Task Order 00001 - Statement of Work.docx

DOCX document 27 KB Posted

Attached to
USDA Forest Service National Tower IDIQ Federal contract opportunity
Solicitation number
AG-7604-S-12-0020
Issued by
Department of Agriculture Forest Service Washington Office Acquisitions

About this file

Task Order 0001 Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to USDA Forest Service National Tower IDIQ, newest first.
File Type Posted
Rev_Sample_Task_Order.docx DOCX document
RFP_AG-7604-S-12-0020_National_Tower_IDIQ_v8_-_lsh.docx DOCX document
Rev_9-20-2012_Task_Order_00001_-_Statement_of_Work.docx DOCX document
Pricing_Tables_1_2_3.xls XLS spreadsheet
Amendment_006_SF-30.doc DOC document
RFP AG-7604-S-12-0020 National Tower IDIQ v7 - lsh.docx DOCX document
Amendment 005.doc DOC document
Pricing Tables 1 2 3.xls XLS spreadsheet
Davis Bacon - Lincoln Cty OR72.pdf PDF
Task Order 00001 - Statement of Work.docx DOCX document
Past Performance Questionnaire - Final.doc DOC document
Geotechnical Investigation - Cougar Tower - Lincoln Cty OR.PDF PDF
Sample Task Order.docx DOCX document
Revised Questions for AG-7604-S-12-0020.docx DOCX document
RFP AG-7604-S-12-0020 National Tower IDIQ v6.docx DOCX document
Davis Bacon Gogebic MI36.pdf PDF
Davis Bacon Silver Bow MT76.pdf PDF
Davis Bacon Idaho ID12.pdf PDF
Davis Bacon Lemhi ID12.pdf PDF
Task Order 00001 - Statement of Work.docx DOCX document
Davis Bacon Houston TX123.pdf PDF
Questions for AG-7604-S-12-0020.docx DOCX document
Past Performance Questionnaire - Final.doc DOC document
RFP AG-7604-S-12-0020 National Tower IDIQ v5.docx DOCX document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Task Order 0001
Geotechnical Investigations
5/25/2012
CLIN #0001-001
526 SPUR
PRICE: $
QUANTITY
1 Each Geo-Technical Investigations
TOWER SIZE
120 Feet
CONTRACT TYPE
FIRM FIXED FEE
LOCATION
Latitude N 31° 29.206’ Longitude W 095° 13.804’ Elevation 462’
STATE
Texas
COUNTY
Houston
FS REGION
8
FOREST
Davey Crockett National Forest
POINT OF CONTACT
George Rosenthal (936) 707-1832

DESCRIPTIVE DATA

The contractor shall furnish the necessary labor, supplies, equipment, materials, travel, facilities, hardware, required to accomplish the Geotechnical Investigations detailed in SOW Paragraph 4.0. Task Orders will be issued in accordance with Section H entitled "Ordering Procedures."

CLIN #0001-002
BALL FIELD
PRICE: $
QUANTITY
1 Each Geo-Technical Investigations
TOWER SIZE
120 Feet
CONTRACT TYPE
FIRM FIXED FEE
LOCATION
Latitude N 31° 10.977’ Longitude W 095° 02.167’ Elevation 356’
STATE
Texas
COUNTY
Houston
FS REGION
8
FOREST
Davey Crockett National Forest
POINT OF CONTACT
George Rosenthal (936) 707-1832

DESCRIPTIVE DATA

The contractor shall furnish the necessary labor, supplies, equipment, materials, travel, facilities, hardware, required to accomplish the Geotechnical Investigations detailed in SOW Paragraph 4.0. Task Orders will be issued in accordance with Section H entitled "Ordering Procedures."

CLIN #0001-003
MARENISCO TOWER
PRICE: $
QUANTITY
1 Each Geo-Technical Investigations
TOWER SIZE
200 Feet
CONTRACT TYPE
FIRM FIXED FEE
LOCATION
Latitude N 46° 22’ 48.6” Longitude W 089° 39’ 42.50” Elevation 356’
STATE
Michigan
COUNTY
Gogebic
FS REGION
9
FOREST
Ottawa National Forest
POINT OF CONTACT
Kevin Throop (218) 327-5926

DESCRIPTIVE DATA

The contractor shall furnish the necessary labor, supplies, equipment, materials, travel, facilities, hardware, required to accomplish the Geotechnical Investigations detailed in SOW Paragraph 4.0. Task Orders will be issued in accordance with Section H entitled "Ordering Procedures."

CLIN #0001-004
HIGHLAND LOOKOUT
PRICE: $
QUANTITY
1 Each Geo-Technical Investigations
TOWER SIZE
60 Feet
CONTRACT TYPE
FIRM FIXED FEE
LOCATION
Latitude N 45° 46’ 7.0” Longitude W 112° 29’ 6.6” Elevation 9718’
STATE
Montana
COUNTY
Silver Bow
FS REGION
1
FOREST
Beaverhead / Deerlodge National Forest
POINT OF CONTACT
Bill Givens (406) 660-0114

DESCRIPTIVE DATA

The contractor shall furnish the necessary labor, supplies, equipment, materials, travel, facilities, hardware, required to accomplish the Geotechnical Investigations detailed in SOW Paragraph 4.0. Task Orders will be issued in accordance with Section H entitled "Ordering Procedures."

