Amendment No. 1

View the file

Other files for this federal contract opportunity

Other files attached to Shelter Stewardship, newest first.
File Type Posted
Final_Amendment_4.docx DOCX document
Amendment_3.pdf PDF
Amendment_2.pdf PDF
VolumeSummary.pdf PDF
DecomissioningSpecs.pdf PDF
i.Construction_Wage_WA1.txt TXT text file
g.4ShelterCAMpage4.pdf PDF
g.7ShelterCAMpage7.pdf PDF
a.Cover_Letter_File_Code.docx DOCX document
f.2App_D_-_Decomm_Plans_2900110.pdf PDF
f.1App_D_-_Decomm_Plans_2900105.pdf PDF
g.2ShelterCAMpage2.pdf PDF
b.Shelter_Stewardship_Solicitation.docx DOCX document
g.1ShelterCAMpage1.pdf PDF
g.5ShelterCAMpage5.pdf PDF
g.3ShelterCAMpage3.pdf PDF
g.6ShelterCAMpage6.pdf PDF
f.5App_D_-_Reconstruction_Plans.pdf PDF
f.3App_D_-_Decomm_Sample_Worksheet.pdf PDF
f.4App_D_-_Decomm_Specs.pdf PDF
c.Shelter_Stewardship_BiddersPacket.docx DOCX document
h.SCA_Wage_Rate_77-0209.txt TXT text file
f.6App_D_-_Reconstruction_Supplemental_Specifications.pdf PDF
e.App_C_-_Haul_Maintenance.pdf PDF
d.Appendix_B_Shelter_Scaled.doc DOC document
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE
PAGE OF PAGES

2 AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

07/13/2015

4. REQUISITION/PURCHASE REQ. NO

5. PROJECT NO.(IF APPLICABLE)

6. ISSUE BY CODE

7. ADMINISTERED BY (if other than item 6) CODE

R6 Stewardship Acquisition Group 72510 Coyote Road Pendleton, OR 97801

8.NAME AND ADDRESS OF CONTRACTOR(No., street, county, State and ZIP Code)
X
9A. Amend Solicitation No.

AG-05G2-S-15-9000, Shelter Stewardship IRSC

X
9B. Dated 7/1/2015

10A. Modification of Contract/Order #

10B. Dated

code
facility code

11. THIS ITEM APPLIES ONLY TO AMENDMENT OF SOLICITATION

[ X] The above numbered solicitation is amended as set forth in the item 14. The hour and date specified for receipt of Offers [ ] is extended [X ] is not extended. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted, or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. This change order is issued pursuant to; (specify authority):

B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.) set forth in item 14, pursuant to the authority of FAR 43.103(b)..

C. This supplemental agreement is entered into pursuant to authority of:

D Other: (Specify type of modification and authority):

E. IMPORTANT: Contractor [] is not [X] is required to sign this document and return 1 Original to the issuing office.:

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible See Attached Site Visit Document (2 Page) See Attached Volume Summary Sheet (6 Page) See Attached Revised Decomissioning Specifications. Please replace the cooresponding pages out of the plans.

Revised: Item 2900110 (culvert removal) was to be completed by end of contract now the government would like it complete no later than October 31st 2017

By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER

Contracting Officer

15B. CONTRACTOR/OFFEROR

By (Signature of person authorized to sign)

15C. DATE SIGNED
16B. UNITED STATES OF AMERICA

By______________________________ (Signature of Contracting Officer)

16C. DATE SIGNED

Standard Form 30 Prescribed by GSA FAR (48CFR) 53.243

Notes from the Site Visit for Shelter Stewardship 7/7/2015

Vendors: Bower Logging/ Larsen Timber/ A.T.R./ S.P.I.

Forest Service: Steve M./ Ray H./ Kevin G./ Pete S./ Bob M./ Jennie C./ Chris D/ Jana C./ Gavin S.

The group met at the Pacific Ranger District in Forks Washington and discussed the following solicitation information.

This solicitation and resultant contract is an Integrated Resource Service Contract using Stewardship Authority which allows the government to trade the value of the standing timber to pay for service restoration work. Under this solicitation the government appraisal of the timber is anticipated to be less than the total cost the service work therefore the government has appropriated dollars to help pay for service work that the value of the timber can not cover.

