This is a Nontidal Wetlands and Waterways Pre-Application Summary document prepared by the Maryland Department of the Environment (MDE) in coordination with Charles County Department of Public Works and Charles County Department of Recreation, Parks & Tourism regarding a proposed dredging project at Wheatley Dam. The pre-application meeting was conducted on August 14, 2025, at 10:00 a.m., with attendees including Sara Albrecht and Sebastian Fernandez from MDE, Keith Roumfort from Charles County Department of Public Works, and Anthony Hancock from Charles County Department of Recreation, Parks & Tourism. The project involves proposed dredging of Wheatley Dam while the lake is drained for separate retrofit construction and repair work being reviewed through MDE Dam Safety. The site is located at Wheatley Lake within Gilbert Run Park, 13140 Charles Street, Charlotte Hall, Maryland 20622. During the site visit, four areas of nontidal wetlands were identified within the lake, with the majority of Wheatley Lake consisting of open water that is not regulated as nontidal wetlands or waterways. The pre-application review determined that proposed dredging may be able to avoid the identified wetland areas entirely, contingent upon finalized dredging plans.

The document indicates that the project would require state authorization, though the specific type depends on final dredging plans and design. MDE staff recommended that once dredging plans are developed, the applicant should consult further with MDE to determine whether authorization would be required and what category of permitting may apply. The 100-year nontidal FEMA floodplain expands beyond the water's edge, and any staging activities within the floodplain would require temporary impact authorization provided the area is restored to prior conditions following work completion. Coves 1, 2, and 4 had clearly apparent wetland boundaries where vegetation transitioned to open water, while Cove 3 contained a more complex braided wetland and stream system where Wheatley Run and tributaries enter the lake. MDE staff emphasized that dredging should be avoided in shallower areas with wetland presence, with further consultation required if dredging must occur near wetland areas. The review was conducted by Sara Albrecht, MDE Nontidal Wetlands Division, who can be contacted at sara.albrecht@maryland.gov or 410-537-3691.

View the file

Other files

File Type Posted
Wheatley_Dam_Dredging_Services.pdf PDF
Wheatley_Dam_Dredging_Services.pdf PDF
Appendix_H_Wetland_PreApp.pdf PDF
Appendix_G_Wheatley_Reservoir_Bathy_Contours_Depths.pdf PDF
Appendix_G_Wheatley_Reservoir_Bathy_Contours_Depths.pdf PDF
Appendix_F_Wheatley_Reservoir_Bathy_Depths.pdf PDF
Appendix_F_Wheatley_Reservoir_Bathy_Depths.pdf PDF
Appendix_E_Wheatley_Reservoir_Bathy_Contours_NAVD88.pdf PDF
Appendix_E_Wheatley_Reservoir_Bathy_Contours_NAVD88.pdf PDF
Appendix_D_Wheatley_Reservoir_Bathy_NAVD88.pdf PDF
Appendix_D_Wheatley_Reservoir_Bathy_NAVD88.pdf PDF
Appendix_C_Bathymetric_Survey_Report.pdf PDF
Appendix_C_Bathymetric_Survey_Report.pdf PDF
Appendix_B_Dredging_Drawings.pdf PDF
Appendix_B_Dredging_Drawings.pdf PDF
Appendix_A_Technical_Specifications_for_Dredging_and_Sediment_Removal.pdf PDF
Appendix_A_Technical_Specifications_for_Dredging_and_Sediment_Removal.pdf PDF
Performance_Labor_Bonds.pdf PDF
Performance_Labor_Bonds.pdf PDF
Sample_Contract_-_Term_&_Renewals_Specified.pdf PDF
Sample_Contract_-_Term_&_Renewals_Specified.pdf PDF
Draft_dredging_RFQ_Bid_Form_revised_12.12.25.docx DOCX document
Wheatley_Reservoir_Dredging_Procurement_Request_07.15.25_-_signed.pdf PDF
Draft_dredging_RFQ_Bid_Form_revised_12.12.25.docx DOCX document
Dredging_Contract_Special_Provisions_12.12.25kr.docx DOCX document
Dredging_Contract_Special_Provisions_12.12.25kr.docx DOCX document
Wheatley_Reservoir_Dredging_Procurement_Request_07.15.25_-_signed.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Nontidal Wetlands and Waterways Pre-Application Summary

