This is a Pre-Bid Questions document for Tyrone Township, Pennsylvania, addressing contractor inquiries regarding Phase 2 of the Municipal Building project. Phase 2 consists of constructing a community hall and paving the parking lot at 3129 Shermans Valley Road, Loysville, PA 17047. Sealed proposals were accepted via the PennBid Program until 5:00 p.m. on September 29, 2026, with bid opening held on the same date at the Loysville Community Center. An optional pre-bid meeting was conducted on August 25, 2026 at 1:00 p.m. at the project site. The contractor's responsibilities include excavation, foundation construction, stone laying, sidewalk installation with stone subbase and concrete, and utility line trenching, while Tyrone Township will mass grade the site and prepare the building pad. The Township has already acquired necessary permits and will provide them to the contractor; the contractor must file an NPDES Co-Permitee Acknowledgement Form. Sidewalk installation is designated for Phase 1 of the project. A site trailer is not required but may be accommodated if the contractor wishes to provide one.

The project budget will not be posted to maintain fair and competitive bidding, as the building has been reduced in size and complexity since the previous 2024 bid window. The successful bidder must post a performance bond equal to 100 percent of the bid price, a labor and material payment bond equal to 100 percent of the bid price, and a maintenance bond equal to 10 percent of the bid price. All workmen employed on the project must be paid prevailing minimum wages under Pennsylvania's Prevailing Wage Act, which applies to all contractors and subcontractors. Third-party testing is required as outlined in contract documents, with the contractor responsible for supplying testing reports and results to the engineer. Siding specifications will be arranged during construction, with bidders recommended to estimate mid-range metal siding. Civil drawings, including Land Development, PCSM, and ESC plan sets, are available in the public files on PennBid.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

August 31, 2026

Tyrone Twp Building – Phase 2

Pre-Bid Meeting Questions

What portion of ground work is the Contractor Responsible for?

The Township will mass grade the site and have the building pad ready for construction, the Contractor will be required to excavate, lay stone, and construct foundations for the building. Contractor will also be required to excavate area for sidewalk, install stone subbase, and pour concrete for the sidewalk installation.

Finally contractor to conduct trenching for utility lines. Any other site work not performed by Township Personnel will be bid at a later date.

Can civil drawings be added to the PennBid listing?

Land Development, PCSM, & ESC plan sets have been added to the public files.

Is there a budget for this project?

It is understood that this is the third time this project has been advertised for bids, the building has since been reduced in size and complexity since the 2024 bid window. To keep the bidding process fair and competitive for the Township, a budget will not be posted.

Will there be 3rd party testing?

Yes, the Contractor shall supply third party testing as outlined in the contract documents and submit testing reports and results to the Engineer.

What permits need to be acquired?

The necessary permits have been acquired for this project and will be provided to the Contractor. The Contractor will be required to file an NPDES (National Pollutant Discharge Elimination System) Co-Permitee Acknowledgement Form.

The well location is different on the building plan compared to the civil site plan, which is the correct location?

The civil site plan shows the correct location for the new well, the building plans will show the correct location when the first revision set is posted.

Which phase is the sidewalk to be installed on?

Sidewalk shall be installed during Phase 1 of the project.

Is there a requirement for manufacture/style of siding?

Siding will be arranged with Township during construction, for now it is recommended that bidders prepare an estimate for mid-range metal siding. The building plans illustrate the chosen color of exterior finishes.

Where can we find specifications for the foundations?

All building specs can be found within the building plans.

Is a site trailer required for this project?

A site trailer is not required. If the awarded contractor would like to bring one to the site, possible locations for it will be determined at that time.