAN
FRONT ELEVATION
SECTION A-A
'H' / 1
/2
FRONT ELEVATION
11"
'H' / 1
/2
CG
12.3"
SLAB PER PLAN
EQUIP PER SCHED
ON SHT S101
'H'
.4"
M
AX
SECTION A-A
CG
3'- 4"
3'-0 1/2"
EQUIP PER SCHED
(4) 1/2" THR RODS
EQ
EQ
12.3"
1 GANTRY AND PATIENT TABLE SUPPORT DETAIL
3/4" = 1'-0"
3 PATIENT TABLE SUPPORT DETAIL
1" = 1'-0"
2 ASSEMBLY PLATE ANCHORAGE DETAIL
1 1/2" = 1'-0"
8 C-FRT CABINET ANCHORAGE DETAIL
1" = 1'-0"
7 MAIN DISCONNECT PANEL - WALL MOUNTED
1 1/2" = 1'-0"
5 POWER DISTRIBUTION UNIT
1" = 1'-0"
4 UPS SEISMIC KIT ANCHORAGE DETAIL
1" = 1'-0"
1870 Cordell Court, Suite 202 El Cajon, CA 92020 tel 619 312 6336 aarkengineering.com
R
Exp. 6/30/2022
NE
TA
S
T
FO
ACOF LI
R R
AI
L
OSOR FE SI
T I
EG
S
DE
ER
P
No. 4948
J
NA
GI
E
RE
N
EN
TS
U C
A
AR
ON
AMES STEELE
T U RAL
ASDAVY.074.00 SP
A R C H I T E C T
EXP I RES A UGUS T 3 1 , 2
0 2
1#C 14152
STATE
OF CA L I FORN
I A
ER
IC H . DAVY
OFFICE OF
CONSTRUCTION AND
FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
ENGINEER OF RECORD SHEET TITLE
F
E
D
C
B
A
VA FORM
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10
ARCHITECT OF RECORD
APPROVED PROJECT DIRECTOR
PROJECT PHASE
BUILDING CONSTRUCTION
PROJECT TITLE
PROJECT LOCATION
ISSUE DATE CHECK BY DRAWN BY
PROJECT NUMBER
BUILDING NUMBER
DRAWING NUMBER
08 - 6231
REVISIONS: DATE:NO.
664-CSI-116
BLDG #1
VA MEDICAL CENTER SAN DIEGO, 3350 LA JOLLA
VILLAGE DR., SAN DIEGO, CA 92161
100% CONSTRUCTION DOCUMENTS
FULLY SPRINKLEREDMICHAEL DEGNAN - VA DESIGN PROJECT MANAGER
06/11/2019 07/16/2019 08/23/2019 12/24/2020
35% SCHEMATIC DESIGN
35% SCHEMATIC DESIGN- RESUBMITTAL
65% DESIGN DEVELOPMENT
REVISED 65% DESIGN DEVELOPMENT
MAY 10, 2021
02/18/202195% CONSTRUCTION DOCUMENTS
04/09/2021100% CONSTRUCTION DOCUMENTS
REVIEWED IN
ACCORDANCE WITH THE
REQUIRMENTS OF CFM
BY:___________________
DATE:________________
U.S. DEPARTMENT OF
VETERANS AFFAIRS
ENGINEERING SERVICES
APPROVED05/10/2021IFC DOCUMENTS 4TH FLOOR 4N CARDIOLOGY CATH LAB 2
S-504
STRUCTURAL DETAILS
6 COOLIX CHILLER ANCHORAGE DETAIL
1" = 1'-0"
P:
\D
AV
Y
- D av y Ar ch ite ct ur e\ D
AV
Y.
- V A
La Jo lla C at h
La b\
D ra w in gs \S tru ct ur al
\D
AV
Y0
-S
4.
dw g, /6
/2
4:
:4
PM
, D W
G To
P D
F.
CG
Y Z
H1 H2
1 1/2"
MIN
#12 SMS, TYP OF (4)
EA ANGLE
1/2" HILTI KB-TZ WEDGE
ANCHOR x 2 3/8" NOM EMBED, TYP OF (4) TOTAL
L6 x 3 x 3/16 (LDV), CTR ON
EQUIP, TYP OF (2), VERTICAL
LEG DIM MAY BE INCREASED UP
TO 8" (TOTAL HT) AS REQD
OUTLINE OF EQUIP,
18 GA MIN HOUSING
SECTION A-A
FRONT ELEVATION
CG
1/2 'H
'H' P
ER
SC
HE
D
EQUIP PER SCHED
(E) CONC SLAB
PER PLAN
ELEVATIONSECTION
FINISH PER ARCH DWGS
EQ
EQ
(2) 1/4" SMS T&B (4 TOTAL) BRACKET TO STUDS,
INSTALL IN MFR PROVIDED HOLES
FLAT PANEL MONITOR PER ARCH
EXIST 3 5/8" x 16 GA STUDS @ 16" OC MIN
CG
4"
WALL MOUNT BRACKET PER
EQUIP ANCHORAGE SCHEDULE
BACKING TO (3) STUDS MIN PER
DET 5 ON SHT AG905, TYP
EXIST 362S162-43 @ 16" OC
NEW WALL MOUNT BRACKET
PER SECTION
NEW 600T125-54 BACKING,
TYP T&B, ATTACH TO EA OF
(3) STUDS MIN W/ (3) #12 SMS
NEW (4) TEK SCREWS PER
SECTION, TYP OF (2) EA T&B
24"
EQ6" MAX
TYP
EQ
CG
TYP
5/16"
HSS BEM PER PLAN
HSS BEM PER PLAN
HSS BEM PER PLAN
L2X2X1/4, TYP EA SIDE
TYP
3/16" 2-12
2-12
TYP
DECK PER PLAN
CG
2'- 1 1
/2" M
IN
2'-4 1/2" MIN
SECTION A-A
FRONT ELEVATION
CG
1/2 'H
'H' P
ER
SC
HE
D
EQUIP PER SCHED
(E) CONC SLAB
PER PLAN
3/4" DIA SS HILTI KB-TZ WEDGE
ANCHOR x 2" NOM EMBED, TYP
OF (4) TOTAL
HOUSEKEEPING PAD
PER DETAIL 6 THIS SHT
6" M
N
" M
AX
12"
CLEAN ROUGH SURFACE (1/4" MIN
AMPLITUDE)
DWLS INSERTED IN DRILLED HOLES FILLED W/
HILTI HIT-RE 500 V3 EPOXY, DOWELS SHALL BE
TENSION TESTED PER NOTES ON S001
EXIST 5" CONC SLAB#4 @ 12" OC EW
0"
2"
CLR
2"
CL
R
CONC EQUIP PAD
#4 @ 12" OC ALL EDGES
TYP
5" 5"
MI
N2 3
/8"
CG
8"
MAX
.1"
(N
TS
.4"
(N
TS
"D" PER SCHED (NTS)
EQ
EXIST 3 5/8" 16 GA MTL STUDS
@ 16" OC, MIN
GALV UNISTRUT P3300, TYP T&B
3/8" DIA BOLT, PANEL TO STRUT,
TYP OF (4)
#10 SMS, STRUT TO STUD, TYP OF (6)
PLANSIDE ELEVATION
EXIST STUD
ATTACH STRUT TO (1) STUDS BEYOND EA
END OF EQUIP (MIN (3) STUDS), TYP T&B
EQ
"W" PER SCHED
EXIST WALL FINISH
SWIVEL BRACKET
(300# MIN CAPACITY)
7'- 0"
MA
X (
FV
UNISTRUT 'P2486' @ 9" OC,
TYP EA HGR ROD
1 5/8" x 1 5/8" x 12 GA
STRUT STIFFENER, TYP EA
ROD (24" MIN TO 60" MAX)
2 1 /2"
NO
M
1/2" HILTI KB-TZ2
WEDGE ANCHOR
(E) CONC SLAB PER PLAN 1/2" HILTI KB-TZ2 WEDGE
ANCHOR, TYP EA BRACE
CLG PER ARCH
30°° TO
60°
LIGHT ASSEMBLY
1/2" COUPLER NUT
ANGLE (54 MIL) TYP BOTH
SIDES OF EA BRACE
(2) 1/2" A307 BOLT,
WASHER & CHANNEL NUT,
TYP EA END OF BRACE
CLG PL (2) #8 SCWS EA LEG
2" MA
X
4" MA
X
1/2" TH ROD
ELEVATION
1 5/8" X 1 5/8" X 12GA STRUT
IN (2) PERP DIRECTIONS
1870 Cordell Court, Suite 202 El Cajon, CA 92020 tel 619 312 6336 aarkengineering.com
R
Exp. 6/30/2022
NE
TA
S
T
FO
ACOF LI
R R
AI
L
OSOR FE SI
T I
EG
S
DE
ER
P
No. 4948
J
NA
GI
E
RE
N
EN
TS
U C
A A
RO
N
AMES STEELE
T U RAL
ASDAVY.074.00 SP
A R C H I T E C T
EXP I RES A UGUS T 3 1 , 2
0 2
1#C 14152
STATE
OF CA L I FORN
I A
ER
IC H . DAVY
OFFICE OF
CONSTRUCTION AND
FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
ENGINEER OF RECORD SHEET TITLE
F
E
D
C
B
A
VA FORM
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10
ARCHITECT OF RECORD
APPROVED PROJECT DIRECTOR
PROJECT PHASE
BUILDING CONSTRUCTION
PROJECT TITLE
PROJECT LOCATION
ISSUE DATE CHECK BY DRAWN BY
PROJECT NUMBER
BUILDING NUMBER
DRAWING NUMBER
08 - 6231
REVISIONS: DATE:NO.
