This document is an Appendix I Time and Material (T&M) Proposal Form, which outlines a standardized protocol for contractors to submit repair, replacement, or upgrade proposals to an Authorized User (AU). The form provides a detailed mechanism for processing and approving time and material work requests, with specific steps for both standard and emergency repair scenarios. While the specific state or agency is not explicitly named, the document appears to be part of a structured procurement and maintenance agreement.
The T&M Proposal Form includes comprehensive sections for documenting work requirements, including contractor and authorized user identification, detailed justification for repairs, scope of work, labor and material cost breakdowns, and health and safety considerations. The protocol requires contractors to submit proposals within two business days, with the Authorized User reviewing and approving based on three key criteria: staff inability to perform the repair, acceptable scope of work, and reasonable pricing. The form allows for labor rate tracking across different technician classifications (e.g., Elevator Mechanic Straight Time, Elevator Apprentice Overtime), material markup calculations, and a systematic approach to invoicing and payment verification.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7100423271CheckHydraulic.pdf | ||
| 7100423271SalesReport.xlsx | XLSX spreadsheet | |
| 7100423271ContractTemplate.pdf | ||
| 7100423271Webinar.pdf | ||
| 7100423271SpecEsc.pdf | ||
| 7100423271FAQ.pdf | ||
| 7100423271ra.pdf | ||
| 7100423271SpecHydraulic.pdf | ||
| 7100423271contractorinfo.pdf | ||
| 7100423271pricing.xlsx | XLSX spreadsheet | |
| 7100423271HowToUse.pdf | ||
| 7100423271definition.xlsx | XLSX spreadsheet | |
| 7100423271SpecTraction.pdf | ||
| 7100423271SpecMisc.pdf | ||
| 7100423271pm.pdf | ||
| 7100423271CheckEsc.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX I
Time and Material (T&M) Proposal Form
7100423271 Appendix I – Time and Material Proposal Form
Directions: Refer to page 2 of the T&M Proposal Form for detailed instructions on completing this form.
CONTRACTOR (Complete Sections I - IV Below):
Section I: T&M Identification and Contact Information
AUTHORIZED USER NAME, CONTACT PERSON, PHONE: MINI-BID NUMBER:
T&M NUMBER:
CONTRACTOR NAME, CONTACT PERSON, PHONE: T&M TYPE (check one below) Request for Pre-approval (work to be completed)
Emergency (repairs completed, documentation incl.)
Section II: T&M Justification: (CONTRACTOR to provide a detailed justification that explains the need for the repair/scope of work.)
Building #:
Equipment ID #:
Equipment Description:
Describe Problem or Deficiency:
Describe Troubleshooting Performed:
Section III: T&M Scope of Work: (CONTRACTOR to provide a detailed description of the proposed scope of work.)
Section IV: T&M Not-to-Exceed Quote:
A. Labor
Description (indicate technician classification Contract)
Estimated Labor Hours
Contracted Hourly Labor Rate Total Labor Quote
Elevator Mechanic Straight Time Elevator Apprentice Straight Time Elevator Mechanic Overtime Elevator Apprentice Overtime
Total Labor Quote:
B. Material, Equipment and Subcontractor Costs (Please list material or components. Subcontractor costs must include a detailed breakdown of labor hours, labor rate, and material costs. Attach a separate itemized list, if necessary.)
Description of Major Components Quantity Total Estimated Cost
Material Markup (%)
Less Discounts Allowed Total Material Quote
Subcontractor costs % Freight / Shipping and Handling N/A N/A
Total Material, Equipment and Subcontractor Quote:
Total T&M Not-to-Exceed Quote for Scope of Work (A+B):
Section V: AUTHORIZED USER HEALTH & SAFETY JUSTIFICATION (AU Use Only):
The scope of work detailed below included in this proposal is necessary for the direct health and/or safety of the clients (if applicable), employees, and/or visitors.
Initials Required (AU Designee)
Authorized User Designee: Contractor Representative:
Title: Title:
Date: Date:
Signature: ________________________________________ Signature: ____________________________________
APPENDIX I
Time and Material (T&M) Proposal Form
7100423271 Appendix I – Time and Material Proposal Form
Directions for Completing the T&M Proposal Form The CONTRACTOR shall complete Sections I through IV on page 1. In Section I, the CONTRACTOR shall provide a T&M identification number and indicate if this proposal is for an Emergency T&M response. Authorized User (AU) will not consider approval of this T&M if any sections or fields are omitted by the CONTRACTOR. The CONTRACTOR shall sign the proposal at the time it is submitted to the AU for approval; the AU designee shall sign the proposal. Please expand any sections and/or use additional pages as necessary to provide the required detailed T&M repair information. The AU reserves the right to alter the T&M Proposal Form as necessary.
Summary of T&M Protocol Step 1: When a need is identified by the Contractor or the AU, the Contractor shall note any repairs necessary and provide a T&M Proposal within two (2) business days via fax/email to the AU for repairs, replacements, or upgrades. Once the T&M proposal is received from the Contractor, the AU determines if the work can be performed by internal staff. If the work cannot be performed internally, the AU shall process the T&M “Not-to-Exceed” proposal developed by the Contractor, following the subsequent steps outlined below.
Step 2: The AU reviews the T&M Proposal to ensure that it meets the terms/rates under the AU Mini-bid Agreement. The AU must also review and ensure that the proposal meets the following three (3) criteria for approval: 1) The AU staff is unable to perform the required repair and the Contractor’s services are therefore needed; 2) The scope of work is acceptable; and 3) The price quote is reasonable.
