Atch 1 STATEMENT OF WORK 664_CSI_116.pdf

PDF 349 KB Posted

Attached to
Z2DA--Cardiology Cath Lab II, Project 664-CSI-116
Solicitation number
36C26222B0003
Issued by

About this file

This statement of work outlines requirements for a construction services contract to renovate the 4th floor 4N Cardiology Cath Lab 2 at the VA Medical Center in San Diego, California. The project involves renovating an existing cath lab procedure room and associated support spaces, including asbestos abatement. The period of performance is 365 calendar days from notice to proceed. The contractor must follow specifications prepared by Davy Architecture and applicable construction standards. The estimated price range is between $2 million to $5 million. The Department of Veterans Affairs Veterans Health Administration VISN 22 will award the firm fixed price contract under solicitation number 36C26222B0003 to the lowest priced technically acceptable offeror.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Renovate 4th Floor 4N Cardiology Cath Lab 2 Project 664-CSI-116

Construction Services VA San Diego Health Care System (664)

B.1 INTRODUCTION:

This requirement is for Construction Services for Project 664-CSI-116 “Renovate 4th Floor 4N, Cardiology Cath Lab 2” at VA Medical Center, San Diego , CA 92161 in accordance with items specified herein. The contractor shall utilize the construction documents and specifications as prepared by Davy Architects. This requirement is classified under construction as it calls for the alteration of real property.

B.2 BACKGROUND / DESCRIPTION OF WORK:

A. The project will to renovate the existing Cath Lab 2 Procedure room (approx. 3,345 sf) with associated support spaces, including the abatement of asbestos containing material.

This project was designed through awarded government contract VA262-16-D-0152 to the AE firm Davy Architecture.

B.3 CONSTRUCTION DOCUMENTS:

Contractor shall furnish all labor, equipment, certification, supervision, and materials necessary to perform all operations in connection with this order. This requirement is classified under construction as it calls for the alteration of real property. Contractor shall perform work in strict accordance with the General Specifications, Statement of Work, Design, Schedule, and all other supporting documents for this contract to include, but not limited to, the following attachments:

1. Refer to SECTION D of Solicitation for attachments.

B.4 SPECIFICATIONS:

A. The VA Master Construction Specifications contain work procedures and material requirements designed to meet regulatory compliance requirements. Whenever possible, the Master Construction Specifications shall be used as the basis for project designs.

1. Refer to SECTION D of Solicitation for attachments.

B. A complete list of these specifications can be viewed at the following website:

http://www.cfm.va.gov. Specifications which address EOSH requirements include, but are not limited to:

1. Refer to SECTION D of Solicitation for attachments.

C. In the case of any differences, the specifications will govern over the drawings. Any discrepancies should be brought to the immediate attention of the Contracting Officer and COR for clarification. Any errors or omissions in the contract drawings or specifications must be provided promptly by the Contractor to the COR, but in no case later than the start of related work.

B.5 SPECIFIC REQUIREMENTS:

A. This project will demolish architectural finishes, plumbing, mechanical, electrical systems, and asbestos abatement, for Cath lab 2 SOW areas in accordance with the specifications and contract documents. Construct new flooring and ceilings, plumbing, mechanical, and electrical to support Government Furnished Cath Lab in accordance with contract documents.

B. This project was designed through government contract. The contractor shall provide constructions services in accordance with the attached specifications and construction documents as prepared by Davy Architects. Contract no contract VA262-16-D-0152.

C. This requirement will include but will not be limited to preparation and/or performance for, submittals, change orders, providing construction meeting minutes to the VA COR, phasing/scheduling, utility shut downs, infection control measures, and other related information and services.

D. The contractor shall renovate Cath Lab 2 in Building 1, 4 West in accordance with attached contract documents.

E. Due to COVID-19, all contractors shall comply with VHA Face Covering Policy unless otherwise directed by Contracting or COR. Controls are also subject to change during this period of performance based off CDC, Federal and Local regulations.

1. All workers shall be required to follow CDC guidance and social distancing guidelines with regard to COVID-19 prevention

2. Workers are required to wear masks at all times at their own expense while on campus.

3. Masks with exhalation valves are NOT permitted unless requested or approved by the COR or his/her designee.

4. The CDC IP&C Recommendations for COVID-19 (June 19, 2020) support not using respirators with exhalation valves. This is also subject to change.

https://www.cdc.gov/coronavirus/2019-ncov/hcp/infection-controlrecommendations.html

5. Respirators with an exhalation valve are not recommended for source control as they allow unfiltered exhaled breath to escape.

