832571388 QASP Attachment 3.docx
DOCX document 49 KB Posted
- Attached to
- Mechanicsburg RF EOL Equipment Upgrade Federal contract opportunity
- Solicitation number
- HC102825R0076
- Issued by
- Defense Information Systems Agency
About this file
This document is a Quality Assurance Surveillance Plan (QASP) for a Data Center Mechanicsburg Raised Floor End of Life Equipment Upgrade project. The QASP outlines the government's systematic method for evaluating contractor performance, with 100% inspection as the primary surveillance method. Key performance standards include installation with no required rework, substantial completion verified through SEC inventory submission and system demonstration, and contract close-out requiring submission of O&M pages, spare parts, equipment training, and as-built documents.
The performance will be evaluated using a rating scale from Exceptional to Unsatisfactory, with contractors expected to meet contractual requirements consistently. The Contracting Officer's Representative (COR) will conduct continuous technical oversight, document performance, and report any issues to the Contracting Officer. The project is associated with the Defense Information Systems Agency (DISA), and the solicitation requires contractors to have NAICS code 333415 in their SAM.gov registration. Proposal submissions are due by 12 September 2025 at 2:00 PM Central Time, with questions accepted until 28 August 2025.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 26 24 15 - Computer Room PDUs.pdf | ||
| Q and A HC102825R0076 Part 3 Full.docx | DOCX document | |
| Q and A HC102825R0076 Part 2.docx | DOCX document | |
| Specifications - FY25 RF EOL.pdf | ||
| Installation 1.pdf | ||
| Seismic.pdf | ||
| Q and A HC102825R0076 Part 1.docx | DOCX document | |
| 832571388 PWS Mechanicsburg Raise Floor Attachment 1.docx | DOCX document | |
| HC102825R0076 Solicitation.pdf | ||
| Wage Decision 2015 4225 Attachment 5.docx | DOCX document | |
| 832571388 CLIN Pricing Sheet Attachment 2.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
1. Contract or Task Order Title Data Center Mechanicsburg Raised Floor End of Life Equipment Upgrade
2. Purpose:
This QASP provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
· What will be monitored?
· How monitoring will take place.
· Who will conduct the monitoring?
· How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the QASP should recognize that unforeseen and uncontrollable situations may occur.
This QASP is a “living document” and the Government may review and revise it on a regular basis. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
3. Roles and Responsibilities:
The following personnel shall oversee and coordinate surveillance activities.
Program/Project Manager (PM) – The PM provides program oversight and supports the COR’s performance assessment activities.
Contracting Officer (KO) – The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine the final assessment of the contractor’s performance.
Contracting Officer’s Representative (COR) – The COR is responsible for providing continuous technical oversight of the contractor’s performance. The COR uses the QASP to conduct the oversight/surveillance process. The COR shall keep a Quality Assurance file that accurately documents the contractor’s actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the KO. The COR is required to provide an annual performance assessment to the KO which will be used in documenting past performance. The QASP is the primary tool for documenting contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government’s behalf.
Other Key Government Personnel- Joe Mercik, (717) 918-6181, will be the primary and alternate site POC who will provide information that helps the COR monitor contractor performance.
4. Primary Method of Surveillance: There will be 100% Inspection.
· 100 Percent Inspection. This is usually only the most appropriate method for infrequent tasks or tasks with stringent performance requirements, e.g., where safety or health is a concern. With this method, performance is inspected/evaluated at each occurrence. One hundred percent inspection is too expensive to be used in most cases.
· Random Sampling. This is usually the most appropriate method for recurring tasks. With random sampling, services are sampled to determine if the level of performance is acceptable. Random sampling works best when the number of instances of the services being performed is very large and a statistically valid sample can be obtained. Computer programs may be available to assist in establishing sampling procedures.
· Periodic Inspection: These services are monitored weekly, monthly, quarterly, semiannually, annually, etc. Periodic types of activities are perfect for periodic inspection because not only are they infrequent, but there is normally a predetermined, specified time frame within which the tasks must be accomplished. Therefore, you know exactly when to conduct the evaluations. Periodic inspections automatically become 100 percent evaluations or "100 percent checks." Inspections should be divided and scheduled by frequency: annual, semiannual, quarterly, monthly, weekly and as required. Sometimes services are required for which the time or frequency cannot be predicted, such as accident investigations, one-time special tasking by higher headquarters, etc. These would be labeled "as required inspections." Others are known and predictable such as the quarterly status report or the monthly travel report currently included in some DISA service contracts.
· Customer Input. Although usually not a primary method, this is a valuable supplement to more systematic methods. For example, in a case where random sampling indicates unsatisfactory service, customer complaints can be used as substantiating evidence. In certain situations where customers can be relied upon to complain consistently when the quality of performance is poor, e.g., dining facilities, building services, customer surveys and customer complaints may be a primary surveillance method, and customer satisfaction an appropriate performance standard. In all cases, complaints should be documented, preferably on a standard form.
