Project 1 - Canyon Creek / Canyon Lake Trail

View the file

Other files

File Type Posted
amendment_1.pdf PDF
short_set.pdf PDF
Solicitation.pdf PDF
Attachment B Drawings.pdf PDF
Project 2 Rombo Part 2.pdf PDF
Attachment A.pdf PDF
Project 2 Rombo Part 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project 1 – Canyon Creek Trail

PROJECT 1 – CANYON CREEK/CANYON LAKE TRAIL

This is a real project that will be awarded under a task order simultaneously or shortly after awards are made to RFP AG-03R6-S-08-0055.

The project will also be used in the business/price evaluation as a measure of the Offeror’s price reasonableness.

ITEM DESCRIPTION METHOD

OF MEAS.

QTY PAY

UNIT

UNIT

PRICE

TOTAL

LINE PRICE

911(02) Clearing & Grubbing DQ 1,894 LF $__________ $__________

*911(10) Individual Tree Removal and Disposal AQ 1 EA $__________ $__________

912(01) Excavation DQ 1,894 CY $__________ $__________

*912(07)A Shallow Stream Ford and Gully Crossing Structure

AQ 1 EA $__________ $__________

*912(09) Ditch AQ 25 LF $__________ $__________

*915(01) Trail Restoration – Hike/Pack Trail AQ 3,517 LF $__________ $__________

*915(03) Check Dams AQ 3 EA $__________ $__________

922(0) Treated Log Waterbar, Contractor Furnished & Installed

AQ 91 EA $__________ $__________

951(01) Mobilization LSQ 1 LS $__________ $__________

952(02) Sign Installation AQ 4 EA $__________ $__________

*954(02) Obliteration – Hike/Pack AQ 1,857 LF $__________ $__________

981(02) Brush Cutting DQ 5,398 LF $__________ $__________

982(03) Logging Out DQ 38,447 LF $__________ $__________

991(03) Drainage Maintenance AQ 55 EA $__________ $__________

* Laborer AQ 8 HR $__________ $__________

* Unit Price must match RFP unless specification for this specific project is different.

Description of Work

PROJECT NAME

Canyon Lake 165 / Canyon Creek 16.3 on the Seeley Lake Ranger District, Lolo National Forest, Lewis and Clark County, Montana.

PROJECT LOCATION

The project is located approximately 20 air miles east of Seeley Lake, Montana. The project can best be accessed by either the Monture Creek or the North Fork Blackfoot River Trailhead. The Monture Creek Trailhead is located 8 1/2 miles north of Ovando, Montana, at the end of Road #89. The North Fork Blackfoot River Trailhead is located at the end of Forest Road #5550, 12 miles north from its juncture with State Hwy 200. Road #5550 leaves Hwy 200 approximately 17 miles east of Clearwater junction and is signed "North Fork Blackfoot River Trailhead".

PROJECT DESCRIPTION

The project consists of construction/reconstruction/maintenance work along 7.5 miles of trail.

Project area is thru recent burn area (summer 2007). Main hazard in this area is the possibility of falling snags from burned tree stands.

Work consists of: New trail construction including clearing, grubbing, excavation, and obliteration of abandoned trail ways. Reconstruction clearing, tread work, and grubbing.

Installation or replacement of stream fords, waterbars (treated log or rock is acceptable), ditches, check dams, and signs. Trail maintenance work includes logging out, brush cutting, drainage maintenance, and individual tree removal.

Estimated quantities are as follows:

New Construction = 1,894 LF Ditch Construction= 25 LF Reconstruction Work = 3,517 LF Waterbar = 91 EA Brush Cutting = 5,398 LF Drain Maintenance = 55 EA Logging Out = 38,477 LF Check Dams = 3 EA Sign Installation = 4 EA Tree Removal= 1 EA Obliteration = 1,857 LF Shallow Stream Crossing 1 EA

COMPLETION DATE

All work shall be completed by October 15, 2008.

SPECIFICATIONS

Standard Specifications for Construction of Trails, September 1996, is hereby incorporated into this task order. There are no special project specifications.

Note: Items 981, 982, and 991 are in the Maintenance section of the Standard Specifications.

There are no special project specifications.

DRAWINGS

Drawings provided in the contract are incorporated into this task order. There are no special drawings for this project.

CONTACT

For information regarding site or technical questions, contact Jacob Long or Jim Blackburn, Seeley Lake Ranger District at (406) 677-2233.

For contract or task order questions, contact Sue Beron, Contracting Officer at 406-329-3769.