664-CSI-116
BLDG #1
VA MEDICAL CENTER SAN DIEGO, 3350 LA JOLLA
VILLAGE DR., SAN DIEGO, CA 92161
100% CONSTRUCTION DOCUMENTS
FULLY SPRINKLEREDMICHAEL DEGNAN - VA DESIGN PROJECT MANAGER
06/11/2019 07/16/2019 08/23/2019 12/24/2020
35% SCHEMATIC DESIGN
35% SCHEMATIC DESIGN- RESUBMITTAL
65% DESIGN DEVELOPMENT
REVISED 65% DESIGN DEVELOPMENT
MAY 10, 2021
02/18/202195% CONSTRUCTION DOCUMENTS
04/09/2021100% CONSTRUCTION DOCUMENTS
REVIEWED IN
ACCORDANCE WITH THE
REQUIRMENTS OF CFM
BY:___________________
DATE:________________
U.S. DEPARTMENT OF
VETERANS AFFAIRS
ENGINEERING SERVICES
APPROVED05/10/2021IFC DOCUMENTS 4TH FLOOR 4N CARDIOLOGY CATH LAB 2
S-505
STRUCTURAL DETAILS
1 INTEGRATION CABINET ANCHORAGE DETAIL
1" = 1'-0"
2 MONITOR ANCHORAGE DETAIL (WALL MOUNTED)
1" = 1'-0"
3 HSS BEAM CONNECTION DETAIL
1" = 1'-0"
4 DECK INTERFACE AT HSS BEAM DETAIL
1" = 1'-0"
5 WAGD EQUIPMENT DETAIL
1" = 1'-0"
6 EQUIPMENT PAD DETAIL
1" = 1'-0"
7 WALL MOUNTD EQUIPMENT DETAIL
1" = 1'-0"
8 LIGHT SUPPORT DETAIL
1" = 1'-0"
P:
\D
AV
Y
- D av y Ar ch ite ct ur e\ D
AV
Y.
- V A
La Jo lla C at h
La b\
D ra w in gs \S tru ct ur al
\D
AV
Y0
-S
5.
dw g, /6
/2
4:
:0
PM
, D W
G To
P D
F.
WT PER PLAN, EXTEND AT LEAST
12" BEYOND NEXT ADJACENT
PANEL POINT IN EACH DIRECTION
(E) WT
1/2 " M
AX
12" EA
END, TYP5/16" 4-12
TYP
3/16" 2-12
TYP
5/16"
NOTE:
1. COPE FLANGE OF NEW 'T' SECTION TO AVOID (E) TRUSS DIAGONALS
2 1 /2"
TOP OF
DECK
SLAB INFILL PER PLAN
LINE OF SYMM WHERE OCCURS
L2X2X1/4
WT PER PLAN, EXTEND AT LEAST
12" BEYOND NEXT ADJACENT
PANEL POINT IN EACH DIRECTION
(E) WT
1/2 " M
AX
12" EA
END, TYP5/16" 4-12
TYP
5/16"
NOTE:
1. COPE FLANGE OF NEW 'T' SECTION TO AVOID (E) TRUSS DIAGONALS
SLAB INFILL PER PLAN
LINE OF SYMM WHERE OCCURS
L2X2X1/4
TYP
3/16" 2-12
WT PER PLAN, EXTEND AT LEAST
12" BEYOND NEXT ADJACENT
PANEL POINT IN EACH DIRECTION
(E) WT
1/2 " M
AX
1/2" MAX
12" EA
END, TYP5/16" 4-12
TYP
5/16" 4
TYP
5/16"
NOTE:
1. SEE DET 8 / S-503 FOR CONNECTION AT (E) VERTICAL / (E) DIAGONAL
2. COPE FLANGE OF NEW 'T' SECTION TO AVOID (E) TRUSS DIAGONALS
S-505
2 1 /2"
TOP OF
DECK
1"
L2X2X1/4"
5/16"
3/8" PL EA SIDE
TYP
3/16" 3/16" 2-12
2-12
SLAB INFILL PER PLAN
ANGLE PER PLAN
1870 Cordell Court, Suite 202 El Cajon, CA 92020 tel 619 312 6336 aarkengineering.com
R
Exp. 6/30/2022
NE
TA
S
T
FO
ACOF LI
R R
AI
L
OSOR FE SI
T I
EG
S
DE
ER
P
No. 4948
J
NA
GI
E
RE
N
EN
TS
U C
A A
RO
N
AMES STEELE
T U RAL
ASDAVY.074.00 SP
A R C H I T E C T
EXP I RES A UGUS T 3 1 , 2
0 2
1#C 14152
STATE
OF CA L I FORN
I A
ER
IC H . DAVY
OFFICE OF
CONSTRUCTION AND
FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
ENGINEER OF RECORD SHEET TITLE
F
E
D
C
B
A
VA FORM
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10
ARCHITECT OF RECORD
APPROVED PROJECT DIRECTOR
PROJECT PHASE
BUILDING CONSTRUCTION
PROJECT TITLE
PROJECT LOCATION
ISSUE DATE CHECK BY DRAWN BY
PROJECT NUMBER
BUILDING NUMBER
DRAWING NUMBER
08 - 6231
REVISIONS: DATE:NO.
664-CSI-116
BLDG #1
VA MEDICAL CENTER SAN DIEGO, 3350 LA JOLLA
VILLAGE DR., SAN DIEGO, CA 92161
100% CONSTRUCTION DOCUMENTS
FULLY SPRINKLEREDMICHAEL DEGNAN - VA DESIGN PROJECT MANAGER
06/11/2019 07/16/2019 08/23/2019 12/24/2020
35% SCHEMATIC DESIGN
35% SCHEMATIC DESIGN- RESUBMITTAL
65% DESIGN DEVELOPMENT
REVISED 65% DESIGN DEVELOPMENT
MAY 10, 2021
02/18/202195% CONSTRUCTION DOCUMENTS
04/09/2021100% CONSTRUCTION DOCUMENTS
REVIEWED IN
ACCORDANCE WITH THE
REQUIRMENTS OF CFM
BY:___________________
DATE:________________
U.S. DEPARTMENT OF
VETERANS AFFAIRS
ENGINEERING SERVICES
APPROVED05/10/2021IFC DOCUMENTS 4TH FLOOR 4N CARDIOLOGY CATH LAB 2
S-506
STRUCTURAL DETAILS
1 DETAIL
3" = 1'-0"
3 BOTTOM CHORD
3" = 1'-0"
2 DETAIL
3" = 1'-0"
4 DETAIL
3" = 1'-0"
P:
\D
AV
Y
- D av y Ar ch ite ct ur e\ D
AV
Y.
- V A
La Jo lla C at h
La b\
D ra w in gs \S tru ct ur al
\D
AV
Y0
-S
6.
dw g, /6
/2
4:
:0
PM
, D W
G To
P D
F.
ENGINEER OF RECORD SHEET TITLE
F
E
D
C
B
A
VA FORM
OFFICE OF
CONSTRUCTION AND
FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10
ARCHITECT OF RECORD
APPROVED PROJECT DIRECTOR
PROJECT PHASE
BUILDING CONSTRUCTION
PROJECT NUMBER
BUILDING NUMBER
DRAWING NUMBER
08 - 6231
REVISIONS: DATE:NO.
664-CSI-116
BLDG #1
QUALITY CONSTRUCTIONMICHAEL DEGNAN - VA DESIGN PROJECT MANAGER
www.coffman.com ph 619.232.4673
1455 Frazee Rd., Suite 600 San Diego, CA 92108 ph 619.232.46736/11/2019
7/16/2019 8/23/2019
12/24/2020
35% SCHEMATIC DESIGN
35% SCHEMATIC DESIGN- RESUBMITTAL
65% DESIGN DEVELOPMENT
REVISED 65% DESIGN DEVELOPMENT
100% CONSTRUCTION DOCUMENTS
02/18/2021 95% CONSTRUCTION DOCUMENTS
04/09/2021 100% CONSTRUCTION DOCUMENTS
PROJECT TITLE
PROJECT LOCATION
ISSUE DATE CHECK BY DRAWN BY
VA MEDICAL CENTER SAN DIEGO, 3350 LA JOLLA
VILLAGE DR., SAN DIEGO, CA 92161
MAY 10, 2021
REVIEWED IN
ACCORDANCE WITH THE
REQUIRMENTS OF CFM
BY:___________________
DATE:________________
U.S. DEPARTMENT OF
VETERANS AFFAIRS
ENGINEERING SERVICES
05/10/2021 IFC DOCUMENTS 4TH FLOOR 4N CARDIOLOGY CATH LAB 2
GENERAL MECHANICAL NOTES
(THESE NOTES ARE TO BE APPLIED TO ALL MECHANICAL DRAWINGS WITHIN THIS SET AND ANY
ADDENDUMS, RFI'S, OR SUBSEQUENT DOCUMENTATION PERTAINING TO THIS PROJECT.)
1. CONTRACTOR SHALL SECURE, MAINTAIN, AND PAY FOR ALL REQUIRED PERMITS, LICENSES, AND
INSPECTIONS FOR DURATION OF WORK UNLESS DIRECTED OTHERWISE.
2. ALL WORK SHALL COMPLY WITH THE OWNER'S REQUIREMENTS, AND WITH ALL APPLICABLE
STATE AND LOCAL CODES, OR AUTHORITY HAVING JURISDICTION.
3. DRAWINGS ARE DIAGRAMMATIC IN NATURE AND DO NOT ATTEMPT TO SHOW ALL REQUIRED
OFFSETS. COORDINATE WITH OTHER TRADES AND PROVIDE ALL NECESSARY OFFSETS. REFER
TO ARCHITECTURAL AND STRUCTURAL DRAWINGS FOR CONSTRUCTION DETAILS.