Items discussed in general terms:

The contracting officer discussed the main solicitation and the need for interested vendors to become registered in the System for Award Management (SAMs). There are resources (one is the Association for Procurement Technical Assistance Centers APTAC) out there to help new contractors navigate government requirements to bid on federal contracts. A link to their site is listed below:

http://www.aptac-us.org/contracting-assistance/

The contracting officer identified the main sections of the solicitation and emphasized the information on the front of the SF-33, where the contractor is required to sign and where the contractor is required to provide pricing on the subsequent pages. Additionally, the contracting officer discussed section L and what the contractors would be required to submit for their proposals as well as section M which lists how the contractors would be evaluated based on the technical and pricing elements submitted. No questions from the group over the solicitation.

Q1: Is there any heritage identified in the project?

A1: No, there are none identified at this time.

Q2: How is local defined and how many sub-contractors can be used?

A2: Local is defined in section L under L.5 “Instructions for the Preparation of Technical and Business Proposals” in technical element 5 “Utilization of Local Workforce”. It is further discussed in section M where the solicitation describes how the highest rating for this element can be achieved.

There is no limit to how many subcontractors can be used under this contract since it is being competed full and open with no business size class identified.

The group then briefly talked about safety when traveling out to the project area and where we were going and the known hazards. The group departed at 0900 to Forest Road 2900-110

Group arrived at 0930 and discussed the specifications for the road reconstruction and culvert removal, Item 2900110 and all technical information was referenced from Appendix D associated with this work activity. Also discussed was the requirement that road reconstruction work needed to be completed by July 31, 2016. The culvert removal was to be completed by end of contract now the government would like it complete no later than October 31st 2017. Cutting units 7,7A,7B have to be logged by October 31, 2016. The group also talked about the urgency to remove this failing culvert before it completely collapsed and caused tremendous resource damage. The disposal site for the excavated material was identified as an old helicopter landing approximately 100 feet away from the culvert to be removed. All the rock for the road reconstruction is to be sourced from commercial site which are certified weed free. Appendix B was also covered at this site since there is a priority logging requirement for units 7, 7A, and 7B (Appendix B under K-G.3.1.5# - PROJECT OPERATION SCHEDULE). All the skips and gaps are identified on the ground and K.C.3.5.7# was discussed as to how the thinning was to be completed under the DxD. Additionally, the inspection of this requirement was pointed out in the provision based on species retention, cut tree stump diameters, and residual spacing. It was emphasised that contractors respond to these timing requirements in their proposals.

Q3: Does the logging of these units have to go down this road?

A3: No, if the the contractors think they can pull the volume behind this pipe removal area out from the upper road that would be acceptable. Please identify how you would do this in your technical proposal.

Q4: How is the decomissioning of the segment behind the pipe going to be achieved?

A4: That all really depends on how the logging of the units will happen. If the material is not hauled out this road then the decom could happen sooner. If the volume it going down the road then that would have to happen first and then the decomissioning would happen after that.

Q5: Is there a volume summary?

A5: Yes, it will be posted with amendment 1 as a separate attachment.

Departed this site at 10:25 Arrived at the 2900-100 road at 10:45

The location of a temp road was identified near unit 5 to access this area.

The group walked down the 105 spur road and looked at the Optional Item of the culvert removal on this road.

Q6: How do contractors do this work without improving the access down this road?

A6: The government has made an allowance in the mobilization costs for contractors to open this segment up down this spur to the pipe.

At this location the decommission specs were discussed out of Appendix D for this work to be done.

Q7: So how is the stumpage really calculated for this contract?

A7: The traditional cost centers for standard timber appraisals were removed in this calculation for stumpage and placed in the contract as service activities to be bid on. What happens when the government appraises timber under these contracts using fewer costs allocations, the value of the timber increases and is reflected in the minimum acceptable bid rate for included timber. The intent is to let the contractors earn the costs of the service work in the Schedule of Items to be used to reduce the actual amount of timber value charged as subdivisions are released.

Q8: How do prime contractors pay their subs if they are exempt from Davis Bacon (Construction Wage Rates)?

A8: Really what it comes down to is how the sub-contractor is set up as a company. The responsibility of the prime is to ensure the sub-contractor is aware of the prevailing wage rates and fringe benefits for the work categories they are performing under the contract. How payments are made should be based on their company structure and how they hire employees. It is your responsibility as a prime to indicate this on the payroll sheets. If there are any questions or doubts please pay your sub-contractors at the prevailing wage identified in this contract. Any further clarification should be submitted to the regional Department of Labor office for your area.

The site visit concluded at 11:30.

CONTRACTORS ARE REQUIRED TO SIGN THE FRONT PAGE OF THIS AMMENDMENT AS ACKNOWLEDGEMENT OF THIS INFORMATION PROVIDED.