Surveillance Matrix
The Surveillance Matrix (Appendix 1) is the list of performance objectives and standards that must be performed by the contractor. This matrix details the method of surveillance the COR will use to validate and inspect these performance elements. Inspection of each element will be documented in the COR file.
Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performance surveillance, using this QASP, to determine the quality of the contractor’s performance as it relates to the performance element standards. The AQL performance Standard Table should be used to form the foundation of the COR’s inspection checklist.
5. Performance Standards:
| Performance Standard |
| Acceptable Quality Level (AQL) |
| Method of Surveillance |
| Installation |
| Performance occurs with no required re-work 100% of the time. |
| Routine inspection during installation; 100% completion inspection prior to acceptance. |
| Substantial Completion |
| SEC Inventory submission; final Commissioning; system demonstration; and provision of equipment warranty information. |
| 100% review and validation of 1) SEC Inventory 2) function of all SEC at commissioning 3) commissioning/TAB reports and 4) all equipment warranty information. |
| Contract Close Out |
| All O&M Pages submitted; all spare parts/keys/materials submitted; all equipment training completed; and As-built documents submitted. |
| 100% inspection and validation of all 1) O&M Pages 2) confirmation of receipt of parts/keys/materials 3) training on all systems provided and 4) system walk through validating as-built documents. |
6. Documenting Performance:
Acceptable Performance.
The Government shall document positive performance. A Performance Assessment Report (PAR) template is attached (Appendix 2). Any report may become part of the supporting documentation for fixed price payments, award/incentive fee payments, Contractor Performance Assessment Reporting System (CPARS) entries, or other actions. Government acceptance of services permits the contractor to invoice for the service fee.
Unacceptable performance.
Unacceptable contractor performance can be identified by customer complaints (Appendix 3) or upon schedule surveillance evaluations. When unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication and may be through the PAR template (Appendix 2). The COR shall document the discussion and place it in the COR file and provide a copy to the KO.
When the COR determines formal written communication is required, the COR shall prepare a Corrective Action Report (CAR). The CAR is forwarded to the KO for dissemination to the contractor. A CAR template is attached to this QASP (Appendix 4).
The contractor shall acknowledge receipt of the CAR in writing. The CAR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CAR will also state how long after receipt the contractor has to present this corrective action plan to the KO and COR. The Government may withhold payment for services until corrective action is taken. The Government shall review the contractor's corrective action plan to determine acceptability. Upon Government acceptance of the corrected services the contractor will be permitted to invoice for the service fee.
Any CAR may become a part of the supporting documentation for contract payment deductions, fixed fee deductions, award fee nonpayment, CPARS or other actions deemed necessary by the KO.
7. Mandatory or regulatory compliance items:
The contractor will provide initial proof of compliance with regulatory and compliance items contained in the contract. The Contracting Officer's Representative (COR) and the Contracting Officer (KO) will evaluate the initial submission and will conduct ad hoc reviews of the contractor's compliance throughout the remainder of the contract. The contractor will monitor compliance as required by FAR 52.222-50, Combating Trafficking in Persons, and report any issues to the KO. The contractor shall inform its employees in writing of contractor employee whistleblower rights and protections as required by DFARS 252.203-7002, Requirement to Inform Employees of Whistleblower Rights. The contractor shall also ensure that the clause is included in all subcontracts.
8. Acceptable Quality Level (AQL):
· 100% equipment provided and functioning as required.
· No major deficiencies noted.
· On time
9. Evaluation Method:
There will be a 100% review of the submittals by Technical POC, as defined by PWS. Once the package has been approved of and all comments have been addressed, the contractor can proceed onto the installation phase. At the close-out of the project a walkthrough will be conducted to verify that the installation was properly done and that there are no deficiencies. Any existing deficiencies shall be added to a punch list and will be addressed in a timely manner.
10. Performance Rating
In evaluating the quality of contractor’s performance, the following performance ratings may be used (same as CPAR ratings).
| Rating |
| Definition |
| Note |
| Exceptional |
| Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective. |
| To justify an Exceptional rating, identify multiple significant events and state how they were of benefit to the Government. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified. |
| Very Good |
| Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective. |
| To justify a Very Good rating, identify a significant event and state how it was a benefit to the Government. There should have been no significant weaknesses identified. |
| Satisfactory |
| Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory. |
| To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract/order. There should have been NO significant weaknesses identified. A fundamental principle of assigning ratings is that contractors will not be evaluated with a rating lower than Satisfactory solely for not performing beyond the requirements of the contract/order. |
| Marginal |
| Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented. |
| To justify Marginal performance, identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the Government. A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g., management, quality, safety, or environmental deficiency report or letter). |
| Unsatisfactory |
| Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective. |
| To justify an Unsatisfactory rating, identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the Government. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g., management, quality, safety, or environmental deficiency reports, or letters). |
Appendix 1 - Surveillance Matrix
Performance Standards Acceptable Quality Levels Methods of Calculation
| Surveillance |
| Results/Ratings |
Information Technology (IT) Service Integration and Delivery Performance Management
High level of (xyz) satisfaction with Contractor delivery management of IT Services (includes the Service Desk services and the SITEC).