4. REFER TO PROJECT MANUAL (SPECIFICATIONS) FOR ADDITIONAL REQUIREMENTS. PLANS AND SPECIFICATIONS SHALL BE TAKEN TOGETHER. PROVIDE ALL WORK CALLED FOR IN EITHER. IN CASE OF CONFLICT BETWEEN SPECIFICATIONS AND PLANS THE MORE STRINGENT SHALL APPLY.
5. MATERIALS OR EQUIPMENT SPECIFIED TO BE "FURNISHED BY OTHERS" SHALL BE FURNISHED BY
THE GENERAL CONTRACTOR AND PROCURED FROM SOURCES SPECIFIED BY THE CONTRACT
DOCUMENTS.
6. ALL EQUIPMENT AND MATERIAL ON THE JOB SITE PRIOR TO INSTALLATION SHALL BE COVERED
AND PROTECTED FROM DIRT, DUST, AND DAMAGE.
7. PROVIDE ALL DEMOLITION WORK CALLED FOR OR REQUIRED BY THE INSTALLATION. REMOVE ALL EXISTING EQUIPMENT AND MATERIALS NOT REUSED UNLESS SPECIFIED OTHERWISE BY THE
OWNER'S REP.
8. VERIFY PHYSICAL DIMENSIONS OF EQUIPMENT TO ENSURE THAT ACCESS CLEARANCES CAN BE
MET. COORDINATE FINAL EQUIPMENT LOCATIONS W/ GENERAL CONTRACTOR AND OTHER
TRADES TO ALLOW FOR REQUIRED MECHANICAL EQUIPMENT CLEARANCES.
9. PROVIDE NEC CODE MINIMUM HORIZONTAL AND VERTICAL WORKING CLEARANCES FOR ALL
ELECTRICAL PANELS AND EQUIPMENT. OFFSET MECHANICAL WORK AS REQUIRED.
10. CONTRACTOR IS RESPONSIBLE FOR VERIFICATION OF INSTALLATION STANDARDS AND
CONSTRUCTION CONDITIONS. CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND
EXISTING CONDITIONS PRIOR TO SHOP FABRICATION AND/OR FIELD INSTALLATION.
DISCREPANCIES BETWEEN EXISTING CONDITIONS AND THE CONSTRUCTION DRAWINGS SHALL BE
CALLED TO THE ATTENTION OF THE ENGINEER. WORK DONE WITHOUT THE ENGINEERS
APPROVAL IS THE RESPONSIBILITY OF THE CONTRACTOR.
11. ALL MECHANICAL EQUIPMENT, MATERIALS, AND INSTALLATION SHALL BE PROVIDED BY THE
CONTRACTOR. ALL EQUIPMENT SHALL BE COMPLETE, INSTALLED, AND FULLY FUNCTIONAL
PRIOR TO FINAL ACCEPTANCE OF THE WORK.
12. INSTALL ALL EQUIPMENT PER MANUFACTURERS RECOMMENDATIONS AND REQUIREMENTS. ANY
CONFLICTS BETWEEN THE MANUFACTURERS DOCUMENTATION AND THE CONTRACT
DOCUMENTS SHALL BE BROUGHT TO THE ATTENTION OF THE ENGINEER.
13. PROVIDE SEISMIC RESTRAINT OF MECHANICAL SYSTEMS AND EQUIPMENT AS REQUIRED BY
ASCE-7 AND INTERNATIONAL BUILDING CODE AS ADOPTED BY THE AUTHORITY HAVING
JURISDICTION.
14. DO NOT ALLOW ANY WORK TO BE COVERED UP OR ENCLOSED UNTIL INSPECTED, TESTED AND
APPROVED BY OWNER'S REPRESENTATIVE OR AUTHORITY HAVING JURISDICTION.
15. MECHANICAL EQUIPMENT SHALL NOT BE USED FOR TEMPORARY HEAT DURING CONSTRUCTION.
GENERAL HVAC NOTES
(THESE NOTES ARE TO BE APPLIED TO ALL HVAC DRAWINGS WITHIN THIS SET AND ANY ADDENDUMS, RFI'S, OR SUBSEQUENT DOCUMENTATION PERTAINING TO THIS PROJECT.)
1. SHEET METAL DUCTWORK AND COMPONENTS INCLUDING HANGING, SEALING, PLENUMS, &
ACCESSORIES SHALL BE CONSTRUCTED IN STRICT ACCORDANCE WITH THE LATEST EDITION OF
SMACNA STANDARDS FOR HVAC DUCT CONSTRUCTION, NFPA 90A, & 90B STANDARDS.
2. ALL DUCTWORK OPENINGS SHALL BE COVERED DURING CONSTRUCTION. ALL DAMPERS TO BE
SET TO BE FULLY OPEN DURING CONSTRUCTION PRIOR TO BALANCING.
3. CONTRACTOR TO PROVIDE TRANSITION TO CONNECT TO ALL MECHANICAL EQUIPMENT.
4. DUCT DIMENSIONS SHOWN ARE INSIDE SHEET METAL DIMENSIONS OR CLEAR OPENING INSIDE
LINED DUCT. THE FIRST NUMBER REPRESENTS THE WIDTH OF DUCT IN PLAN VIEW.
5. ALL ELBOWS SHALL BE LONG RADIUS ELBOWS WHEREVER POSSIBLE, OR SHALL HAVE TURNING
VANES WHERE INDICATED ON PLANS. NO SQUARE THROAT OR ZERO RADIUS ELBOWS ALLOWED.
6. ALL DUCT BRANCH CONNECTIONS TO DIFFUSER OR GRILLES, TO OR FROM MAIN DUCTS SHALL INCLUDE MANUAL VOLUME DAMPERS. ALL SPIN-IN FITTINGS SHALL BE CONICAL, RECTANGULAR
BRANCH DUCT TAKEOFFS SHALL HAVE 45° TAKEOFFS.
7. DUCTWORK SHALL NOT BE CONNECTED DIRECTLY TO DIFFUSER OR GRILLES UNLESS INDICATED IN DRAWINGS. DIFFUSER / GRILLE BOXES WITH LINER AND PERFORATED DIFFUSER PLATES SHALL
BE USED.
8. PROVIDE DIFFUSER AND GRILLE FRAMES COMPATIBLE WITH ARCHITECTURAL CEILING TYPES AND COORDINATE LOCATIONS WITH THE ARCHITECTURAL REFLECTED CEILING PLAN AND ELECTRICAL
LIGHTING LAYOUT.
9. ALL DUCTWORK VISIBLE THROUGH RETURN OR SUPPLY GRILLES TO BE PAINTED FLAT BLACK.
10. ALL SUPPLY, RETURN AND EXHAUST AIR DUCTS SHALL HAVE THE TRANSVERSE JOINTS,
LONGITUDINAL SEAMS AND DUCT WALL PENETRATIONS SEALED AIRTIGHT WITH DUCT SEALANT
(SMACNA SEAL CLASS "A") AND SHALL CONFORM TO LOCAL BUILDING CODES.
11. COORDINATE LOCATIONS OF ALL ROOM THERMOSTATS AND/OR ROOM TEMPERATURE SENSORS
WITH ARCHITECTS PRIOR TO INSTALLATION.
12. BALANCE AIR SYSTEM TO QUANTITIES SHOWN, AND SUBMIT A COPY OF THE BALANCE REPORT TO
THE ENGINEER FOR REVIEW.
GENERAL PLUMBING NOTES
(THESE NOTES ARE TO BE APPLIED TO ALL PLUMBING DRAWINGS WITHIN THIS SET AND ANY
ADDENDUMS, RFI'S, OR SUBSEQUENT DOCUMENTATION PERTAINING TO THIS PROJECT.)
1. PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT NECESSARY TO CONSTRUCT A COMPLETE, OPERATIONAL PLUMBING SYSTEM FOR THE ENTIRE PROJECT AS SHOWN ON THESE DRAWINGS, INCLUDING ALL NECESSARY FEES AND PERMITS.
2. THE ENTIRE INSTALLATION SHALL CONFORM TO THE MOST RECENTLY ADOPTED REQUIREMENTS
OF THE BUILDING CODE, MECHANICAL CODE, PLUMBING CODE, ELECTRICAL CODE, AND ALL
OTHER APPLICABLE CITY, COUNTY, STATE, AND FEDERAL CODES AND REGULATIONS IN EFFECT AT
THE DATE OF THE BID. CONFORM TO ANY CODES, RULES, REGULATIONS AND REQUIREMENTS
THAT THE PROJECT OWNER HAS.
3. PRIOR TO FABRICATION AND INSTALLATION THE CONTRACTOR SHALL COORDINATE THE
INSTALLATION OF ALL PLUMBING WORK WITH ALL OTHER TRADES INCLUDING BUT NOT LIMITED TO
THE MECHANICAL CONTRACTOR, ELECTRICAL CONTRACTOR, GENERAL CONTRACTOR, AND ANY
CONTRACTOR HIRED DIRECTLY BY THE OWNER. WHERE CONFLICTS MAY OCCUR, THEY SHALL BE
RESOLVED PRIOR TO INSTALLATION.
4. THE WORKING DRAWINGS ARE DIAGRAMMATIC. BECAUSE OF THE SMALL SCALE OF THE
DRAWINGS, THEY DO NOT SHOW EVERY OFFSET, BEND OR ELBOW NECESSARY FOR THE
COMPLETE INSTALLATION IN THE SPACE PROVIDED. ALL LOCATIONS FOR PLUMBING EQUIPMENT
AND PIPING SHALL BE CHECKED AND COORDINATED WITH THE ARCHITECTURAL, MECHANICAL,
STRUCTURAL AND ELECTRICAL DRAWINGS.