CANYON LAKE 165 / CANYON CREEK 16-3

SEGMENT A

TRAIL LOG 11/14/2007

LEGEND

SIGN INSTALLATION – SIGN

DRAINAGE MAINTENANCE – DM

OBLITERATION – OB

DITCH CONSTRUCTION – D

WATERBAR INSTALLATION – WB

INDIVIDUAL TREE REMOVAL – TR

STA. DESCRIPTION

CONSTRUCTION

OR

RECONSTRUCTION

CLEAR TREAD

WORK

0+00 Begin Segment A Beginning of Project

New Sign Installation:

< FALLS – CANYON TR NO 16

> RIDGE TR NO 165

Sign not in inventory, will need ordered (Sec. 952)

SIGN-1

EA

0+00 Loose Rock Removal – remove all rocks larger than 2” from the trailbed to station 6+50 ~ 650 FT (Sec. 984)

0+90 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA |

2+11 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA |

2+85 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA |

3+52 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA |

4+63 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA 650 LF

5+82 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA |

6+50 New Ditch - Dig a ditch above the trail near spring (stakes should be in ground up there) to improve the flow of water away from the trail and down the natural path ~ 25ft (See Pictures) Dig at 1:1 at least 1.5 ft deep or deeper as needed to effectively drain water.

D-25 LF

CANYON LAKE “RIDGE” TR. #165

SEGMENT A

TRAIL LOG

11/14/2007

CLEAR TREAD

WORK

6+50 End Loose Rock Removal |

6+61 Existing Waterbar – Drainage Maintenance

DM-1 EA

6+83 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

7+14 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

7+61 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

8+72 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

9+62 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

11+42 Intermittent Stream Crossing

11+97 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

13+87 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

18+08 Intermittent Stream Crossing

45+26 Retread 192 FT to station 47+18 (Sec. 915) ----------

45+68 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA |

46+42 Existing Waterbar – Drainage Maintenance

DM-1 EA |

CANYON LAKE “RIDGE” TR. #165

SEGMENT A

TRAIL LOG

11/14/2007

CLEAR TREAD

WORK

46+87 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA 192 LF

47+18 End Retread |

47+18 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

48+01 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

48+78 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

49+71 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

52+88 Retread 175 FT to station 54+63 (Sec. 915) ----------

53+30 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA |

175 LF

54+23 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA |

54+63 End Retread |

55+96 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

77+74 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

78+85 Existing Waterbar – Drainage Maintenance

DM-1 EA

CANYON LAKE “RIDGE” TR. #165

SEGMENT A

TRAIL LOG

11/14/2007

CLEAR TREAD

WORK

82+10 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

82+79 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

83+51 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

84+14 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

84+88 Obliteration of Abandoned Trailway – Place rock and woody debris in main erosion channel to encourage use of braided trail ~ 91 FT (Sec.

954)

OB-91 LF

86+26 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

86+88 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

87+62 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

88+51 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

89+54 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

89+56 Retread 42 FT to station 89+98 – Backfill Trenched Trailbed by pulling the trail berm and cut-slope soil material back onto the trail (See Pictures) (Sec. 915)

42 LF

89+98 End Retread |

89+98 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

CANYON LAKE “RIDGE” TR. #165

SEGMENT A

TRAIL LOG

11/14/2007

CLEAR TREAD

WORK

92+64 Individual Tree Removal – Remove “pack bump” from within clearing limits (Sec. 911)

TR-1 EA

98+53 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

100+55 Install New Waterbar (Rock or Treated Timber) Construct a long lead-off ditch to point of daylight (Sec. 922)

WB-1 EA

103+29 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

104+05 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

104+95 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

106+12 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

107+13 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

109+45 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

111+72 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

113+75 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

115+73 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

116+27 Retread 190 FT to station 118+17 (Sec. 915) ----------

117+56 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA |

190 LF

CANYON LAKE “RIDGE” TR. #165

SEGMENT A

TRAIL LOG

11/14/2007

CLEAR TREAD

WORK

118+17 End Retread |

119+82 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

124+64 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

125+70 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

126+54 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

128+50 Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1 EA

128+85 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

129+72 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

130+13 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

131+22 Existing Waterbar – Drainage Maintenance (Sec. 991)

DM-1 EA

136+57 Junction of Ridge TR NO 165 / Falls – Canyon TR NO 16 / Conger Creek TR NO 403

136+57 New Sign Installation:

^ FALLS – CANYON TR NO 16

< CANYON CR TR NO 16

> RIDGE TR NO 165

Sign not in inventory, will need ordered (Sec. 952)

