This document is an Addendum No. 3 issued by the City of Kissimmee for the Woodside Drainage Improvements Project, specifically soliciting Professional Services for Construction Engineering & Inspection (CEI) under Bid No. RFQ2025-007. The addendum provides clarifications and responses to six key questions from potential proposers, addressing technical details about the project, including FAA and stormwater permits, verification testing requirements, specification standards, airfield operational protocols, and subconsultant participation guidelines. The project appears to involve drainage improvements with work taking place within airport limits, requiring specific safety and operational compliance.
The addendum outlines critical requirements for contractors, including mandatory Airfield/Safety Training for foremen or crew leads, gate guard provisions during hauling, use of lime green cones to delineate construction limits, and mandatory check-ins with airport operations personnel before each construction phase. The governing technical specifications will be the FDOT January 2021 Standard Specifications for Road and Bridge Construction. Proposers are required to acknowledge receipt of the addendum by completing the appropriate section in the original Request for Qualifications (RFQ) document and submitting it with their proposal. Additional project-specific documents, including the FAA permit, Stormwater permit, and Geotechnical report, are available via a provided Dropbox link.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 18, 2025 Addendum No.3
Project: Woodside Drainage Improvements - Professional Services for Construction Engineering & Inspection (CEI) Bid No: RFQ2025-007
TO ALL PROPOSERS:
The following items are clarifications, corrections, additions, deletions and / or revisions, which shall take precedence over the original documents.
Question 1: Can you provide the FAA permit, Stormwater permit, and the Geotechnical report?
Answer. FFA permit provided in Dropbox link on addendum 2. Stormwater permit and Geotechnical report provided in Dropbox link on this addendum.
https://www.dropbox.com/scl/fo/abbckciuvbb3mwnljwsx0/ABMLcAH5MsGosnTeODY_N Ls?rlkey=kl9d2o6asxwt8xrz481hif8e4&st=gr2wxcvp&dl=0
Question 2: Will the CEI be required to perform verification testing for the TWA (Toho) portion of the work?
Answer: Yes, the CEI will be required to perform verification testing for the TWA (Toho) portion of the work.
Question 3: Will the drainage portion of the project adhere to the FDOT January 2022 specifications?
Answer: The governing standard specifications for Phase 2 of the Woodside Drainage Improvements Project are the FDOT January 2021 Standard Specifications for Road and Bridge Construction.
Question 4: Are there any clearance or training requirements for personnel operating within the airfield limits?
Answer: The contractor's foreman or crew lead will be required to go through an Airfield / Safety Training meeting with Airport operations. This meeting is expected to be less than 2 hours. The contractor shall have at least one representative that has gone through this training on site at all times work is being performed on the Airfield. Gate guards will be required if any airport security fence / gate is open during hauling conditions to ensure traffic not affiliated with construction cannot access the site. Lime https://www.dropbox.com/scl/fo/abbckciuvbb3mwnljwsx0/ABMLcAH5MsGosnTeODY_NLs?rlkey=kl9d2o6asxwt8xrz481hif8e4&st=gr2wxcvp&dl=0 https://www.dropbox.com/scl/fo/abbckciuvbb3mwnljwsx0/ABMLcAH5MsGosnTeODY_NLs?rlkey=kl9d2o6asxwt8xrz481hif8e4&st=gr2wxcvp&dl=0 green cones shall be used along all haul roads within airport property to delineate construction limits and reduce the risk of construction personnel driving into restricted airport areas.
Question 5: Is there a contract Special Provision applicable to work within the airfield limits, and if so, could you kindly provide it?
Answer: The CSPP and Airfield Safety / Phasing plan sheets have been provided and shall be followed at all times. Construction personnel shall check in with Shaun Germolus and/or Ramon Senorans with the Kissimmee Gateway Airport prior to the start of each phase of construction and if deviating from the approved plans.
Question 6: Could you specify which firms are disqualified from participating as subconsultants to the CEI?
Answer: Subconsultants shall adhere to the same rules, regulations, policies, standards, and procedures that apply to the Prime Consultant.
ACKNOWLEDGMENT OF ADDENDA:
1. The proposer shall acknowledge receipt of this addendum by completing the applicable section in the RFQ. The Proposer shall submit said Form with the proposal.
2. All other terms and conditions of the RFQ remain unchanged.
Brandon Durango Financial Resources and Systems Manager
ACKNOWLEDGMENT OF ADDENDA NO.(S) _________ (IF APPLICABLE)
(Signature)
COMPANY NAME _______________________________________
COMPANY ADDRESS _______________________________________
BY: _________________________ DATE:________________________