5. ALL EQUIPMENT SHALL BE INSTALLED IN STRICT ACCORDANCE WITH THE EQUIPMENT
MANUFACTURER'S RECOMMENDATIONS. PROVIDE ALL FITTINGS, TRANSITIONS, VALVES, AND
OTHER DEVICES AND ACCESSORIES REQUIRED FOR A COMPLETE, WORKABLE INSTALLATION.
6. PENETRATIONS THRU FIRE RATED ASSEMBLIES SHALL COMPLY WITH THE LATEST ACCEPTED
VERSION OF THE IBC. COORDINATE WITH ARCHITECTURAL PLANS.
7. PROVIDE PROPER PROVISIONS FOR EXPANSION OR MOVEMENT OF ALL PIPING.
8. PROVIDE WATER HAMMER ARRESTORS (SHOCK ABSORBERS) AT ALL PIPE LOCATIONS WHERE
VALVE CLOSURES (SUCH AS FLUSH VALVES) MAY CAUSE WATER HAMMER OR RESULT IN
EXCESSIVE PIPE VIBRATION OR MOVEMENT.
9. PROVIDE ALL CLEANOUTS AS REQUIRED BY CODE, INCLUDING BUT NO LIMITED TO ALL SINKS, URINALS AND END OF RUNS.
ABBR
STANDARD ABBREVIATIONS
DESCRIPTION ABBR DESCRIPTION
A/E ARCHITECT/ENGINEER
AAV AUTOMATIC AIR VENT
ACH AIR CHANGES PER HOUR
AD ACCESS DOOR
AFF ABOVE FINISHED FLOOR
AHU AIR HANDLING UNIT
AP ACCESS PANEL
APD AIR PRESSURE DROP
ARCH ARCHITECT/ARCHITECTURAL
ASME AMERICAN SOCIETY OF MECHANICAL
ENGINEERS
BAS BUILDING AUTOMATION SYSTEM
BD BACKDRAFT DAMPER
BFP BACK FLOW PREVENTER
BG BELOW GROUND
BHP BRAKE HORSEPOWER
BLDG BUILDING
BOD BOTTOM OF DUCT
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNITS PER HOUR
CAP CAPACITY
CC COOLING COIL
CFM CUBIC FEET PER MINUTE
CI CAST IRON
CLG CEILING
CMU CONCRETE MASONRY UNIT
CO CLEANOUT
CONC CONCRETE
COND CONDENSER
CONN CONNECT/CONNECTION
CONST CONSTRUCTION
CONT CONTINUATION
COP COEFFICIENT OF PERFORMANCE
CW COLD WATER
CWR CHILLED WATER RETURN
CWS CHILLED WATER SUPPLY
DB DECIBEL or DRY BULB
DDC DIRECT DIGITAL CONTROL
DEMO DEMOLISH
DIA/Ø DIAMETER
DIM DIMENSION
DN DOWN
DWG DRAWING
EA EXHAUST AIR
EAT ENTERING AIR TEMPERATURE
EC ELECTRICAL CONTRACTOR
EDB ENTERING DRY BULB
EER ENERGY EFFICIENCY RATIO
EF EXHAUST FAN
EFF EFFICIENCY
EG EXHAUST GRILLE
ELEC ELECTRIC/ELECTRIAL
EL ELEVATION
EMCS ENERGY MANAGEMENT CONTROL
SYSTEM
ENCL ENCLOSURE
EQUIP EQUIPMENT
ESP EXTERNAL STATIC PRESSURE
EWB ENTERING WET BULB
EWT ENTERING WATER TEMPERATURE
EXH EXHAUST
F FAHRENHEIT
FCO FLOOR CLEANOUT
FD FLOOR DRAIN or FIRE DAMPER
FDC FIRE DEPARTMENT CONNECTION
FF FINAL FILTER
FLA FULL LOAD AMPS
FLR FLOOR
FP FIRE PROTECTION
FPM FEET PER MINUTE
FPI FINS PER INCH
FPS FEET PER SECOND
FS FLOOR SINK
FSD FIRE-SMOKE DAMPER
FT FEET or FLASH TANK
FV FACE VELOCITY
GA GAGE or GAUGE
GAL GALLONS
GALV GALVANIZED STEEL
GC GENERAL CONTRACTOR
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
HB HOSE BIBB
HC HEATING COIL
HEPA HIGH EFFICIENCY PARTICULATE AIR
HG HOT GAS
HP HORSEPOWER
HR HOUR
HTG HEATING
HVAC HEATING, VENTILATION, AND AIR
CONDITIONING
HW HOT WATER
HWC HOT WATER CIRCULATION
HX HEAT EXCHANGER
HZ HERTZ
IBC INTERNATIONAL BUILDING CODE
ID INSIDE DIAMETER
IE INVERT ELEVATION
IEEC INTERNATIONAL ENERGY
EFFICIENCY CODE
IFC INTERNATIONAL FIRE CODE
IMC INTERNATIONAL MECHANICAL CODE
IN INCHES
INSUL INSULATION
KW KILOWATT
KWH KILOWATT HOUR
LAT LEAVING AIR TEMPERATURE
LBS POUNDS
LDB LEAVING DRY BULB
LWB LEAVING WET BULB
LWT LEAVING WATER TEMPERATURE
MAV MANUAL AIR VENT
MAX MAXIMUM
MBH THOUSAND BTU PER HOUR
MCA MINIMUM CIRCUIT AMPS
MC MECHANICAL CONTRACTOR
MCC MOTOR CONTROL CENTER
MECH MECHANICAL
MFR MANUFACTURER
MIN MINIMUM or MINUTES
MISC MISCELLANEOUS
MOCP MAXIMUM OVER CURRENT
PROTECTION
NA NOT APPLICABLE
NC NORMALLY CLOSED or NOISE
CRITERIA
NIC NOT IN CONTRACT
NO NORMALLY OPEN
NPT NATIONAL PIPE THREAD
NTS NOT TO SCALE
OBD OPPOSED BLADE DAMPER
OC ON CENTER
OD OUTSIDE DIAMETER
ORD OVERFLOW ROOF DRAINAGE
OA or OSA OUTSIDE (SUPPLY) AIR
PD PRESSURE DROP
PGW PROPYLENE GLYCOL
PH/Ø PHASE
PLBG PLUMBING
POC POINT OF CONNECTION
PRV PRESSURE REDUCING VALVE
PSI POUNDS PER SQUARE INCH
PSIG POUNDS PER SQUARE INCH GAGE
PT PRESSURE TEMPERATURE
RA RETURN AIR
REQD REQUIRED
REV REVISION(S)
RO REVERSE OSMOSIS
BFP REDUCED PRESSURE BACKFLOW
PREVENTER
RPM REVOLUTIONS PER MINUTE
SA SUPPLY AIR
SD SMOKE DETECTOR or SMOKE
DAMPER
SEER SEASONAL ENERGY EFFICIENCY
RATIO
SENS SENSIBLE
SF SUPPLY FAN or SQUARE FEET
SIM SIMILAR
SM SHEET METAL
SMACNA SHEET METAL AND AIR
CONDITIONING CONTRACTORS
NATIONAL ASSOCIATION
SP STATIC PRESSURE
SPEC SPECIFICATION or SPECIFIED
SQ SQUARE
SQ FT SQUARE FEET
SS STAINLESS STEEL
STD STANDARD
TAB TEST, ADJUSTMENT & BALANCE
TC TEMPERATURE CONTROLS
TEMP TEMPERATURE
TP TRAP PRIMER or TEST PLUG
TSP TOTAL STATIC PRESSURE
TSTAT THERMOSTAT
TU TERMINAL UNIT
TYP TYPICAL
UNO UNLESS NOTED OTHERWISE
UPC UNIFORM PLUMBING CODE
V VENTS OR VOLTS
VAC VACUUM or VOLTAGE ALTERNATING
CURRENT
VAV VARIABLE AIR VOLUME
VD VOLUME DAMPER
VEL VELOCITY
VFD VARIABLE FREQUENCY DRIVE
VTR VENT THRU ROOF
WB WET BULB
WC WATER CLOSET
WCO WALL CLEANOUT
WH WATER HEATER
WHA WATER HAMMER ARRESTOR
W/ WITH
W/O WITHOUT
ZVB ZONE VALVE BOX
PIPING LEGEND
SYMBOL ABBR DESCRIPTION SYMBOL ABBR DESCRIPTION
SANITARY WASTE - ABOVE GROUND
SANITARY WASTE - BELOW GROUND
VENT
ACID WASTE
ACID VENT
RAINWATER DRAINAGE
RAINWATER DRAINAGE OVERFLOW
MEDIUM PRESSURE STEAM SUPPLY (20 PSIG)
MEDIUM PRESSURE STEAM CONDENSATE RETURN
HIGH PRESSURE STEAM SUPPLY (100 PSIG)
HIGH PRESSURE STEAM CONDENSATE RETURN
AW
AV
RD
ORD
D
IRR
DI
CS
CR
CHWS
CHWR
RL
RS
HG
RHWS
RHWR
FOS
FOR
G
LPG
LPS
LPR
MPS
MPR
HPS
HPR
PC
MA
MV
O
N2
CO2
A
VAC
WAGD
N2O
WASTE ANESTHESIA GAS DISPOSAL
VACUUM
COMPRESSED AIR
CARBON DIOXIDE
NITROGEN
NITROUS OXIDE
OXYGEN
MEDICAL VACUUM
COMPRESSED MEDICAL AIR
PUMPED CONDENSATE RETURN
LOW PRESSURE STEAM CONDENSATE RETURN
LOW PRESSURE STEAM SUPPLY (<15 PSIG)
LIQUID PETROLEUM GAS
