This is a solicitation for the Orion Main Engine (OME). NASA/JSC is seeking proposals for the OME no later than June 11, 2020. A virtual pre-proposal conference will be held on April 2, 2020. The solicitation is for OME certification to be completed by September 15, 2024 under CLIN 0001A, and production of four engines under CLIN 0002A to meet the dates outlined in Attachment L-9A. Offerors may also propose accelerated schedules for certification under CLIN 0001B by June 30, 2024 and production under CLIN 0002B. The solicitation also includes CLINs for special studies and tasks under CLIN 0003 and storage services under CLIN 0004. Pricing templates are provided in Attachments L-6A and L-6B to facilitate cost proposals for the baseline and accelerated schedules. The model contract and additional solicitation requirements are provided in Volume V.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Ashley H. Chaves
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to update the RFP. See the Change log on Pages 2-22.
NASA Johnson Space Center 2101 NASA Parkway Houston TX 77058-3696
80JSC020R0031
See Block 16C
03/19/2020
1 22
4/17/2020
80JSC020R0031 Amendment 2
RFP Change Log
# Section Reference Page
From To
1 B CLIN 0002 OME
PRODUCTION
B-2 The values shown in the Unit Price Based on
Ordering Quantity” column represent the total price of the order, including quantity discounts, for ordering multiple engines in a Delivery Order that the respective fiscal year.
The values shown in the Unit Price Based on
Ordering Quantity” column represent the total price of the order, including quantity discounts, for ordering multiple engines in a Delivery Order that the respective contract year.
2 B CLIN 0004 OME
STORAGE
B-5 Bonded storage facility space under CLIN 0004 will be procured via a FFP task order. NASA reserves the right to determine, on an as needed basis, if there is a need for the OME(s) to be stored.
If it is determined that additional days are required to store the OME prior to DD Form 250 date, the appropriate contract year storage price per day will be multiplied by the number of days of storage needed times the number of engines A subsequent amendment to the FFP task order will be executed.
Bonded storage facility space under CLIN 0004 will be procured via a FFP task order. No later than 30 calendar days prior to Milestone 2, Pre-Ship
Hardware Acceptance Review, NASA will notify the contractor if storage is required. NASA reserves the right to determine, on an as needed basis, if there is a need for the OME(s) to be stored.
If it is determined that additional days are required to store the OME prior to DD Form 250 date, the appropriate contract year storage price per day will be multiplied by the number of days of storage needed times the number of engines. A subsequent amendment to the FFP task order will be executed.
3 H OME
CERTIFICATIO
N & ENGINE
PRODUCTION
PAYMENTS,
MILESTONE
EVENTS, AND
COMPLETION
CRITERIA
H-7 Table II.A.1-2B: OME Accelerated Production
Payment Schedule Per Engine (First Lot Buy - Four
Engines)
Engine Production Milestone 1, Authority to
Proceed
Engine Production Milestone 3, Post Flight
Assessment Review
Table II.A.1-2B: OME Accelerated Production
Payment Schedule Per Engine (First Lot Buy - Four
Engines)
Engine Production Milestone 0, Authority to
Proceed
Removed Milestone 4, Post Flight Assessment
Review
4 H H-8 Table II.A.1-2B2: OME Accelerated Production
Payment Schedule Per Engine (Second Lot Buy-
Four Engines)
Engine Production Milestone 1, Authority to
Proceed
Table II.A.1-2B2: OME Accelerated Production
Payment Schedule Per Engine (Second Lot Buy-
Four Engines)
Engine Production Milestone 0, Authority to
Proceed
5 H H-9 9After successful completion of OME certification, the total of production milestone payments prior to and including the Production Milestone 2, Pre-Ship
Hardware Acceptance Review, for each production engine shall not exceed 70% of the total price of each engine.
9After successful completion of OME certification, the total of production milestone payments prior to and including the Production Milestone 2, Pre-Ship
Hardware Acceptance Review, for each production engine shall not exceed 90% of the total price of each engine.
6 H H-9 10Production Milestone 3, Post-Ship Hardware
Acceptance Review, milestone payments for each engine must equal at least 20% of the total price of each engine.
10Production Milestone 3, Post-Ship Hardware
Acceptance Review, milestone payments for each engine must equal at least 10% of the total price of each engine.