6. Respirators with exhalation valves are not recommended for source control and should not be used during surgical procedures as unfiltered exhaled breath would compromise the sterile field.

B.6 CONFORMANCE STANDARDS:

All design and construction accomplished pursuant to this contract shall comply with the latest edition of the following documents unless the contractor is directed otherwise by the Contracting Officer. Any exceptions shall be approved in writing by the Contracting Officer prior to construction startup.

1. VA Master Construction Specifications – VA Technical Information Library link:

https://www.cfm.va.gov/til/spec.asp#01

2. VA Construction Standards

3. VA Seismic Design Handbook

4. VA Space Planning Criteria

5. VA Design Manuals

6. VA CADD Standards

7. NFPA 101, Life Safety Code

8. NFPA 70, National Electric Code

9. NFPA 99, Health Care Facilities

10. NFPA 241, Standard for Safeguarding Construction, Alteration and Demolition Operations including but not limited to Ch. 8.

11. NFPA 12, Installation of Sprinkler Systems

12. Accessibility Standards (ADAAG, ABAAS, Barrier Free Design Guide)

13. AIA Guidelines for Construction and Equipment of Hospital and Medical Facilities

14. International Building Codes

15. State and Local codes and guidelines (as applicable)

B.7 HOURS OF COVERAGE:

A. Normal hours of operation are Monday through Friday from 7:30 am to 4:00 pm PST time. All work is expected to be performed generally during normal hours of coverage unless requested or approved by the COR or his/her designee.

B. Before commencement of work, the Contractor shall confer with the VHA COR and Contracting Office to agree on a sequence of procedures; means of access to premises and building. All work performed, to include delivery of materials and equipment, shall be made with minimal interference to Government operations and personnel.

C. Federal Holidays observed by Veterans Health Administration are:

1. Federal Holidays are as follows:

New Year’s Day Independence Day

Birthday of Martin Luther King, Jr. Labor Day

Blank Columbus Day

Washington’s Birthday Veterans Day

Memorial Day Thanksgiving Day

Juneteenth National Independence Day Christmas Day

For actual dates observed, see the following link:

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/

B.8 IDENTIFICATION, PARKING, NO SMOKING, & VA REGULATIONS:

The Contractor's FSEs shall wear visible badge identification issued by VASDHCS Police Section at all times while on the premises of VAHCS. It is the responsibility of the Contractor to park in the appropriate designated parking areas. Information on parking is available from the VA Police Section. VASDHCS shall not invalidate or make reimbursement for parking violations of the Contractor under any conditions. Smoking is strictly prohibited anywhere on the Veterans Affairs Health Care Facilities, to include main facility, and any other buildings at or on the premises. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.

B.9 INFORMATION SECURITY:

In accordance with Appendix A, Handbook 6500.6 Checklist blocks 7, the C&A requirements do not apply to this requirement, and Security Accreditation Package is not required. The nature of this requirement is technical; however, there is no information to be protected.

B.10 POINTS OF CONTACT AND PHYSICAL LOCATION:

Access to worksite shall be coordinated through:

COR: Wilson Rowley VA San Diego HCS

3350 La Jolla Village Dr San Diego CA 92161

Cell 858 518-2705

B.11 PERIOD OF PERFORMANCE:

Commencement of work shall begin within 10 days of receipt of written Notice to Proceed (NTP) and should last no longer than a duration of 365 calendar days after date NTP is issued.

(Note: Reference Section A.4 for Main Item and Bid Additives POP)

B.12 SUBMITTALS:

A. Contractor shall submit all required material/shop drawing submittals to the

Contracting Officer within 10 calendar days of award, or as agreed to by the Contracting Officer for approval. No materials shall be installed prior to approval via submittal exchange or other electronic transfer method.

B. All material submittals and shop drawings shall have the Project Title, Project Number, and Contract number clearly indicated.

C. Material submittals and shop drawings shall be checked and signed by the Contractor’s Quality Control Manager prior to submission to the Government.

D. Submittals shall be legible and shall include all technical data needed to verify that the item meets requirements of listed specifications, and applicable codes.

E. Contractors shall utilize Material Approval Submittal (or similar template) for use as cover sheet when submitting to Government for approval. Forms shall be provided to contractor at post-award, pre-construction conference.