NATURAL GAS
FUEL OIL RETURN
FUEL OIL SUPPLY
RE HEAT WATER RETURN
RE HEAT WATER SUPPLY
HOT GAS LINE - REFRIGERANT
REFRIGERANT SUCTION
REFRIGERANT LIQUID
CHILLED WATER RETURN
CHILLED WATER SUPPLY
CONDENSER WATER RETURN
CONDENSER WATER SUPPLY
DEIONIZED WATER
IRRIGATION WATER
DRAIN - INDIRECT
DOMESTIC HOT WATER RETURN
DOMESTIC HOT WATER
DOMESTIC COLD WATER
V
W
W
AW
AV
RD
ORD
D
IRR
DI
CS
CR
CHWS
CHWR
RL
RS
HG
RHWS
RHWR
FOS
FOR
G
LPG
LPS
LPR
MPS
MPR
HPS
HPR
PC
MA
MV
O
N2
CO2
A
VAC
WAGD
N2O
V
W
W
HWR
HW
CW
TP TP TRAP PRIMER LINE
RO REVERSE OSMOSIS WATERRO
F FIRE PROTECTIONF
FLEXIBLE CONNECTOR
PUMP
MANUAL AIR VENT
AUTOMATIC AIR VENT
PRESSURE GAUGE
THERMOMETER
WATER HAMMER ARRESTOR
PRESSURE/TEMPERATURE TEST PLUG
FLANGES
UNION
AUTOMATIC FLOW CONTROL VALVE
SOLENOID VALVE (TWO-POSITION W/ACTUATOR)
OUTSIDE SCREW AND YOKE VALVE
GLOBE VALVE
Y-TYPE STRAINER
FLOW MEASUREMENT VALVE
PRESSURE RELIEF VALVE
PRESSURE REDUCING VALVE
3-WAY CONTROL VALVE (PNEUMATIC)
2-WAY CONTROL VALVE (PNEUMATIC)
MANUAL BALANCING VALVE W/ FLOW
MEASUREMENT
BUTTERFLY VALVE
CHECK VALVE
BALL VALVE
SHUTOFF VALVE (AS SPECIFIED FOR SYSTEM)
ROOF DRAIN
OVERFLOW ROOF DRAIN
FLOOR SINK
FLOOR DRAIN
AREA DRAIN
FIRE DEPARTMENT CONNECTION
CLEANOUT/WALL CLEANOUT
HOSE BIBB/WALL HYDRANT
PIPE SLEEVE or ALIGNMENT GUIDES
PIPE ANCHOR
PIPE CONNECTION
CONCENTRIC REDUCER (NOT TYPICALLY SHOWN)
TEE DOWN
PIPE TURNING UP OR TOWARD
PIPE TURNING DOWN OR AWAY
PIPE END CAP
AAV
WHA
PT
OSY VA
GLV
FMS
PRV
BFV
CKV
BV
RD
ORD
FS
FD
AD
FDC
CO/WCO
HB
TEE UP
ECCENTRIC REDUCER (NOT TYPICALLY SHOWN)
PIPE EXPANSION JOINT
FLOOR CLEANOUTFCO
CLEANOUT TO GRADECOG
PIPE FLOW DIRECTION
PIPE SLOPE DIRECTION
3-WAY MOTORIZED VALVE
2-WAY MOTORIZED VALVE
Y-TYPE STRAINER W/ BLOWDOWN VALVE
PLUG VALVEPV
QUICK DISCONNECT
THERMOWELL
REDUCED PRESSURE BACKFLOW PREVENTERRPBP
DRAIN VALVE W/ HOSE THREAD
EMERGENCY EYEWASH/SHOWER
EMERGENCY EYEWASH
MAV
MEDICAL GAS OUTLET IDENTIFICATION
(REFER TO SCHEDULE)
MEDICAL GAS ZONE VALVE STATION
MOUNTED IN WALL
MEDICAL GAS ALARM PANEL MOUNTED IN WALL
MEDICAL GAS OUTLET
TEMPERED WATERTW TW
GREASE WASTE - BELOW GROUNDGW GW
STEAM TRAP
METER
DIFFERENTIAL PRESSURE MONITOR
SYMBOL DESCRIPTION SYMBOL DESCRIPTION
AIR DISTRIBUTION LEGEND
18"x12"
18"x12"18"x10"
18"/12"
18"x10"
18"Ø
D
18"Ø
D
R R
18"x12" 18"x12"
1S-CFM
DUCT SIZE IN INCHES FIRST SIZE
LISTED IS SIDE SHOWN
DUCT OFFSET (UP) IN DIRECTION OF
ARROW (NOT TYPICALLY SHOWN)
DUCT OFFSET (DN) IN DIRECTION OF
ARROW (NOT TYPICALLY SHOWN)
CHANGE OF DUCT SIZE
(TRIANGLE NOT ALWAYS SHOWN)
RECTANGULAR SUPPLY DUCT
ELBOW TURNED DOWN OR AWAY
RECTANGULAR RETURN/EXHAUST DUCT
ELBOW TURNED UP
RECTANGULAR RETURN/EXHAUST DUCT
ELBOW TURNED DOWN OR AWAY
SMALL RECTANGULAR DUCT ELBOW
TURNED DOWN OR AWAY
END OF DUCT WITH CAP
(UNLESS INDICATED OTHERWISE)
RECTANGULAR ELBOW WITH TURNING
VANES (SINGLE LINE)
BRANCH DUCT TAKE-OFF (SINGLE LINE)
GRILLE, REGISTER OR OPEN DUCT
(SUPPLY SHOWN)
TAG FOR GRILLE, REGISTER OR DIFFUSER.
REFER TO GRD SCHEDULE.
LINEAR SLOT DIFFUSER. REFER TO DIFFUSER AND
GRILLE SCHEDULE FOR ADDITIONAL INFORMATION.
CEILING SUPPLY DIFFUSER. REFER TO GRD
SCHEDULE
HYDRONIC HEATING OR COOLING COIL. REFER TO
DRAWING NOTES AND/OR SCHEDULE FOR CAPACITY.
MODULATING OPPOSED BLADE DAMPER
BACKDRAFT DAMPER
FIRE/SMOKE DAMPER
FIRE DAMPER
VOLUME DAMPER
RADIUS ELBOW (SINGLE LINE)
DUCT ACCESS DOOR
FLEXIBLE DUCT
ROUND DUCT ELBOW TURNED DOWN
OR AWAY
ROUND DUCT ELBOW TURNED UP
RECTANGULAR SUPPLY DUCT ELBOW
TURNED UP
CHANGE OF DUCT SIZE
OVAL DUCT IN INCHES
ROUND DUCT IN INCHES
ACOUSTIC LINED DUCT
BDD
MD
FSD
FDPR
VD
INDICATES RETURN or EXHAUST AIR FLOW
DIRECTION
INDICATES SUPPLY AIR FLOW DIRECTION
DUCT SMOKE DETECTOR
LOW LIMIT THERMOSTATLLT
DSD
MTD MOTORIZED DAMPER
SD SMOKE DAMPER
CEILING GRILLE (RETURN OR TRANSFER)
REFER TO GRD SCHEDULE
CEILING EXHAUST GRILLE (RETURN OR TRANSER)
REFER TO GRD SCHEDULE
18"/12"
RECTANGULAR EXHAUST DUCT TURNED UP
RECTANGULAR EXHAUST DUCT TURNED DOWN
RECTANGULAR OUTSIDE AIR DUCT TURNED UP
RECTANGULAR OUTSIDE AIR DUCT TURNED DOWN
SHEET INDEX
M-001 MECHANICAL GENERAL NOTES AND LEGENDS
M-002 MECHANICAL SCHEDULES
M-100 MECHANICAL HVAC ZONE PLAN
MD-101 MECHANICAL HVAC FLOOR PLAN - DEMO
MD-102 MECHANICAL HVAC INTERSTITIAL FLOOR PLAN - DEMO
M-101 MECHANICAL HVAC FLOOR PLAN
M-102 MECHANICAL HVAC INTERSTITIAL FLOOR PLAN
M-201 MECHANICAL PIPING PLAN
M-301 MECHANICAL HVAC SECTIONS
M-501 MECHANICAL DETAILS
M-502 MECHANICAL DETAILS
M-611 MECHANICAL DIAGRAMS
M-701 MECHANICAL CONTROL DIAGRAMS
PD-101 3RD FLOOR INTERSTITIAL PLUMBING PLAN - DEMO
PD-102 4TH FLOOR PLUMBING PLAN - DEMO
PD-103 4TH FLOOR MEDGAS PLAN - DEMO
P-101 3RD FLOOR INTERSTITIAL PLUMBING PLAN
P-102 4TH FLOOR PLUMBING PLAN
P-501 PLUMBING AND MEDGAS DETAILS
P-601 PLUMBING RISER DIAGRAMS
PG-103 4TH FLOOR MEDGAS PLAN
PG-104 MECHANICAL HVAC ROOF PLAN
SD
H
T
AHU-1
P1-1
GENERAL LEGEND
SYMBOL DESCRIPTION
THIN LINEWORK INDICATES EXISTING
MEDIUM LINEWORK INDICATES NEW
THERMOSTAT OR TEMPERATURE SENSOR (WALL MOUNTED)
HUMIDISTAT OR HUMIDITY SENSOR (WALL MOUNTED)
DETAIL SYMBOL: A = IDENTIFYING NUMBER
B = SHEET WHERE DETAIL IS SHOWN
SECTION SYMBOL: A = IDENTIFYING LETTER
B = SHEET WHERE SECTION IS SHOWN
SECTION CUT LINE INDICATOR
THICK DASHED LINEWORK INDICATES
EXISTING TO BE DEMOLISHED
KEYED REFERENCE NOTE SPECIFIC TO LOCATION INDICATED
POINT OF CONNECTION (POC)
PLUMBING FIXTURE TAG (REFER TO SCHEDULE)
MECHANICAL EQUIPMENT TAG (REFER TO SCHEDULES)
REVISION CLOUD AND REVISION NUMBER
SMOKE DETECTOR
GENERAL NOTE APPLIES TO ENTIRE SHEETX.