CANYON LAKE “RIDGE” TR. #165

SEGMENT A

TRAIL LOG

11/14/2007

CLEAR TREAD

WORK

136+57 New Sign Installation:

^ CONGER CR TR NO 403

< RIDGE TR NO 165

> CANYON CR TR NO 16

Sign not in inventory, will need ordered (Sec. 952)

End of Segment A Equation – 136+57 Back = 0+00 Forward

CANYON LAKE 165 / CANYON CREEK 16-3

SEGMENT B

TRAIL LOG 11/15/2007

LEGEND

SIGN INSTALLATION – SIGN

DRAINAGE MAINTENANCE – DM

OBLITERATION – OB

WATERBAR INSTALLATION – WB

SHALLOW STREAM FORD – SSF

CHECK DAM – CD

STA. DESCRIPTION

CONSTRUCTION

OR

Equation – 136+57 Back = 0+00 Forward

CLEAR TREAD

WORK

0+00 Begin Segment B

Junction of Ridge TR NO 165 / Falls – Canyon TR NO 16

/ Conger Creek TR NO 403

1+21 Creek Ford – Conger Creek

CONSTRUCTION

16+65 Reroute 172 ft to station 17+92 – Build new trail away from eddy in creek – 1 ft. either side of center line (Sec. 911, 912)

16+96 Center Line

17+18 Center Line

17+52 Center Line

17+92 End Reroute – Tie new construction into existing trailbed

Obliterate existing trail approximately 100 ft – lightly block access by placing woody debris on trailbed

OB-100

LF

CLEAR TREAD

WORK

18+36 Creek Ford – Canyon Creek

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

RECONSTRUCTION

CLEAR TREAD

WORK

38+41 Retread 38 ft to creek – Remove roots and grub trail trench walls back to open trail

38 LF

38+79 Creek Ford – Canyon Creek End Retread

39+87 New Sign Installation:

Scapegoat Wilderness Boundary

Small Metal Sign? Or Change? (Sec. 952)

41+74 Retread next 15 ft – remove roots and slope trail banks back (Sec. 915)

15 LF

42+02 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

43+83 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

48+28 Intermittent Steam Crossing

54+32 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

55+40 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

Retread 50 ft to station 55+90 – Remove roots and slope trail banks back (Sec. 915)

55+90 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

50 LF

End Retread |

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

RECONSTRUCTION

CLEAR TREAD

WORK

60+16 Retread / Construct 312 ft. to station 63+29 – Trail is sloughing downhill – Pull trail up hill 3 ft. along the trails current layout (Sec. 915)

312 LF

63+29 End Retread / Construction |

63+78 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

65+22 Intermittent Steam Crossing

66+42 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

66+51 Reroute / New Trail Construction 513 ft. to station 71+64 (Existing trail for 402 ft. is in swampy area – construct new trail up hill out of wet area)

Construct new trailbed 1 ft to either side of center line Full Bench Construction Waterbar Placement is not exact nor is there stakes in ground location – use judgment to place waterbars to optimize effectiveness

(Sec. 911, 912)

67+55 Center Line – Tree Removal Area

67+99 Center Line – Install New Waterbar (Rock or Treated Timber) (Sec. 922)

WB-1

68+32 Center Line

68+57 Center Line – Construct trail with a negative grade into, and a positive grade out of intermittent stream

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

69+08 Center Line

69+64 Center Line – Install New Waterbar (Rock or Treated Timber) (Sec. 922)

69+96 Center Line – Tree Removal Area

70+45 Center Line – Install New Waterbar (Rock or Treated Timber) (Sec. 922)

70+83 Center Line

71+19 Center Line – Install New Waterbar (Rock or Treated Timber) (Sec. 922)

71+64 End New Construction – Tie into existing trail

66+51 71+64

Obliterate existing trail by placing woody debris along trail approximately 402 ft.