7 H H-9 11Production Milestone 4, Post-Flight Assessment
Review, milestone payments for each engine must equal at least 5% of the total price of the engine.
11 Reserved
8 H H-10 14For future lot buys, the total of production milestone payments prior to and including the
Production Milestone 2, Pre-Ship Hardware
Acceptance Review, for each production engine shall not exceed 75% of the total price of each engine.
14For future lot buys, the total of production milestone payments prior to and including the
Production Milestone 2, Pre-Ship Hardware
Acceptance Review, for each production engine shall not exceed 90% of the total price of each engine.
9 I 52.222-46
EVALUATION
OF
COMPENSATIO
N FOR
PROFESSIONAL
EMPLOYEES
(FEB 1993)
I-3 52.222-46 EVALUATION OF COMPENSATION
FOR PROFESSIONAL EMPLOYEES (FEB 1993)
DELETED
10 I 52.223-3
HAZARDOUS
MATERIAL
IDENTIFICATIO
N AND
MATERIAL
SAFETY DATA
(JAN 1997) (ALT
1) (JUL 1995)
I-3 52.223-3 HAZARDOUS MATERIAL
IDENTIFICATION AND MATERIAL SAFETY
DATA (JAN 1997) (ALT 1) (JUL 1995)
Removed from Incorporated by Reference
11 I I-15 CLAUSE ADDED AS FULL TEXT 52.223-3
HAZARDOUS MATERIAL IDENTIFICATION
AND MATERIAL SAFETY DATA (JAN 1997)
(ALT 1) (JUL 1995)
12 I 52.232-19
AVAILABILITY
OF FUNDS FOR
THE NEXT
FISCAL YEAR
(APR 1984)
I-28 52.232-19 AVAILABILITY OF FUNDS FOR
THE NEXT FISCAL YEAR (APR 1984)
Funds are not presently available for performance under this contract beyond. The
Government’s obligation for performance of this contract beyond that date is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise for performance under this contract beyond, until funds are made available to the Contracting Officer for performance and until the Contractor receives notice of availability, to be confirmed in writing by the Contracting Officer.
52.232-19 AVAILABILITY OF FUNDS FOR THE
NEXT FISCAL YEAR (APR 1984)
Funds are not presently available for performance under this contract beyond TBD. The Government’s obligation for performance of this contract beyond that date is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the
Government for any payment may arise for performance under this contract beyond TBD , until funds are made available to the Contracting Officer for performance and until the Contractor receives notice of availability, to be confirmed in writing by the
Contracting Officer.
13 I 1852.228-75
MINIMUM
INSURANCE
COVERAGE
(OCT 1988)
I-34 INSERTED 1852.228-75 MINIMUM INSURANCE
COVERAGE (OCT 1988)
14 J-1 Title Page 1 March 13, 2020 April 17, 2020
15 J-1 Section 2.2
2nd Paragraph
7 Post-Flight Assessment Report Post-Flight Assessment Review
16 J-1 Section 2.2
3rd Paragraph
7 PFAR Deleted PFAR
17 J-1 Section 2.2
3rd Paragraph
7 PFAR Deleted PFAR
18 J-1 Section 2.3 8 N/A Added “preparing the OME Post-Flight Performance
Reconstruction Analysis Report and conducting the
OME Post-Flight Assessment Review;”
19 J-1 Section 8.2.2
Table 2, 6. o.
26 Decontamination Plan, for removing hazardous material from the OME after ATP hot fire and prior to shipping to Bremen, Germany, has been negotiated and accepted by ESA and its prime contractor and ready to be baselined after review comments are incorporated.
Decontamination Plan, for removing hazardous material from the OME after ATP hot fire and prior to shipping to Bremen, Germany or Marshall Space
Flight Center (MSFC), has been negotiated and accepted by ESA and its prime contractor or the designated MSFC organization(s), and ready to be baselined after review comments are incorporated.
20 J-1 Section 8.3
4th Paragraph
31 PFAR Deleted PFAR
21 J-1 Production
Milestone 3 –
Post-Ship HAR
36 Production Milestone 3 – Post-Ship HAR 8.3.4 PRODUCTION MILESTONE 3 – POST-
SHIP HAR
22 J-1 Old Section 8.3.4 37 Section 8.3.4 was Milestone 4 - Post-Flight
Assessment Review because Milestone 3 – Post-
Ship HAR section number was inadvertently deleted. Section 8.3.4 is now Milestone 3 –
Post-Ship HAR.