EXISTING(E)
NEW(N)
RELOCATE(REL)
NEW LOCATION(NL)
CO2 CO2 SENSOR
M-001
MECHANICAL GENERAL NOTES AND
LEGENDS
TAH MRN
MEDICAL GAS PRESSURE SENSOR
HWS
HWR HEATING WATER RETURN
HEATING WATER SUPPLYRWS
RWR
STAINLESS STEAL DUCT
DUCTWORK CONSTRUCTION AND LEAKAGE TESTING
SYSTEM
ROUND/ OVAL RECTANGULAR
REMARKSPRESS. CLASS (IN
WC)
DUCT SEAL
CLASS
PRESS. CLASS (IN
WC)
DUCT SEAL
CLASS
OA INTAKE FROM
LOUVER TO AHU 3-4 A 3-4 A
SUPPLY DUCT FROM
AHU TO TU 3-4 A 3-4 A
SUPPLY DUCT
DOWNSTREAM FROM TU 2 A 2 A
GENERAL EXHAUST
DUCT UPSTREAM OF
ETU
2 A 2 A
GENERAL EXHAUST
DUCT FROM ETU TO FAN 2-3 A 2-3 A
GENERAL EXHAUST
DUCT FROM FAN TO
LOUVER
2-3 A 2-3 A
1. NOT USED.
2. NOT USED.
E
D
C
B
A
VA FORM
OFFICE OF
CONSTRUCTION AND
FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 10
ARCHITECT OF RECORD
APPROVED PROJECT DIRECTOR
PROJECT PHASE
BUILDING CONSTRUCTION
PROJECT NUMBER
BUILDING NUMBER
DRAWING NUMBER
08 - 6231
REVISIONS: DATE:NO.
664-CSI-116
BLDG #1
QUALITY CONSTRUCTIONMICHAEL DEGNAN - VA DESIGN PROJECT MANAGER
www.coffman.com ph 619.232.4673
1455 Frazee Rd., Suite 600 San Diego, CA 92108 ph 619.232.46736/11/2019
7/16/2019 8/23/2019
12/24/2020
35% SCHEMATIC DESIGN
35% SCHEMATIC DESIGN- RESUBMITTAL
65% DESIGN DEVELOPMENT
REVISED 65% DESIGN DEVELOPMENT
100% CONSTRUCTION DOCUMENTS
02/18/2021 95% CONSTRUCTION DOCUMENTS
04/09/2021 100% CONSTRUCTION DOCUMENTS
PROJECT TITLE
PROJECT LOCATION
ISSUE DATE CHECK BY DRAWN BY
VA MEDICAL CENTER SAN DIEGO, 3350 LA JOLLA
VILLAGE DR., SAN DIEGO, CA 92161
MAY 10, 2021
REVIEWED IN
ACCORDANCE WITH THE
REQUIRMENTS OF CFM
BY:___________________
DATE:________________
U.S. DEPARTMENT OF
VETERANS AFFAIRS
ENGINEERING SERVICES
05/10/2021 IFC DOCUMENTS 4TH FLOOR 4N CARDIOLOGY CATH LAB 2
M-002
MECHANICAL SCHEDULES
TAH MRN
SHEET NOTES
1. BASIS OF DESIGN EQUIPMENT ARE SHOWN IN SCHEDULES. APPROVED EQUALS MAY
ALSO BE CONSIDERED, IF CONSTRUCTION MATERIALS, QUALITY, AND PERFORMANCE
MEET OR EXCEED THE BASIS OF DESIGN EQUIPMENT CHARACTERISTICS, AS PROVIDED
IN THE MANUFACTURERS LITERATURE AND THE PROJECT SPECIFICATIONS, AND IF
DIMENSIONAL CONSTRAINTS ARE ALSO MET.
EQUIPMENT HEAT GAIN CALCULATION
QUANTITY EQUIPMENT HEAT OUTPUT (BTUH) TOTAL HEAT OUTPUT
(BTUH)
CATH LAB
1 GANTRY 5,528 5,528
1 TILTING TABLE 614 614
1 DISPLAY ON BOOM 1,706 1,706
TOTAL CATH LAB HEAT LOAD 7,848
CONTROL ROOM
1 ADVANTAGE WORKSTATION 2,019 2,019
1 OPERATOR CONSOLE 341 341
2 CHATWORTH CABINETS - -
TOTAL CONTROL ROOM LOAD 2,360
EQUIPMENT ROOM
1 C-FRT CABINET 2,388 2,388
1 SYSTEMS INTERFACE CABINET 1,365 1,365
1 DETECTOR CONDITIONER 717 717
1 COOLIX WATER CHILLER 23,646 23,646
1 MAIN DISCONNECT PANEL 205 205
1 20kVA FLUORO UPS UL 6,756 6,756
TOTAL EQUIPMENT ROOM HEAT LOAD 35,077
PER GE HEALTHCARE DESIGN DOCUMENTS DATED 12/08/2020
WATER SOFTENER SCHEDULE
TAG MANUFACTURER/ MODEL SERVES EXCHANGE MEDIA
(FT^3)
EXCHANGE CAPACITY SALT STORAGE CAPACITY
(LBS)
UNIT POWER REQUIREMENTS
REMARKS
VOLTS Ø WATTS
WS-01 CULLIGAN/
HE-9 HU-401 1.0 27,100 GRAINS @ 8 LBS 375 24 1 35 1,2,3
1. TOTAL HARDNESS MAXIMUM 75GPG. CONFIRM WITH VA THAT CURRENT WATER HARDNESS TEST AT FACILITY IS EQUAL TO OR BELOW LISTED MAX. HARDNESS.
2. RATED SERVICE FLOW AT 15PSI IS 10.8 GPM.
3. PROVIDED WATER SOFTENER TANK TO FEATURE QUAD HULL LEAK PROTECTION.
SOUND DATA
OCTAVE BAND
INLET OUTLET
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8
FREQ. HZ 63 125 250 500 1K 2K 4K 8K 63 125 250 500 1K 2K 4K 8K
AHU-401 79 76 82 92 83 80 79 82 83 79 79 82 83 77 73 67
GX-401 72 75 79 75 73 70 65 58 72 71 69 63 59 56 50 43
1. SOUND DATA PROVIDED FOR BASIS-OF-DESIGN EQUIPMENT LISTED ON VARIOUS EQUIPMENT SCHEDULES.
LOUVER SCHEDULE
TAG SERVES MANUFACTURER/ MODEL MATERIAL AIRFLOW
(CFM)
LOUVER
SIZE, WxH
(IN)
FACE
AREA (SF)
FACE
VELOCITY
(FPM)
FREE
AREA (SF)
FREE AREA
VELOCITY (FPM)
APD
(IN WC)
DRAINABLE
BLADE (YES/NO)
BLADE
ANGLE
(DEG)
FRAME
DEPTH (IN)
WEIGHT
(LBS)
REMARKS
LV-401A AHU-401 INTAKE GREENHECK/
FDS-602
STAINLESS
STEEL 6,500 36 x 69 17.25 377 9.11 714 0.08 YES 35 6 89 1,2
LV-401B AHU-401 INTAKE AAF/
AMERVANE VI
STAINLESS
STEEL 6,500 50 x 50 17.36 374 - - 0.25 - - 8 3,4
LV-402 GX-401 EXHAUST GREENHECK/
ESD-635 ALUMINUM 6,500 36 x 69 17.25 377 9.11 714 0.08 YES 35 6 89 1,2
1. PROVIDE W/ INTERNAL BIRD SCREEN, SAME MATERIAL AS LOUVER.
2. 70% KYNAR FINISH TO MATCH SURROUNDING FACILITY COLOR. CONFIRM FRAME TYPE WITH ARCHITECTURAL SCOPE PRIOR TO ORDERING LOUVER.
3. MIST ELIMINATOR WITH STATIONARY S-HOOK BLADES. SEE FILTER SCHEDULE FOR COALESCING PAD MOUNTED DIRECTLY BEHIND MIST ELIMINATOR.
4. MIST ELIMINATOR PROVIDED WITH 1-1/2" DRAIN CONNECTION. PIPE TO AHU CONDENSATE DRAIN PIPE.
VARIABLE FREQUENCY DRIVE SCHEDULE
TAG LOCATION SERVES MANUFACTURER/ MODEL
MOTOR ELECTRICAL REQUIREMENTS
BYPASS DISCONNECT AND
FUSES NEMA ENCLOSURE INPUT LINE
REACTOR OUTPUT LC FILTER
HP VOLTS Ø EMERG.
VFD-1 AHU-401 AHU SUPPLY FAN ABB/
ACH 580 5 460 3 YES NO YES NEMA 1 YES IF MOTOR LEAD LENGTH EXCEED 25 FT.
VFD-2 AHU-401 AHU SUPPLY FAN ABB/
ACH 580 5 460 3 YES NO YES NEMA 1 YES IF MOTOR LEAD LENGTH EXCEED 25 FT.
VFD-3 GX-401 GX-401 ABB/
ACH 580 5 460 3 YES YES YES NEMA 1 YES IF MOTOR LEAD LENGTH EXCEED 25 FT.