OB-402

CLEAR TREAD

WORK

73+96 Retread 406 ft. to station 78+02 ----------

74+39 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

406 LF

74+89 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

78+02 End Retread |

78+02 Root Removal 231 ft. ----------

231 LF

80+33 End Root Removal |

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

80+33 Reroute / New Construction 1090 ft. to station 91+23 (Existing trail is low across bottom of hillside – trail is eroding due to water using it as a main channel and trail is in a boggy wet area)

Construct new trailbed 1 ft to either side of center line Full Bench Construction Waterbar Placement is not exact nor is there stakes in ground location – use judgment to place waterbars to optimize effectiveness

(Sec. 911, 912)

80+84 Center Line

81+47 Center Line

81+47 Construct Shallow Stream Ford - Construct trail with a negative grade into, and a positive grade out of ford crossing (SEE

DRAWING 912-5)

SSF-20

81+91 Center Line - Install New Waterbar (Rock or Treated Timber) (Sec. 922)

82+22 Center Line

82+75 Center Line - Install New Waterbar (Rock or Treated Timber) (Sec. 922)

83+25 Center Line

83+75 Center Line

84+25 Center Line

84+47 Center Line - Install New Waterbar (Rock or Treated Timber) (Sec. 922)

84+75 Center Line

85+25 Center Line

85+75 Center Line

86+25 Center Line - Install New Waterbar (Rock or Treated Timber) (Sec. 922)

86+75 Center Line

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

87+25 Center Line

87+75 Center Line

88+25 Center Line - Install New Waterbar (Rock or Treated Timber) (Sec. 922)

88+75 Center Line

89+25 Center Line

89+75 Center Line – Rocky Area – 148 ft. to station 91+23 (Heavy Excavation with rock breaking and possibility of needing some blasting - to be determined after starting the excavation)

90+25 Center Line - Install New Waterbar (Rock or Treated Timber) (Sec. 922)

90+65 Center Line

90+90 Center Line

91+23 End New Construction – Tie into existing trail

80+33 91+23

Obliterate existing trail – Do good job to help slow erosion by placing woody debris along trail – Backfill Trenches by caving in trench walls, use borrow material if needed (no borrow source is designated) - approximately 1114 ft

OB-

1114 LF

CLEAR TREAD

WORK

91+23 Retread / Root Removal 318 ft. to station 94+41 (Sec. 915, 985)

318 LF

318 LF

94+41 End Retread / Root Removal |

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

98+86 Retread 281 ft. to station 101+67 ----------

100+13 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

281 LF

101+27 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

101+67 End Retread |

103+16 Retread / Root Removal 199 ft. to station 105+15 (Sec. 915, 985)

199 LF

199 LF

105+15 End Retread / Root Removal |

107+32 Retread / Root Removal 186 ft. to station 109+18 (Sec. 915, 985)

186 LF

186 LF

109+18 End Retread / Root Removal |

109+18 Reroute / New Construction 119 ft. to station 110+37 - Construct new trailbed 1 ft to either side of center line Full Bench Construction (Sec. 911, 912)

109+55 Center Line

109+95 Center Line

110+37 End Reroute / New Construction Tie into existing trail

109+18 110+37

Obliterate existing trail by placing woody debris along trail approximately 150 ft.

OB-150

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

RECONSTRUCTION

CLEAR TREAD

WORK

110+37 Retread 83 ft. to next station ----------

83 LF

111+20 End Retread |

111+92 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

135+75 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

135+75 Retread as necessary / Rock and Root Removal / Drainage Maintenance - 193 ft. to station 137+68

(Area is a bad seep – trail passes through the best location, this is a rerouted trail as old trail used to pass through bellow – No possible other reroute) Spend some time here and try to clean up the bog as best you can…

*full solution is unknown and may not be possible – may just be a boggy area for 200 ft.*

- See Pictures (Sec. 915, 985, 991)

193 LF

193 LF

136+03 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

137+68 End Maintenance on boggy area |

138+84 Install New Waterbar (Native Timber) to reinforce natural stream flow

Remove existing WB and Replace moving it back 1 to 2 ft.

*10+ ft. long Waterbar (Sec. 922)

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

RECONSTRUCTION

140+47 Lopping / Clearing 751 ft. to station 147+98 (Canyon Creek Crossing) Use Loppers to remove regen trees from within the trail clearing limits – most or all regen was burned in recent fire (Sec. 911)

143+73 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

144+70 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

145+72 Existing Waterbar – Drainage Maintenance Cut out log blocking lead out ditch and improve (Sec. 991)

DM-1

EA

145+72 Retread / Rock Removal 148 ft. to station 147+20 Backfill Trenched trail by pulling the berm back onto the trail (Sec. 915, 985)

146+18 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

751 LF |

146+51 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

EA

| 148 LF

147+20 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

147+20 End Retread / Rock Removal |

147+98 End Lopping / Clearing |

147+98 Creek Crossing – Canyon Creek

148+45 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

RECONSTRUCTION

149+27 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

150+73 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

150+95 Install New Waterbar (Rock or Treated Timber) Long WB > 10 ft. (Sec. 922)