Deleted the entire Milestone 4 – Post-Flight
Assessment Review section, the old Section 8.3.4.
23 J-1 Section 12.2.3
1st Paragraph
55 The Contractor shall be responsible for transporting the OME to Airbus Defence &
Space in Bremen, Germany, in accordance with
NPR 6000.1
The Contractor shall be responsible for transporting the
OME to Airbus Defence & Space in Bremen, Germany, or to MSFC in Alabama, in accordance with NPR 6000.1
24 J-2 Title Page 1 March 13, 2020 April 17, 2020
25 J-2 OME-M-003
7.
1 The OME Work Plan will establish the milestones schedules and payments milestones;
propellant quantities and schedule; hardware list;
and delivery schedules.
The OME Work Plan will establish the milestones schedules and payments milestones; propellant quantities and schedule; and hardware list.
26 J-2 OME-M-003
13.3
2 Note: Post-Flight Assessment Review to be performed only after each of the first four engines have flowin into orbit.
TEXT DELETED
27 J-2 OME-T-093
6.
1 OME Post-Flight Performance Reconstruction
Analysis Report OME Post-Flight Performance Reconstruction
Analysis Report and OME Post-Flight Assessment
Review
28 J-2 OME-T-093
7.
1 N/A: Addition at end of section A Post-Flight Assessment Review (FPAR) will be held once the report has been completed. The PFAR evaluates how well mission objectives were met during a mission and identifies all flight and ground system anomalies that occurred during the flight and determines the actions necessary to mitigate or resolve the anomalies for future flights of the same engine design.
29 J-2 OME-T-093
13.3
2 N/A: Addition at end of section The PFAR’s entrance criteria, accomplishment criteria, and applicable products are shown in the table below.
Entrance
Criteria
Accomplishme nt Criteria
Applicable
Products
1. All anomalies that occurred during the mission, as well as during preflight testing, countdown, and ascent, are dispositioned.
2. Post-flight analyses have been completed and ready for review.
3. Problem reports, corrective action requests, and post-flight anomaly records pertaining to the OME are completed.
Formal final report documenting flight performance and recommendation s for future missions is complete and adequate.
Post-Flight
Performanc e
Reconstruct ion
Analysis
Report
All anomalies have been adequately documented and dispositioned.
The impact of anomalies on future flight operations has been assessed and documented
OME Design
Data Book
OME Ground
Operations and Logistics
Requirements
Document
OME
OME Ground
Support
Equipment
Requirements and Plans
4. All flight hardware and flight performance data evaluation reports are completed.
Reports and other documentation have been retained for performance comparison and trending.
Post-Flight
Performan ce
Reconstruc tion
Analysis
Report
Future work has been adequately defined, agreed to, and scheduled for completion.
Action list and meeting minutes
30 J-2-A Title Page 1 March 13, 2020 April 17, 2020
31 J-2-A OME-T-093 29 OME Post-Flight Performance Reconstruction
Analysis Report OME Post-Flight Performance Reconstruction
Analysis Report and OME Post-Flight Assessment
Review
32 J-2-A OME-T-093 29 *Report 60 days post landing. Only for the first four engines that fly into orbit.
*Report 60 days post landing and review to be held a week after report completed. To be executed through CLIN 0003.
33 J-3 Title Page 1 March 15, 2020 April 17, 2020
34 J-3 Section 4.0 29 OMS-E GSE, Ground, and Flight Installation
Hardware List Export Controlled Deleted Export Controlled
35 L L.17.1
INTRODUCTIO
N
L-13 Paragraph Paragraph Title
L.17.1 Introduction
L.17.2 Proposal
Arrangement, Page
Limitations, Copies, and Due
Dates
L.17.3 Instructions for
Preparation of
Proposal
L.17.4 Mission Suitability
Factor (Volume I)
L.17.5 Past Performance
Information Factor
(Volume II)
L.17.6 Price Factor
(Volume III)
L.17.7 Responsibility
Considerations
(Volume IV)
L.17.8 Model Contract
(Volume V)
Paragraph Paragraph Title
L.17.1 Introduction
L.17.2 Proposal Arrangement, Page
Limitations, Copies, and Due
Dates
L.17.3 Proposal Marking and Delivery through Large File Transfer
L.17.4 Instructions for Preparation of
Proposal
L.17.5 Mission Suitability Factor -
Volume I
L.17.6 Past Performance Information
Factor - Volume II
L.17.7 Price Factor - Volume III
L.17.8 Responsibility Considerations -
Volume IV
L.17.9 Model Contract - Volume V
36 L L.17.1
INTRODUCTION
1st Paragraph
L-15 The entire proposal is due no later than June 11, 2020 at 1:30 p.m. Central Time. Proposal Volume
II, Past Performance Information is requested early by May 21, 2020 at 1:30 p.m. Central Time but not officially due until the proposal submittal date.