DAMPER SCHEDULE
TAG LOCATION SERVES MANUFACTURER/ MODEL TYPE WIDTH (IN) HEIGHT
(IN)
FLOW
(CFM)
APD
(IN WC)
FIRE RATING LEAKAGE
CLASS
CLOSE
TEMP BLADE STACK
UNIT POWER REQUIREMENTS
REMARKS
VOLTS Ø FLA
CD-402 LV-402 GX-401 EXHAUST
AIR
GREENHECK/
VCD-23 LOW-LEAKAGE CONTROL 30 22 6,000 0.05 - 1A - PARALLEL BLADE 120 1 1
1. FAIL CLOSED. PROVIDE WITH END SWITCH TO CONFIRM STATUS FOR CONTROLS.
PLUMBING FIXTURES
TAG TYPE MANUFACTURER
TRIM
TRAP
BRANCH CONNECTIONS
REMARKSFIXTURE TRIM SUPPLIES WASTE VENT CW HW
P-103 WATER CLOSET KOHLER K-4325 OPEN FRONT SEAT, LESS COVER SLOAN ROYAL 111-ESS-1.28 P-TRAP 4" 2" 1" - 1,2,3
P-418 LAVATORY KOHLER K-2032 SLOAN OPTIMA ETF-700-4-BOX-BDT-CP-0.5GPM-LAM-IR-S-FCT GRID DRAIN P-TRAP 2" 1-1/2" 1/2" 1/2" 2,4,5,6
P-520 SCRUB SINK ELKAY EWS25201 SLOAN OPTIMA ETF-500-BOX-CP-2.2GPM-LAM-IR-S-FCT GRID DRAIN P-TRAP 3" 1-1/2" 1/2" 1/2" 5,7
P-704 SHOWER EVERFAB S6336A3 SYMMONS SAFETYMIX 1-25-FSB-2.0-X KOHLER K-9232 DRAIN P-TRAP 2" 2" 1/2" 1/2" 8
FD-1 FLOOR DRAIN SMITH 2005Y02-A05NB TRAP PRIMER - P-050 - P-TRAP 2" 2" 1/2" - 9
1. PROVIDE & INSTALL WATER HAMMER ARRESTOR ON CW LINE (AND HW IF APPLICABLE) SERVING FIXTURE, SEE PLAN FOR SIZE.
2. PROVIDE AND INSTALL SUPPORT CARRIER; SEE ARCHITECTURAL FOR MOUNTING HEIGHT.
3. FLUSH VALVES SHALL BE PROGRAMED TO FLUSH EVERY 72 HOURS. FLUSH VALVES TO HAVE OVERRIDE BUTTON AND BE HARD WIRED. PROVIDE WITH MODEL 3L-154 120V/24V 50VA TRANSFORMER.
4. OFFSET EXPOSED TRAPS FOR ADA COMPLIANCE. INSULATE ALL EXPOSED PIPING (CW, HW, & SAN) BELOW SINK WITH TRUEBRO MODEL 102 & 105 HANDI LAV-GUARD KIT.
5. PROVIDE AND INSTALL SYMMONS MODEL 7-210-CK MIXING VALVE ON HOT WATER SERVING FIXTURE, SET TO 110°F.
6. WHITE VITREOOUS CHINA LAVATORY WALL MOUNT. SENSOR FAUCET, 0.5 GPM LAMINAR SPRAY, SINGLE HOLE MOUNTING, HARD-WIRED 24 VAC POWER CONNECTION WITH BATTERY BACKUP, PROVIDE WITH 120V/24VAC TRANSFOREMER.
7. WALL HUNG 14 GAUGE 304 STAINLESS STEEL SINK WITH GOOSENECK SPOUT WITH SENSOR 2.2 GPM LAMINAR FLOW, HARD-WIRED 24 VAC POWER CONNECTION WITH BATTERY BACKUP, PROVIDE WITH 120V/24VAC TRANSFORMER.
8. ONE-PIECE SHOWER STALL WITH SMOOTH WALLS. PROVIDE AND INSTALL PRESSURE BALANCING VALVE SYMMONS 4-500-X WITH INTEGRAL STOPS, 30" SLIDE BAR WITH 60" HOSE, SHOWER HANDLE WITH 2.0 GPM, AND ADA GRAB BARS.
9. PROVIDE AND INSTALL PRECISION PLUMBING PRODUCTS, INC. MODEL P1/P2 TRAP PRIMER. ROUTE 1/2" PIPING FROM TRAP PRIMER TO DRAIN. PROVIDE AND INSTALL ACCESS PANEL FOR TRAP PRIMER.
HUMIDIFIER SCHEDULE
TAG LOCATION SERVES MANUFACTURER/ MODEL TYPE REQUIRED
OUTPUT (LB/HR)
RATED POWER
(kW)
UNIT POWER REQUIREMENTS CONNECTIONS (IN)
OP WT.
(LBS)
REMARKS
CW IN DRAIN OUT STEAM
OUTVOLTS Ø MCA/ MOCP
HU-401 4TH FLOOR
INTERSTITIAL AHU-401 CONDAIR/
EL 150/440-480/3
ELECTRIC STEAM
GEN. 151 56.1 480 3 67.5/
90 2x 0.5 2x 1.18 2x 1.75 245 1,2,3
1. DISPERSION GRID INTERNAL TO AHU-401.
2. UNIT SHALL ACCEPT 0-10V CONTROL INPUT.
3. PROVIDE WITH IN-LINE WATER FILTER (5 MICRON) AND CONDENSATE COOLER ACCESSORY.
FAN SCHEDULE
TAG SERVES MANUFACTURER/ MODEL
DESCRIPTION FAN PERFORMANCE MOTOR ELECTRICAL
REQUIREMENTS UNIT WT.
(LBS)
REMARKS
TYPE DRIVE FLOW
(CFM)
ESP
(" WC)
SPEED
(RPM)
BHP
HP VOLTS Ø FLA
(E)
GX-37
EXISTING SPACES TRANE/
T-8 - V-BELT 4,500 1.25 2065 1.88 3 460 3 - - 2
(E)
GX-65
(E) CATH LAB
MCQUAY/
LYF108CH - - 4,230 0.75 1.05 2 460 3 - - 2
GX-401 (N) CATH LAB
GREENHECK/
QEI-22 MIXED FLOW BELT 6,850 1.75 1201 3.14 5 460 3 7.6 565 1,3,4
1. SEE VFD SCHEDULE FOR MOTOR VFD INFORMATION, UNIT WILL MODULATE SPEED TO MEET TU DEMAND.
2. EXISTING FAN. FLOW RATE SHOWN IS ORIGINAL DESIGN AIRFLOW. CURRENT AIRFLOW WILL BE DETERMINED BY CONTRACTOR TAB PRE-READS PRIOR TO CONSTRUCTION. FAN REBALANCING MAY BE REQUIRED AFTER
ENGINEER OF RECORD REVIEW OF PRE-READ TAB REPORT.
3. FAN MUST BE OSHPD SEISMIC CERTIFIED.
4. PROVIDE FAN WITH FACTORY MOUNTED ISOLATION BASE, INLET AND OUTLET COMPANION FLANGES.
SEISMIC AND VIBRATION CONTROL SEISMIC RESTRAINT PROVISIONS
TAG EQUIPMENT LEVEL RESTRAINTS BASE
VIBRATION
ISOLATOR
TYPE(S)
FLEXIBLE CONNECTORS DEFLECTION (IN)
SEISMIC SUPPORTS ARE REQUIRED FOR THIS PROJECT FOR ALL MECHANICAL AND ELECTRICAL EQUIPMENT AND DISTRIBUTION SYSTEMS. SEISMIC RESTRAINT CALCULATIONS MUST BE PROVIDED BY THE PRODUCT MANUFACTURER FOR ALL CONNECTIONS OF EQUIPMENT TO THE STRUCTURE. ALL RESTRAINING DEVICES SHALL HAVE TESTING DATA TO VALIDATE MAXIMUM RESTRAINT RATINGS. PREAPPROVALS BASED ON INDEPENDENT TESTING ARE PREFERRED TO PREAPPROVALS BASED ON CALCULATIONS.
CALCULATIONS (INCLUDING THE COMBINING OF TENSILE AND SHEAR LOADING) TO SUPPORT SEISMIC RESTRAINT DESIGNS MUST BE STAMPED BY A REGISTERED PROFESSIONAL ENGINEER LICENSED IN CA. THE ENGINEERING ANALYSIS MUST INDICATE CALCULATED DEAD LOADS, STATIC SEISMIC LOADS, AND CAPACITY OF MATERIALS UTILIZED FOR CONNECTIONS TO EQUIPMENT STRUCTURE.
ANALYSIS MUST DETAIL ANCHORING METHODS, BOLT DIAMETER, EMBEDMENT, AND/OR WELDED LENGTH.
AHU-401 AIR HANDLING UNIT 4 AM B 4,5 Y 1.5
GX-401 MIXED FLOW GENERAL EXHAUST FAN 4 Y B 3,5 Y 1.5
FCU-01 FAN COIL UNIT 4 Y A 3,5 Y 1.5
WS-01 WATER SOFTENER 4 A NA NA N NA
HU-401 ELECTRIC STEAM-GEN HUMIDIFIER 4 A NA NA N NA ALL SEISMIC RESTRAINT DEVICES SHALL BE DESIGNED TO ACCEPT, WITHOUT FAILURE, THE FORCES PRESCRIBED PER THE ASCE 7-05 ACTING THROUGH THE EQUIPMENT CENTER OF GRAVITY. OVERTURNING MOMENTS MAY EXCEED FORCES AT GROUND LEVEL AND MAY BE RESISTED BY SEISMIC RESTRAINTS, SUPPORT, OR ANCHORAGE. ANCHORAGE TO CONCRETE MUST HAVE AN ICC TESTING REPORT THAT ADHERES TO THE REQUIREMENTS OF THE 2015 IBC AND MUST BE RATED FOR SEISMIC RESTRAINT IN CRACKED CONCRETE USING THE APPROPRIATE REDUCTION FACTORS PER ACI 318 APPENDIX D. ACCEPTABLE ANCHORS INCLUDE THE HILTI KWIK BOLT TZ AND SIMPSON STRONG BOLT WEDGE ANCHORS OR HILTI HIT-RE 500-SD AND SIMPSON SET XP EPOXY
ANCHORS. EPOXIES ARE NOT ACCEPTABLE FOR USE IN OVERHEAD APPLICATIONS.