Target Criteria:
90% of all survey respondents are Satisfied, More Than Satisfied, or very Satisfied
Minimum Acceptable:
> 85% of all survey respondents are Satisfied, More Than Satisfied, or Very Satisfied with Contractor delivery management of all SITEC IT Services Calculation:
The number of users who were Satisfied, More Than Satisfied, or Very Satisfied divided by the total number of completed surveys returned.
At least XX(insert number) Government personnel must complete and return surveys for the results to have at least a 90% confidence factor with a 5% error rate.
Measurement Interval – The Measurement Interval is three (3) months for the first year and then every six (6) months thereafter.
Measurement Period – The Measurement Period begins at 00:01 on the first day of the month and ends at 24:00on the last day of the month.
Source of Measurement Data – Data will be collected from management surveys containing satisfaction criteria specified by (xyz) that are either developed internally by (xyz) personnel or by a (xyz) selected impartial 3rd party.
Method of Surveillance – Customer feedback. The Government will issue customer satisfaction surveys to designated Government SITEC management representatives from (xyz) (Contractors cannot participate), , and survey responses will be tabulated to determine overall satisfaction with Contractor delivery management of IT Services using a five (5) category scale. The scale is: Dissatisfied, Less than Satisfied, Satisfied, More than Satisfied, Very Satisfied.
Timing of Measurement – Measurements are taken within five (5) days of the end of the Measurement Period.
Reporting Frequency: - Reporting to commence upon Contract Award and continue throughout the Period of Performance.
Monthly reporting of Service Level Agreement (SLA) and / or QASP attainment to periods survey. Quarterly survey reporting from (xyz) during the first year, semi-annual thereafter.
(Exceptional Very Good Satisfactory Marginal Unsatisfactory)
(A rollup of assessment of the Surveillance Inspection Results to develop an overall rating for this objective)
Appendix 2 – Performance Assessment Report
PERFORMANCE ASSESSMENT REPORT (PAR)
(If more space is needed, use reverse and identify by number)
| 1. CONTRACT/TASK ORDER NUMBER |
| 2. CONTRACTOR |
| 3. TYPE OF SERVICES |
4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE AND DATE
| 5. COR PHONE |
| 6. SUSPENSE DATE |
I. PERFORMANCE
7. |_| DEFICIENCY (CHECK ALL BOXES THAT APPLY)
|_| NEW
|_| REPEAT
|_| NO DEFICIENCY NOTED
8. SERVICES SUMMARY or PWS PARAGRAPH ITEM REVIEWED
| 9. BRIEF DESCRIPTION OF DEFICIENCY (IF DEFICIENCY BOX WAS CHECKED) |
| 10. DETAILED PERFORMANCE ASSESSMENT |
II. CONTRACTOR VALIDATION
11. CONTRACTOR REPRESENTATIVE |_| CONCUR |_| NON-CONCUR
12. CORRECTIVE ACTION ESTIMATED COMPLETION DATE
13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF RECURRENCE OR REASON FOR NON-CONCURRENCE OF COR CITED DEFICIENCY
III. ACTION CORRECTED
14. |_| CONCUR |_| NON-CONCUR COR SIGNATURE AND DATE
15. COR REMARKS (REQUIRED)
6. CONTRACTOR REPRESENTATIVE REMARKS
Appendix 3 – Customer Complaint Record
CUSTOMER COMPLAINT RECORD
DATE/TIME OF COMPLAINT
SOURCE OF COMPLAINT
ORGANIZATION
BUILDING NUMBER
INDIVIDUAL
PHONE NUMBER
NATURE OF COMPLAINT
CONTRACT REFERENCE
VALIDATION
DATE/TIME CONTRACTOR INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR
RECEIVED/VALIDATED BY
Appendix 4 – Corrective Action Report
CORRECTIVE ACTION REPORT (CAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACTOR
2. CONTRACT NUMBER
3. TYPE OF SERVICES
4. FUNCTIONAL AREA
5. SUSPENSE DATE
6. CONTROL NUMBER
7. DEFICIENCY |_| MAJOR |_| MINOR
FINDING:
FINDING IMPACT:
Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the deficiency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.
8. QUALITY ASSURANCE PERSONNEL (COR)
TYPED NAME AND GRADE
SIGNATURE AND DATE
9. ISSUING AUTHORITY
TYPED NAME AND GRADE
SIGNATURE AND DATE
10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT RECURRENCE
11. COR DETERMINATION
|_| ACCEPTED |_| REJECTED
12. CLOSE DATE
Controlled By: DISA Controlled By: PSD/PS8332 CUI Category: PROCURE Distribution/Dissemination Control: FEDCON POC: disa.scott.ocfo.mbx.wcf-p2p-internal-upr@mail.mil
Template updated August 2024