The entire proposal is due no later than June 17, 2020 at 1:30 p.m. Central Time. Proposal Volume
II, Past Performance Information is requested early by May 28, 2020 at 1:30 p.m. Central Time but not officially due until the proposal submittal date.
37 L Table L-2:
Overview of
Proposal
Volumes, Page
Limitations, Copies, and
Format
L-15 Table L-2: Overview of Proposal Volumes, Page
Limitations, Copies, and Format
Approach to Meeting the Intent of Technical
Standards
Alternate Standards
DRD OME-T-094
Table L-2: Overview of Proposal Volumes, Page
Limitations, Copies, and Format
Approach to Meeting the Intent of Technical
Standards
Alternate Standards
DRD OME-T-094
Note- Offerors Alternate Standards in response to Volume I number 1 is excluded from the page count
38 L Table L-2:
Overview of
Proposal
Volumes, Page
Limitations, Copies, and
Format
L-16 IV Responsibility Considerations
Subcontractor listing
IV Responsibility Considerations
DELETED Subcontractor Listing
39 L
L.17.3
PROPOSAL
MARKING AND
DELIVERY
THROUGH
LARGE FILE
TRANSFER
(LFT)
L-17 to
L-18
Email invitations with LFT links expire in 168 hours. Therefore, all Offerors must submit their request for an LFT invitation to submit the Past
Performance Information the aforementioned emails, no later than 1:30 p.m. Central on May
14, 2020. The Government anticipates responding with an invitation to use LFT on
May 19, 2020.
All Offerors must submit their request for an
LFT invitation for the final proposal to the aforementioned emails, no later than 1:30 p.m.
Central on June 04, 2020. The Government anticipates responding with an invitation to use
LFT on June 08, 2020
The Government is not responsible for any failure attributable to the transmission or receipt of documents submitted using electronic means, including the missing of any established deadlines. Please note that uploading documents via LFT and the transmission of the files from the Offeror to the Government may not be instantaneous. Offerors are cautioned to allow for sufficient time to ensure timely proposal delivery before the submission deadline of June 11, 2020 at 1:30 p.m. Central.
To ensure successful delivery, Offerors should submit proposals at least 24 hours prior to the time specified in the solicitation.
Email invitations with LFT links expire in 168 hours. Therefore, all Offerors that plan to submit Volume II, Past Performance early must submit their request for an LFT invitation to submit the Past Performance Information to the aforementioned emails, no later than 1:30 p.m.
Central on May 21, 2020. The Government anticipates responding with an invitation to use
LFT on May 22, 2020.
All Offerors must submit their request for an
LFT invitation for the final proposal to the aforementioned emails, no later than 1:30 p.m.
Central on June 10, 2020. The Government anticipates responding with an invitation to use
LFT on June 12, 2020.
The Government is not responsible for any failure attributable to the transmission or receipt of documents submitted using electronic means, including the missing of any established deadlines. Please note that uploading documents via LFT and the transmission of the files from the Offeror to the Government may not be instantaneous. Offerors are cautioned to allow for sufficient time to ensure timely proposal delivery before the submission deadline of June 17, 2020 at 1:30 p.m. Central.
To ensure successful delivery, Offerors should submit proposals at least 24 hours prior to the time specified in the solicitation.
40 L L.17.7 PRICE
FACTOR-
VOLUME III
L-28 (a) Introduction
A Price Proposal that is suitable for evaluation shall:
Account for all resources necessary to complete requirements of this RFP.
Provide traceability to the technical/management proposal(s) in
Volume I, Mission Suitability.
Include a narrative portion that explains all pricing and estimating techniques, including the basis for proposed price estimates.