MVP-1 WAGD MEDICAL VACUUM PUMP 6 A NA NA NA NA
6S SUPPLY PLENUM ARRAY 4 Y NA NA NA NA
WS-01 WATER SOFTNER 4 Y NA NA NA NA
TU TERMINAL UNITS 4 Y NA NA NA NA
ASCE 7-10 SEISMIC DESIGN CRITERIA
SEISMIC DESIGN CATEGORY "D"
OCCUPANCY CATEGORY IV
SITE CLASS "D"
SEISMIC IMPORTANCE FACTOR FOR BUILDING, I e = 1.5
SEISMIC IMPORTANCE FACTOR FOR COMPONENT, I P = 1.5
HEATING HOT WATER 4 Y NA (4) Y (6),(7) COMPONENT RESPONSE MODIFICATION AND AMPLIFICATION FACTORS REHEAT HOT WATER 4 Y NA (4) Y (6),(7) SHALL BE DETERMINED IN ACCORDANCE WITH ASCE 7-10, TABLE 13.6-1.
CHILLED WATER 4 Y NA (4) Y (6),(7) DESIGN SPECTRAL RESPONSE ACCELERATION AT SHORT PERIODS (0.2 SECOND):
DOMESTIC COLD 4 Y NA NA Y NA SDS = 0.818 G.
DOMESTIC HOT 4 Y NA NA Y NA DESIGN SPECTRAL RESPONSE ACCELERATION AT 1-SECOND PERIOD:
WASTE 3 Y NA NA NA NA SD1 = 0.476 G.
VENT 3,4 Y NA NA NA NA
MEDICAL GAS PIPING 4 Y NA NA NA NA
NOTES
RESTRAINTS BASE TYPE 1. CONCRETE PAD MASS TO EQUAL AT LEAST 75% OF EQUIPMENT
A = ANCHOR A = ISOLATOR ATTACHED TO EQUIPMENT DIRECTLY 2. NR=NOT REQUIRED, NA=NOT APPLICABLE AM = ANCHOR SPECIFIED BY EQUIPMENT MANUFACTURER B = STRUCTURAL STEEL RAILS OR BASE 3. PIPING TO BE BRACED LATERALLY A MINIMUM OF EVERY 40' AND LONGITUDINALLY EVERY 80' REGARDLESS OF SEISMIC
REQUIREMENTS.B = RESTRAINING BASE WITH SNUBBER C = CONCRETE INERTIA BASE
Y = REQUIRED PER SPECIFICATIONS 13 05 41 AND 23 05 41 D = CURB-MOUNTED BASE 4. SEE SPECIFICATION SECTION 23 05 41 FOR DESCRIPTION AND REQUIREMENTS OF BASES, ISOLATORS, AND RESTRAINTS.
ISOLATOR TYPE 5. ALL EQUIPMENT, PIPING, PLUMBING, AND MEDGAS PIPING SEISMIC RESTRAINTS TO BE DETERMIEND BY DELEGATED DESIGNER
PER SPECIFICATION 13 05 41.
1. PAD: RUBBER, GLASS FIBER 4. RESTRAINED SPRING ISOLATOR 6. TYPE 7 ISOLATORS WITH 0.75" DEFLECTION ARE REQUIRED IN MECHANICAL ROOMS AND ON RISERS.
2. RUBBER ISOLATOR, FLOOR OR HANGER 5. THRUST RESTRAINT 7. FIRST THREE HANGARS FROM EQUIPMENT SHOULD PROVIDE THE SAME DEFLECTION AS EQUIPMENT ISOLATORS.3. SPRING ISOLATOR, FLOOR OR HANGER 6. AIR SPRING
WASTE ANESTHESIA GAS DISPOSAL PUMP SCHEDULE
TAG LOCATION SYSTEM TYPE MANUFACTURER / MODEL PUMP TYPE RECEIVER (GAL) PRESSURE
(IN HG)
SCFM SOUND LEVEL dB(A)
MOTOR ELECTRICAL DATA
WEIGHT
(LBS)
REMARKS
HP VOLTS PHASE FLA
MVP-1 MECH. ROOM 7001 MEDICAL VACUUM BEACON MEDAES / VH02D-060H-D CLAW 60 19 16 70 2 460 3 3.4 1,629 1,2,3,4,5
1. OIL-LESS CLAW MEDICAL VACUUM PUMP; DUPLEX SYSTEM WITH SINGLE POINT CONNECTION.
2. UNIT SHALL OPERATE AFTER A SEISMIC EVENT. PROVIDE SEISMIC CERTIFICATION (TESTING OR ANALYSIS) IN ACCORDANCE WITH SECTION 13.2 OF ASCE 7.
3. VACUUM PUMP COMMISSIONING AND START UP SHALL BE PERFORMED BY EQUIPMENT MANUFACTURER.
4. BASIS OF DESIGN = BEACON MEDAES. APPROVED EQUALS MAY ALSO BE CONSIDERED.
5. PROVIDE UNIT WITH CALIFORNIA OSHPD SEISMIC CERTIFICATION.
GRILLES, REGISTERS, DIFFUSERS SCHEDULE
TAG TYPE MANUFACTURER/ MODEL MATERIAL GRILLE SIZE NECK SIZE PANEL SIZE GRD TYPE FINISH NOTES
1S SUPPLY PRICE/
AMCD ALUMINUM 8x8 8 - MODULAR
CORE WHITE 1,5
2S SUPPLY PRICE/
AMCD ALUMINUM 12x12 12 - MODULAR
CORE WHITE 1,5
3S SUPPLY PRICE/
SMCD STEEL 8x8 8 - MODULAR
CORE WHITE 1,5
4S SUPPLY PRICE/
SMCD STEEL 12x12 12 - MODULAR
CORE WHITE 1,5
5S SUPPLY PRICE/
SMCD STEEL 18x18 14 - MODULAR
CORE WHITE 1,5
6S SUPPLY PRICE/
HGPL STAINLESS - VARIES VARIES - 4
7S SUPPLY PRICE/ STEEL 8x8 8 - SINGLE
DEFLECT.
1E EXHAUST PRICE/
730 STAINLESS 20x16 20x16 - SINGLE
DEFLECT. WHITE 2,5
2E EXHAUST PRICE/
630 ALUMINUM 8x8 8 - SINGLE
DEFLECT. WHITE 3,5
3E EXHAUST PRICE/
530 STEEL 10x10 10 - SINGLE
DEFLECT. WHITE 3,5
4E EXHAUST PRICE/
530 STEEL 14x12 12 - SINGLE
DEFLECT. WHITE 3,5
5E EXHAUST PRICE/
530 STEEL 8x8 8 - SINGLE
DEFLECT. 3
1R RETURN PRICE/
80 STEEL 20x14 14 - EGG CRATE WHITE 3,5
1. PROVIDE WITH SQUARE-TO-ROUND TRANSITION ACCESSORY SIZED FOR NECK SIZE.
2. LOW EXHAUST GRILLES IN CATH LAB. INSTALLED 7" ABOVE FINISHED FLOOR. SINGLE-DEFLECTION, 45 DEGREE ANGLE.
3. TRANSITION TO ROUND DUCTWORK FIELD FABRICATED AND INSTALLED.
4. SIZE FOR 25-35 FPM FACE VELOCITY PER ASHRAE 170-2017.
5. CONFIRM GRD FRAME STYLE WITH VA PRIOR TO ORDERING. AIRFLOW DIRECTIONS TO MATCH PLANS.
FILTER SCHEDULE
TAG FILTER TYPE LOCATION SERVES MANUFACTURER/ MODEL FLOW (CFM) FILTER EFFICIENCY CLEAN PD (IN.
W.C.)
DIRTY PD (IN.
W.C.)
QTY DIMENSIONS
(WxHxD)
REMARKS
F-01 COALESCING PAD LV-401B AHU-401 OA INTAKE AAF/
AMERKOOL M81 6,850 - 0.1 0.25 4 25 x 25 x 3 4
F-02 MERV 8 PREFILTER INTERNAL
AHU-401 AHU-401 - 6,850 MERV 8 0.2 0.55 4 24 x 24 x 2 1,2,3
F-03 MERV 11 PREFILTER INTERNAL
AHU-401 AHU-401 - 6,850 MERV 11 0.2 0.55 4 24 x 24 x 4 1,2,3
F-04 HEPA FINAL FILTER INTERNAL
AHU-401 AHU-401 - 6,850 MERV 17
(HEPA)
1.0 1.5 4 24 x 24 x 12 1,2,3,5
F-05 FCU PANEL FILTER INTERNAL
FCU-01 FCU-01 - 1,450 MERV 8 0.1 1 2 24 x 24 x 2 1,2,3
1. MECHANICAL CONTRACTOR TO PROVIDE CLEAN FILTERS AFTER CONSTRUCTION IS COMPLETED.
2. MECHANICAL CONTRACTOR TO PROVIDE AN EXTRA SET OF FILTERS.
3. MECHANICAL CONTRACTOR TO INSTALL FILTERS PRIOR TO TEST AND BALANCE ONLY.
4. COALESCING PAD FILTER INSTALLED DIRECTLY BEHIND (DOWNSTREAM) MIST ELIMINATOR LOUVER.
5. HEPA FILTERS SHALL BE TESTED AT THE FACTORY PRIOR TO SHIPMENT TO JOBSITE VIA FACE SCANNING TEST.
AIR HANDLING…