Step 3: AU Designee shall initial the Authorized User Health & Safety Justification Statement in Section V indicating the need for the repair and forwards the completed, Contractor-signed (electronic signature is acceptable) T&M Proposal Form and any related documentation via e-mail to mailto: ______________________.
Step 4: AU shall consult with any necessary personnel or consultants as needed to review and evaluate the T&M Proposal Form. If additional information is needed to complete the T&M review process, the AU will e-mail the Contractor. .
Step 5: If approved, the AU designee signs the T&M Proposal form and notifies the Contractor to proceed and provides the signed T&M Proposal.
Step 6: Contractor performs T&M work.
Step 7: AU ensures that the work has been performed to its satisfaction and make any additional notification as necessary (e.g., AU Finance Office).
Step 8: Contractor submits an invoice, with a copy of the AU-approved T&M Proposal Form, repair service tickets, material cost supporting documentation/receipts, and invoices from subcontractors (if utilized), to the email address _________________.
Step 9: AU reviews the invoice to ensure that: 1) the actual hours worked and documented in the invoice and service ticket(s) is accurate as compared to the labor hours logged by the Contractor in the AU sign-in/out log book; 2) the materials billed match the costs indicated in the material cost supporting documentation; and 3) the Contractor billed at the correct labor rate(s) and applied the correct material markup as stated in Mini-bid Agreement. If the invoice is acceptable, AU shall authorize payment in accordance with its internal procedures (e.g., FileNet / SFS).
Emergency T&M Post-Audit Review and Approval Process:
This process follows the T&M Protocol with the following deviations:
The AU will immediately call in the Contractor to perform the repair rather than waiting for pre-approval.
After the Emergency T&M repair is complete, the Contractor shall then submit the related invoice to AU e-mail at:
________________________ with a completed T&M Proposal Form and a copy of all applicable service ticket(s) and material cost supporting documentation. The Section V: T&M Not-to-Exceed Quote section of the T&M Proposal Form shall reflect the actual costs associated with the Emergency T&M repair as detailed in the invoice submitted.
The AU designee forwards the completed, Contractor and AU-signed T&M Proposal Form, the applicable service ticket(s) and material cost supporting documentation, and a copy of the AU sign-in/out log book for the applicable date(s) of service via e-mail to mailto: _________________ in accordance with its internal procedures.
mailto:
mailto:mailto:
| CONTRACTOR NAME CONTACT PERSON PHONE: |
| MINIBID NUMBER: |
| TM TYPE check one below: |
| CONTRACTOR NAME CONTACT PERSON PHONE_2: |
| Building Equipment ID: |
| Equipment Description: |
| Describe Problem or Deficiency: |
| Section III TM Scope of Work CONTRACTOR to provide a detailed description of the proposed scope of work: |
| Section IV TM NottoExceed Quote: |
| Elevator Mechanic Straight Time: |
| Estimated Labor HoursElevator Mechanic Straight Time: |
| Contracted Hourly Labor RateElevator Mechanic Straight Time: |
| Total Labor QuoteElevator Mechanic Straight Time: |
| Elevator Apprentice Straight Time: |
| Estimated Labor HoursElevator Apprentice Straight Time: |
| Contracted Hourly Labor RateElevator Apprentice Straight Time: |
| Total Labor QuoteElevator Apprentice Straight Time: |
| Elevator Mechanic Overtime: |
| Estimated Labor HoursElevator Mechanic Overtime: |
| Contracted Hourly Labor RateElevator Mechanic Overtime: |
| Total Labor QuoteElevator Mechanic Overtime: |
| Elevator Apprentice Overtime: |
| Estimated Labor HoursElevator Apprentice Overtime: |
| Contracted Hourly Labor RateElevator Apprentice Overtime: |
| Total Labor QuoteElevator Apprentice Overtime: |
| Total Labor QuoteTotal Labor Quote: |
| Description of Major ComponentsRow1: |
| QuantityRow1: |
| Total Estimated CostRow1: |
| Less Discounts Allowed: |
| Total Material Quote: |
| Description of Major ComponentsRow2: |
| QuantityRow2: |
| Total Estimated CostRow2: |
| Less Discounts Allowed_2: |
| Total Material Quote_2: |
| Description of Major ComponentsRow3: |
| QuantityRow3: |
| Total Estimated CostRow3: |
| Less Discounts Allowed_3: |
| Total Material Quote_3: |
| QuantitySubcontractor costs: |
| Total Estimated CostSubcontractor costs: |
| Less Discounts Allowed_4: |
| Total Material Quote_4: |
| Total Estimated CostNA: |
| Less Discounts AllowedNA: |
| Total Material QuoteNA: |
| Total Material QuoteTotal Material Equipment and Subcontractor Quote: |
| undefined: |
| Initials Required: |
| Authorized User Designee: |
| Contractor Representative: |
| Title: |
| Title_2: |
| Step 8 Contractor submits an invoice with a copy of the AUapproved TM Proposal Form repair service tickets material cost: |
| After the Emergency TM repair is complete the Contractor shall then submit the related invoice to AU email at: |
| tickets and material cost supporting documentation and a copy of the AU signinout log book for the applicable dates: |
| Mailto:: |
| Check Box2: Off |
| Check Box3: Off |
File details come from the government source that posted it. Updated .