Comply with applicable Federal Acquisition
Regulation (FAR), NASA FAR Supplement
(NFS), and statutory requirements.
Include all templates required in this RFP.
(a) Introduction
A Price Proposal that is suitable for evaluation shall:
Account for all resources necessary to complete requirements of this RFP.
Include a narrative portion that explains all pricing and estimating techniques, including the basis for proposed price estimates.
Comply with applicable Federal Acquisition
Regulation (FAR), NASA FAR Supplement
(NFS), and statutory requirements.
Include all templates required in this RFP.
41 L L.17.7 PRICE
FACTOR-
VOLUME III
L-29 (b) Specific Guidelines
The price instructions apply to the Prime Offeror, inter-divisional organizations, and all major subcontractors. For proposal preparation purposes, the term “subcontractor” shall include “inter-divisional organizations.” A subcontractor is considered to be a “major subcontractor” if is responsible for one or more of the following critical components: Main Isolation Valve, Regulators, Injectors, and Combustion Chambers. A subcontractor is considered to be a “minor subcontractor” if it is not responsible for one or more of the critical components mentioned above.
(b) Specific Guidelines
The price instructions apply to the Prime Offeror, inter-divisional organizations, and all major subcontractors. For proposal preparation purposes, the term “subcontractor” shall include “inter-divisional organizations.” A subcontractor is considered to be a “major subcontractor” if is responsible for one or more of the following critical components: Main Isolation Valve, Regulators, Injectors, and Combustion Chambers. A subcontractor is considered to be a “minor subcontractor” if it is not responsible for one or more of the critical components mentioned above.
If a contractor (Prime or major subcontractor) is responsible for one or more of the critical parts listed above, the contractor shall complete the major subcontractor templates for each critical part.
42 L L.17.7 PRICE
FACTOR-
VOLUME III
L-29 b) Indirect Rates
i. Indicate whether any Forward Pricing Rate
Agreement (FRPA) or Forward Pricing Rate
Recommendation (FPRR) has been used for any indirect rate component comprising a portion of the
FBR. Provide the date of the FPRA/FPRR(s). If the Offeror does not have an FPRA/FPRR, then the
Offeror shall submit the most current Forward
Pricing Rate Proposal (FPRP) and the status of its audit.
b) Indirect Rates
i. Indicate whether any Forward Pricing Rate
Agreement (FRPA) or Forward Pricing Rate
Recommendation (FPRR) has been used for any indirect rate component comprising a portion of the FBR. Provide the date of the
FPRA/FPRR(s). If the Offeror does not have an FPRA/FPRR, then the Offeror shall submit the most current Forward Pricing
Rate Proposal (FPRP) and the status of its audit.
For all indirect rate components for which a FPRA has not been used, identify each indirect rate component separately and describe the cost pool and allocation base of each of the indirect rates utilized in the FBRs that were applied in the price proposal for each of the contract years included in the proposal.
43 L L.17.7 PRICE
FACTOR-
VOLUME III
L-30 1. Pricing for IDIQ Delivery Order- CLIN
0001A: Baseline Certification
a) Offerors shall propose the required resources
– level of WYES/hours, appropriate skill mix, and amount of non-labor resources – necessary to accomplish their unique technical approach to performing the PWS portion identified as 2.1 OME Certification
(Contract Line Item Number (CLIN) 0001)) to be certified no later than September 15, 2024.
The proposed labor and non-labor resources are for the Prime Offeror’s entire team (i.e., the prime and all subcontractors) and shall be identified and described in Volume I, Mission Suitability, Basis of Estimate (BOE) paragraph, from a management and technical point of view. Subsequently, in Volume III, Price Proposal, the Offeror’s proposed Task
Order hours and Non-Labor Resources
(NLRs) for the entire team must be provided in the PPST CLIN 0001 (Cert).
Because of the uncertainties involved with
IDIQ work, Offerors are cautioned that this estimate is not a guarantee of future work.
Offerors are directed to Section B, Clause
JSC 52.216-90 IDIQ MINIMUM AND
MAXIMUM ORDERING LIMITS”
regarding the guaranteed minimum order for
IDIQ.
1. Pricing for IDIQ Delivery Order- CLIN
0001A: Baseline Certification
(a) Offerors shall propose the required resources – level of WYES/hours, appropriate skill mix, and amount of non-labor resources – necessary to accomplish their unique technical approach to performing the PWS portion identified as 2.1 OME
Certification (Contract Line Item Number (CLIN)
0001)) to be certified no later than September 15, 2024.