B.13 COMMENCEMENT, COMPLETION, AND PAYMENT FOR WORK:

A. The Contractor shall be required to commence work required at the time specified on the Notice to Proceed (NTP), execute the work, and complete the entire work not later than the completion time specified on the NTP. The time stated for completion shall include final cleanup of the premises. At the government’s option, it may choose to specify a two-stage performance period. For example, separating material lead-time from construction days can considerably decrease the length of time occupied buildings are inconvenienced by construction.

B. Before commencement of work, the Contractor shall confer with the VA COR and Contracting Office to agree on a sequence of procedures; means of access to premises and building; space for storage of materials and equipment; delivery of materials and use of approaches; use of corridors, stairways, elevators, and similar means of communications; location of partitions, eating spaces, and restrooms for the Contractor employees; and the like. Delivery of materials and equipment shall be made with minimal interference to Government operations and personnel.

C. The Contractor shall be paid monthly upon submission of proper invoices for work completed. If the performance period exceeds 30 days and a progress schedule (approved by the Government) has been submitted, partial payment(s) may be authorized. Final payment shall be withheld until all discrepancies are corrected and as-built drawings are approved by the Government.

D. The contractor shall coordinate no less than bi-weekly progress meetings with the COR and/or Contracting Officer to discuss at a minimum; progression of work, projected progress versus actual progress, action items due from the contractor, submittals, invoicing, payroll submission and associated 1413’s, change order request, RFI’s, safety action items due from the government, and any other significant issues that require attention. The contractor also shall document the meeting minutes and forward a signed copy to the COR for concurrence of the documentation. Copies of all minutes shall be forwarded to the Contracting Officer and COR. In the event of any discrepancies, the Contracting Officer or COR shall be notified immediately for clarification. Contractor shall use the Meeting Minutes form (or similar template) provided for use at the post-award, pre-construction conference.

B.14 ESTIMATED COST RANGE

Magnitude estimated price ranges are between $2,000.000 to $5,000,000 in accordance with (IAW) VAAR 836.204

B.15 MODIFICATIONS:

Modifications for this project shall be submitted to the assigned COR who shall then submit a formal request to the Contracting Officer (CO). Work, time, cost or scope changes are not allowed to commence prior to Contracting Officer’s signed and/or written approval via fully executed Standard Form (SF) 30 modification.

B.16 ACRONYMS:

A. ABAAS - Architectural Barriers Act Accessibility Standard

B. ADAAG - Americans with Disabilities Act Accessibility Guidelines.

C. AIA - American Institute of Architects' AIA

D. CAC - Certified Asbestos Consultant

E. CADD - Computer Aided Design and Drawing

F. CO - Contracting Officer. The Federal employee who is warranted by the Government to enter into contracts on behalf of the Government and is the only person authorized to make changes to those contracts

G. COR - Contracting Officer's Representative. Individual designated by the CO to place orders, furnish technical guidance, advice, certify invoices, and provide general supervision of the work performed under the executed contract

H. EOSH - Environmental and Occupational Safety and Health

I. EPA - Environmental Protection Agency

J. FSE - Field Service Engineer

K. HIPAA - Health Insurance Portability and Accountability Act of 1996

L. ICRA - Infection Control Risk Assessment

M. IPRM - Information Protection Risk Management

N. ILSM - Interim Life Safety Measures

O. ISO - International Standards Organization

P. VASDHCS - VA San Diego Health Care System

Q. MOU - Memorandum of Understanding

R. NFPA - National Fire Protection Association

S. NTP - Notice to Proceed

T. OEM - Original Equipment Manufacturer

U. OSHA - Occupational Safety and Health Administration

V. SF - Standard Form

W. SME - Subject Matter Expert

X. SOW – Statement of Work

Y. TIL – Technical Information Library

Z. TWA - Time-Weighted Average

AA. VA – Veteran Affairs

BB. VAHCS – Veteran Affairs Health Care System

CC. VHA - Veterans Health Administration

(END OF SOW)

SECTION D

Drafter (AE Firm) Document Title Document Date

Number of

Pages

Davy Architecture.

Specifications:

IFC100CD Vol 1_VASD 4N Cardio Cath

Lab 2 Project Manual

IFC100CD Vol 2_VASD 4N Cardio Cath

Lab 2 Project Manual

Specs

March 10, 2021 1522

Davy Architecture.

Drawings:

664‐CSI‐116_PLAN_IFC100CD_21‐0510

Plans

March 10, ***REFER TO SECTION D***