CLIN #0001-005
SOUTH SALMON BALDY TOWER
PRICE: $
QUANTITY
1 Each Geo-Technical Investigations
TOWER SIZE
40 Feet
CONTRACT TYPE
FIRM FIXED FEE
LOCATION
Latitude N 45° 08’ 41.45” Longitude W 114° 00’ 32.39” Elevation 9141’
STATE
Idaho
COUNTY
Lemhi
FS REGION
4
FOREST
Salmon / Challis National Forest
POINT OF CONTACT
Jason Bruce (208) 756-5194

DESCRIPTIVE DATA

The contractor shall furnish the necessary labor, supplies, equipment, materials, travel, facilities, hardware, required to accomplish the Geotechnical Investigations detailed in SOW Paragraph 4.0. Task Orders will be issued in accordance with Section H entitled "Ordering Procedures."

CLIN #0001-006
HIGH CAMP TOWER
PRICE: $
QUANTITY
1 Each Geo-Technical Investigations
TOWER SIZE
80 Feet
CONTRACT TYPE
FIRM FIXED FEE
LOCATION
Latitude N 45° 51’ 30” Longitude W 116° 07’ 40” Elevation 5826’
STATE
Idaho
COUNTY
Idaho
FS REGION
1
FOREST
Clearwater National Forest
POINT OF CONTACT
Jim Whitney (208) 983-7002

DESCRIPTIVE DATA

The contractor shall furnish the necessary labor, supplies, equipment, materials, travel, facilities, hardware, required to accomplish the Geotechnical Investigations detailed in SOW Paragraph 4.0. Task Orders will be issued in accordance with Section H entitled "Ordering Procedures."

CLIN #0001-007
IRON MOUNTAIN TOWER
PRICE: $
QUANTITY
1 Each Geo-Technical Investigations
TOWER SIZE
60 Feet
CONTRACT TYPE
FIRM FIXED FEE
LOCATION
Latitude N 45° 55.05’ Longitude W 115° 32.30’ Elevation 7404’
STATE
Idaho
COUNTY
Idaho
FS REGION
1
FOREST
Nez Pierce National Forest
POINT OF CONTACT
Jim Whitney (208) 983-7002

DESCRIPTIVE DATA

The contractor shall furnish the necessary labor, supplies, equipment, materials, travel, facilities, hardware, required to accomplish the Geotechnical Investigations detailed in SOW Paragraph 4.0. Task Orders will be issued in accordance with Section H entitled "Ordering Procedures."

4.0 GEOTECHNICAL INVESTIGATIONS (Normative) ANSI EIA/TIA 222G - Page 209 Vendor shall be responsible to perform and provide a Geotechnical Report to the Forest Service prior to the commencement of tower project. The following are the guidelines set forth in the ANSI EIA/TIA 222G manual.

4.1 Annex contains information that shall be contained in a geotechnical investigation.

4.1.1. Boring logs and report shall provide:

1. Date, sampling methods, number and type of samples

2. Description of the soil strata according to the Unified Soil Classification System

3. Depths at which strata changes occur referenced to a site benchmark elevation

4. Standard Penetration Test blow counts for each soil layer

5. Soil density for each soil layer

6. Internal angle of friction for each soil layer

7. Cohesion for each soil layer

8. Ultimate bearing capacities for each soil layer or at the recommended bearing depth(s)

9. For expansive soil conditions, the active zone of influence and recommendations for design

10. Elevation of free water encountered and the ground water depth below grade to be considered for design

11. Frost depth to be considered for design

12. Soil electrical resistivity, pH values and corrosive nature of soil

13. Other pertinent soil design data and recommendations

14. Recommendations for alternate foundation types

15. Topographic information for the site

16. Note the location within 1,000 ft. [300 m] of the structure of underground pipelines, buried concentric neutral power wires and electrical substations as these may effect electrolytic corrosion.

4.1.2. For drilled piers the following information shall also be provided:

1. Ultimate tip bearing capacity

2. Ultimate skin friction for each soil layer

3. Lateral modulus of soil reaction for each soil layer.

4. Ultimate soil strain at 50% of ultimate compression, for each soil layer.

4.1.3. For rock anchors the following information shall also be provided:

1. Type and condition of rock

2. Rock quality designation, RQD

3. Percent rock sample recovered

4. Ultimate bond stress in the interface between the rock and grout.
5. Ultimate shear strength

DELIVERIES OR PERFORMANCE

A. FEDERAL ACQUISITION REGULATION CONTRACT CLAUSES IN FULL TEXT

FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 14 calendar days. The time stated for completion shall include final cleanup of the premises.