Because of the uncertainties involved with IDIQ work, Offerors are cautioned that this estimate is not a guarantee of future work. Offerors are directed to
Section B, Clause JSC 52.216-90 IDIQ MINIMUM
AND MAXIMUM ORDERING LIMITS”
regarding the guaranteed minimum order for IDIQ.
44 L L.17.7 PRICE
FACTOR-
VOLUME III
L-31 2. Pricing for IDIQ Delivery Order- CLIN
0002A: Baseline Production
(a) Offerors shall propose the required resources
– level of WYES/hours, appropriate skill mix, and amount of non-labor resources – necessary to accomplish their unique technical approach to performing the PWS portion identified as 2.2
OME Production (CLIN 0002) and Attachment
L-9A, OME Baseline Need Dates, for Lot Buy
No.1 (four (4) engines). Offers shall assume Lot
Buy 1 will include OME #1 through OME #4.
The proposed labor and non-labor resources are for the Prime Offeror’s entire team (i.e., the prime and all subcontractors) and shall be identified and described in Volume I, Mission
Suitability, Basis of Estimate (BOE) paragraph, from a management and technical point of view.
Subsequently, in Volume III, Price Proposal, the
Offeror’s proposed Task Order hours and Non-
Labor Resources (NLRs) for the entire team must be provided in the PPST CLIN 0002A (Lot
Buy No. 1).
2. Pricing for IDIQ Delivery Order- CLIN
0002A: Baseline Production
(a) Offerors shall propose the required resources
– level of WYES/hours, appropriate skill mix, and amount of non-labor resources – necessary to accomplish their unique technical approach to performing the PWS portion identified as 2.2
OME Production (CLIN 0002) and Attachment
L-9A, OME Baseline Need Dates, for Lot Buy
No.1 (four (4) engines). Offers shall assume Lot
Buy 1 will include OME #1 through OME #4.
45 L L.17.7 PRICE
L-31 3. Pricing for IDIQ Delivery Order-
CLIN 0001B: Accelerated
Certification
a) Offerors shall propose the required resources – level of WYES/hours, appropriate skill mix, and amount of non-labor resources – necessary to accomplish their unique technical approach to performing the PWS portion identified as
2.1 OME Certification (Contract Line Item
Number (CLIN) 0001) to be certified no later than June 30, 2024.
The proposed labor and non-labor resources are for the Prime Offeror’s entire team (i.e., the prime and all subcontractors) and shall be identified and described in Volume I, Mission Suitability, Basis of Estimate
(BOE) paragraph, from a management and technical point of view. Subsequently, in
Volume III, Price Proposal, the Offeror’s proposed Task Order hours and Non-Labor
Resources (NLRs) for the entire team must be provided in the PPST CLIN 0001 (Cert).
3. Pricing for IDIQ Delivery Order- CLIN
0001B: Accelerated Certification
(a) Offerors shall propose the required resources – level of WYES/hours, appropriate skill mix, and amount of non-labor resources – necessary to accomplish their unique technical approach to performing the PWS portion identified as 2.1 OME
Certification (Contract Line Item Number (CLIN)
0001) to be certified no later than June 30, 2024.
46 L L.17.7 PRICE
L-32 4. Pricing for IDIQ Delivery Order- CLIN
0002B: Accelerated Production
a) The proposed labor and non-labor resources are for the Prime Offeror’s entire team (i.e., the prime and all subcontractors) and shall be identified and described in Volume I, Mission
Suitability, Basis of Estimate (BOE) paragraph, from a management and technical point of view. Subsequently, in Volume III, Price Proposal, the Offeror’s proposed Task
Order hours and Non-Labor Resources
(NLRs) for the entire team must be provided in the PPST CLIN 0002B (Lot Buy No. 1).
4. Pricing for IDIQ Delivery Order- CLIN
0002B: Accelerated Production
a) Offerors shall propose the required resources
– level of WYES/hours, appropriate skill mix, and amount of non-labor resources – necessary to accomplish their unique technical approach to performing the PWS portion identified as 2.2 OME Production
(CLIN 0002) and Attachment L-9B, OME
Accelerated Need Dates, for Lot Buy No.1
(four (4) engines). Offers shall assume Lot
Buy 1 will include OME #1 through OME
#4.