1. AI#:

2. Date: / / Time: :

3. Summary prepared by:

4. Attendees:

5. Property owner name:

6. Address or Site Location/Description (directions, if no physical address is available):

7. Project purpose:

8. Plans provided: Yes No

9. State regulated resources found: Yes No

NTW Type: PEM PSS PFO Landscape Mgmt Area Ag

NTW Buffer Critical Area Tidally Influenced

Waters of the State: Stream Floodplain

11. Delineation provided: Yes No

12. Avoidance/Minimization Discussed? Recap:

PDilnesahu Stamp

Document Date: January 19, 2023

13. Project, as described, would require Authorization: Yes No

If Yes, type of State authorization required:

Permit Letter of Authorization Authorization to Proceed

If Yes, project (as described or shown on plans) under the MDSPGP would be:

Category A Category B Individual Permit

* U.S. ACE categorization is a preliminary determination only and may change upon receipt of application or further consultation with the U.S. ACE staff or other resource agencies

14. Recommended Action (check all that apply):

Consult with Corps Submit Application Schedule follow-up meeting

No action required Other

Pre-App Site Visit Comments:

Maryland Department of the Environment Reviewer Contact Information:

Name Email

Telephone ( ) -

*This document is a summary of the items discussed. Please note that this information is based on MDE staff preliminary cursory review at the time of the preapplication meeting. MDE staff will perform a full review of the project and all available information at the time of the application submission. Additional information may be required.

Applicant/Consultant Signature:

Approximate location of emergent nontidal wetlands following 8/14/25 site visit

Watershed Resources Registry:

100-year nontidal FEMA floodplain

Note: site is not within a Tier II watershed (screened 8/27/25)

PreApp Summary Meeting - Wheatley Dam 1.pdf
Wheatley Dam exhibits for sum
Slide 1
Slide 2
Text1: 38983
Text2: 08
Text3: 14
Text4: 2025
Text5: 10
Text6: 00
Combo Box6: [AM]
Text10: Sara Albrecht - MDE Nontidal Wetlands Division

Sebastian Fernandez - MDE Waterway Construction Division Keith Roumfort - Charles Co Dept of Public Works Anthony Hancock - Charles Co Dept of Recreation, Parks & Tourism

Text8: Board of Charles County Commissioners
Text9: Wheatley Lake within Gilbert Run Park

13140 Charles St, Charlotte Hall, MD 20622 (Charles County)

Text11: Proposed dredging of Wheatley Dam while the lake is drained for a separate project (retrofit construction and repair work being reviewed through MDE Dam Safety).
Check Box7: Off
Check Box8: Yes
Check Box13: Yes
Check Box14: Off
Check Box15: Yes
Check Box16: Off
Check Box17: Yes
Check Box18: Off
Check Box19: Off
Check Box20: Yes
Check Box21: Off
Check Box24: Off
Check Box23: Yes
Check Box9: Yes
Check Box27: Off
Check Box28: Yes
Text29: The majority of Wheatley Lake is open water, which is not regulated as nontidal wetlands or waterways. During the site visit, four areas of the lake had nontidal wetlands present (see attachment). The proposed dredging may be able to avoid these areas entirely. Plans for the dredging must be developed and finalized before a determination of potential impacts to regulated resources can be made.
Check Box30: Off
Check Box31: Off
Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
Check Box5: Off
Check Box6: Off
Check Box32: Off
Check Box33: Off
Check Box34: Off
Check Box35: Off
Text36: Once dredging plans are developed, discuss further with MDE to determine whether authorization would be required.
Text37: Coves 1, 2 and 4 (from attachment) had fairly apparent wetland boundaries where wetland vegetation ended as it became open water.

Cove 3 had a more developed braided wetland/stream system where Wheatley Run and other tributaries entered the northern side of the lake. This wetland was still demarcated by the end of wetland vegetation before becoming open water.

Note that the 100-year nontidal FEMA floodplain expands past the edges of the water (see attachment). If staging is proposed within the floodplain, this would require authorization as a temporary impact, as long as the area was returned to prior conditions following the work.

It was discussed that dredging should be avoided within any of the shallower areas where wetlands are present. If dredging must occur near these areas, please discuss further with MDE once plans are designed to determine what kind of authorization may be required.

Combo Box8: [Sara Albrecht]
Text39: sara.albrecht@maryland.gov
Text40: 410
Text41: 537