151+26 Install New Waterbar (Rock or Treated Timber) Long WB > 10 ft. with long lead out ditch to carry water to daylight (Sec. 922)

151+87 Retread / Brushing

331 LF / 2,514 LF

331 LF

155+18 End Retread / Continue Brushing | |

156+02 Drainage Maintenance – drain standing water pool (Sec. 991)

DM-1

EA

157+90 Drainage Maintenance – drain standing water pool (Sec. 991)

DM-1

EA

Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

2,514 LF

Unkn station look for stake in ground

Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

166+94 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

RECONSTRUCTION

166+94 Brushing / Lopping / Clearing Use Loppers to remove regen trees from within the trail clearing limits (Sec. 911)

168+55 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

170+23 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

170+23 Entering Older Burn Area Continue Brushing / Lopping / Clearing

176+24 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

176+78 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

177+01 Shallow Stream Crossing |

177+01 End Brushing / Lopping / Clearing |

180+07 Existing Waterbar – Drainage Maintenance

DM-1

180+76 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

181+54 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

182+23 Install New Waterbar (Rock or Treated Timber) Remove existing WB and Replace (Sec. 922)

182+71 Install New Waterbar (Rock or Treated Timber) Remove existing WB and Replace (Sec. 922)

186+56 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

CANYON CREEK TR. #16-3

SEGMENT B

TRAIL LOG

11/15/2007

RECONSTRUCTION

187+06 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

189+98 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

190+91 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

198+87 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

200+38 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

204+15 Existing Waterbar – Drainage Maintenance Reset Waterbar (Sec. 991)

DM-1

205+06 Install New Waterbar (Rock or Treated Timber) Remove existing WB and Replace (922)

207+06 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

214+23 Existing Waterbar – Drainage Maintenance 18 Waterbars Total Top of Switchbacks – Trail is in good shape! Waterbars in good shape and working well – All Waterbars need to be cleaned (Sec. 991)

DM-18

223+94 Retread 77 ft. to next station ----------

224+71 End Retread |

TRAIL LOG

11/15/2007

RECONSTRUCTION

225+86 Shallow Stream Ford – Rock Removal / Clearing Remove obstacle rocks from trailway (Sec. 985)

256 LF

228+42 Shallow Stream Ford – Remove logs including cut log placed on northern end (not doing any good)

228+42 Retread Open and improve bank on northern end where stream splits – Improve trailbed next 50 ft. to next small stream crossing (Sec. 915)

50 LF

232+36 Shallow Stream Ford – Dry Fork of N.F. River

232+64 Check Dam / Root Removal Place THREE (ROCK) Check Dams between Dry Fork and where the beaver dam is pushing water over the bank and onto the trail

Remove Roots obstructing the trail (Sec 915-2, 985)

CD-3

EA

100 LF

236+02 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

237+24 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

237+96 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

239+27 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

TRAIL LOG

11/15/2007

239+54 Retread 231 ft. to station 241+85 ----------

240+04 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

231 LF

240+68 Install New Waterbar (Rock or Treated Timber) (Sec. 922) WB-1

EA

241+85 End Retread |

241+96 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

243+25 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

244+37 Install New Waterbar (Rock or Treated Timber) Remove existing WB and Replace (922)

245+81 Existing Waterbar – Drainage Maintenance (Sec. 991) DM-1

267+14 Junction of Trails Canyon Cr #16 – Dry Fork #31 End of Project

End of Segment B End of Canyon Lake / Canyon Creek Project

VICINITY MAP

CANYON LAKE 165 / CANYON CREEK 16-3

PROJECT MAP

CANYON LAKE 165 / CANYON CREEK 16-3

ITEM
DESCRIPTION
CANYON LAKE 165 / CANYON CREEK 16-3
TRAIL LOG
LEGEND
DESCRIPTION
CONSTRUCTION

OR

CANYON LAKE “RIDGE” TR. #165
TRAIL LOG
CANYON LAKE “RIDGE” TR. #165
TRAIL LOG
CANYON LAKE “RIDGE” TR. #165
TRAIL LOG
CANYON LAKE “RIDGE” TR. #165
TRAIL LOG
CANYON LAKE “RIDGE” TR. #165
TRAIL LOG
CANYON LAKE “RIDGE” TR. #165
TRAIL LOG
CANYON LAKE 165 / CANYON CREEK 16-3
TRAIL LOG
LEGEND
DESCRIPTION
CONSTRUCTION

OR

CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG
CANYON CREEK TR. #16-3
TRAIL LOG