47 L L.17.7 PRICE
L-34 5. Pricing for IDIQ RFP Specified Resources
(SR)- CLIN 0003: Special Tasks and Studies
Specified Resources hours =1860 per Standard
Labor Category per Contract Year
5. Pricing for IDIQ RFP Specified Resources
(SR)- CLIN 0003: Special Tasks and Studies
Specified Resources hours = 456 per Standard
Labor Category per Contract Year
48 L L.17.7 PRICE
L-34 6. Pricing for Delivery Order- CLIN 0004:
Storage
Offerors are required to develop a daily storage rate per contract year, and then apply those rates to the 180 days. This pricing approach is facilitated through the Government provided
Price Templates in the EPM, which is explained in detail in Paragraph (d) below.
6. Pricing for Delivery Order- CLIN 0004:
Storage
Offerors are required to develop a daily storage rate per contract year, and then apply those rates to the 180 days for a quantity of two engines.
Offerors are to assume the storage need is for a minimum of three (3) engines. This pricing approach is facilitated through the Government provided Price Templates in the EPM, which is explained in detail in Paragraph (d) below.
49 L L.17.8
RESPONSIBILIT
Y
CONSIDERATI
ONS – VOLUME
IV
L-37 L.17.8 RESPONSIBILITY CONSIDERATIONS
– VOLUME IV
L.17.8 RESPONSIBILITY CONSIDERATIONS
– VOLUME IV
Added
Insurance Coverage
Offerors shall provide proof of insurance coverage to comply with NFS 1852.228-75, Minimum Insurance Coverage
50 L L.17.9 MODEL
CONTRACT
AND
ADDITIONAL
REQUIREMENT
S - VOLUME V
L-38
L.17.9 MODEL CONTRACT AND
ADDITIONAL REQUIREMENTS-VOLUME V
L.17.9 MODEL CONTRACT AND
ADDITIONAL REQUIREMENTS-VOLUME V
Section I
Added 52.223-3 HAZARDOUS MATERIAL
IDENTIFICATION AND MATERIAL SAFETY
DATA (JAN 1997)
51 ATTACHMENT
L-8
GOVERNMENT
TASK
AGREEMENT
INSTRUCTIONS
L-59 GTA Template GTA Template
Added “If a GTA for NASA facilities is required, a
GTA will be used for CLIN 0001A Baseline
Certification and CLIN 0002A Baseline Production and a separate GTA will be used for CLIN 0001B
Accelerated Certification and CLIN 0002B
Accelerated Production.”
52 L ATTACHMENT
L-8
GOVERNMENT
TASK
AGREEMENT
INSTRUCTIONS
L-60 Government Task Agreement Point of Contact
Listing
Location Point-of-Contact
Glenn
Research
Center
Gary Ruff, 216-433-5697, gary.a.ruff@nasa.gov
Goddard
Space Flight
Center
Mark Lupisella, 301-286-2918, mark.l.lupisella@nasa.gov
Johnson
Space
Center
Carlos Westhelle, 281-483-4816, carlos.h.westhelle@nasa.gov
Kennedy
Space
Center
Julius Edelmann, 321-861-7526, j.edelmann@nasa.gov
Government Task Agreement Point of Contact
Listing
Updated the following Points of Contacts
Location Point-of-Contact
Glenn
Research
Center
Kristen Bury, 216- 433-3150, kristen.m.bury@nasa.gov
Goddard
Space Flight
Center
Michelle Gates, 202-358-1048, michele.m.gates@nasa.gov
Mark Lupisella, 301.286.2918, mark.l.lupisella@nasa.gov
Johnson
Space Center
White
Sands Test
Facility
Carlos Westhelle, 281-483-4816, carlos.h.westhelle@nasa.gov
Jeremy Bruggemann
575-525-7659 jeremy.bruggemann@nasa.gov
Kennedy
Space
Center
Nancy Potts, 321-867-4646, nancy.a.potts@nasa.gov
Robyn Mitchell, 321-861-8038, robyn.l.mitchell@nasa.gov
(secondary)
53 L Attachment L-
6A- OME EPM
Templates-
Baseline
Replaced Attachment L-6A OME EPM Templates-
Baseline in its entirety
54 L Attachment L-
6B- OME EPM
Templates-
Accelerated
Replaced Attachment L-6B- OME EPM Templates-
Accelerated in its entirety
55 L 80JSC020R0031
- Model Contract
80JSC020R0031 - Model Contract Model Contract has been replaced in its entirety.
80JSC020R0031 - Model Contract Amendment 2
Structure Bookmarks
Accessibility Report
Filename:
sf30 80JSC020R0031 Amendment 2 r1a.pdf
Report created by:
Organization:
[Enter personal and organization information through the Preferences > Identity dialog.]
Summary
The checker found problems which may prevent the document from being fully accessible.
Needs manual check: 0
Passed manually: 2
Failed manually: 0
Skipped: 3
Passed: 24
Failed: 3
Detailed Report
Document
Rule Name Status Description
Accessibility permission flag Passed Accessibility permission flag must be set
Image-only PDF Passed Document is not image-only PDF
Tagged PDF Passed Document is tagged PDF
Logical Reading Order Passed manually Document structure provides a logical reading order
Primary language Passed Text language is specified
Title Passed Document title is showing in title bar
Bookmarks Passed Bookmarks are present in large documents
Color contrast Passed manually Document has appropriate color contrast
Page Content
Rule Name Status Description
Tagged content Failed All page content is tagged
Tagged annotations Failed All annotations are tagged
Tab order Passed Tab order is consistent with structure order
Character encoding Passed Reliable character encoding is provided
Tagged multimedia Passed All multimedia objects are tagged
Screen flicker Passed Page will not cause screen flicker
Scripts Passed No inaccessible scripts
Timed responses Passed Page does not require timed responses
Navigation links Passed Navigation links are not repetitive
Forms
Rule Name Status Description
Tagged form fields Failed All form fields are tagged
Field descriptions Passed All form fields have description
Alternate Text
Rule Name Status Description
Figures alternate text Passed Figures require alternate text
Nested alternate text Passed Alternate text that will never be read
Associated with content Passed Alternate text must be associated with some content
Hides annotation Passed Alternate text should not hide annotation
Other elements alternate text Skipped Other elements that require alternate text
Tables
Rule Name Status Description
Rows Passed TR must be a child of Table, THead, TBody, or TFoot
TH and TD Skipped TH and TD must be children of TR
Headers Passed Tables should have headers
Regularity Passed Tables must contain the same number of columns in each row and rows in each column
Summary Skipped Tables must have a summary
Lists
Rule Name Status Description
List items Passed LI must be a child of L
Lbl and LBody Passed Lbl and LBody must be children of LI
Headings
Rule Name Status Description
Appropriate nesting Passed Appropriate nesting
Back to Top
| 1 CONTRACT ID CODE: | |
| 4 REQUISITIONPURCHASE REQUISITION NUMBER: | |
| 3 EFFECTIVE DATE See Block 16C6 ISSUED BY CODE: | |
| 5 PROJECT NUMBER If applicableRow1: | |
| NASA Johnson Space Center 2101 NASA Parkway Houston TX 770583696: | |
| 8 NAME AND ADDRESS OF CONTRACTOR Number street county State and ZIP Code: | |
| undefined: | |
| 9B DATED SEE ITEM 11 03192020: | |
| undefined_2: | |
| 10A MODIFICATION OF CONTRACTORDER NUMBER: | |
| CODE: | |
| FACILITY CODE: | |
| 10B DATED SEE ITEM 13: | |
| The above numbered solicitation is amended as set forth in Item 14 The hour and date specified for receipt of Offers: Off | |
| is extended: Off | |
| is not extended: Off | |
| 13 THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTSORDERS: | |
| undefined_3: | |
| A THIS CHANGE ORDER IS ISSUED PURSUANT TO Specify authority THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A: | |
| undefined_4: | |
| undefined_5: | |
| C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: | |
| undefined_6: | |
| D OTHER Specify type of modification and authority: | |
| is not: Off | |
| is required to sign this document and return: Off | |
| copies to the issuing office: | |
| 15A NAME AND TITLE OF SIGNER Type or print: | |
| 16A NAME AND TITLE OF CONTRACTING OFFICER Type or print Ashley H Chaves: | |
| 15C DATE SIGNED: | |
| 2020-04-17T09:57:02-0500 | |
| Ashley Chaves |
16C DATE SIGNED:
File details come from the government source that posted it. Updated .