8-Pre-Bid Conference Agenda.pdf
PDF 206 KB Posted
- Attached to
- 13800 South Mountain View Corridor Sewer Project
- Solicitation number
- JBID971
- Issued by
- Salt Lake County, Utah
About this file
This is a Pre-Bid Conference Agenda for the Jordan Basin Improvement District concerning four related sewer projects in Utah. The conference was held on September 24, 2026, at 2:00 pm at the Jordan Basin Improvement District office. The 13800 South Mountain View Corridor Sewer Project involves installing approximately 500 linear feet of 18-inch PVC sewer pipe, 434 linear feet of trenchless construction guided bore (36-inch steel casing), and related infrastructure with a maximum sewer depth of 31 feet. The 13200 South Mountain View Corridor Sewer Project includes 1,328 linear feet of 18-inch PVC sewer, 121 linear feet of 10-inch PVC sewer, 534 linear feet of trenchless construction guided bore, and a maximum sewer depth of 28 feet. Only prequalified contractors are eligible to submit bids: Newman Construction, Nix Construction, Red Pine Construction, Silver Spur Construction, Spade Excavating, and Whitaker Construction. Sealed bids were due on October 13, 2026, at 2:00 pm local time, with a tentative award date of October 27, 2026, at the JBID Board Meeting. The contract requires substantial completion by June 1, 2027, and final completion by July 1, 2027, with liquidated damages of $600 per day. Construction work hours are 7:00 am to 5:00 pm Monday through Friday, with winter work permitted between October 15 and April 15.
Critical project requirements include engineered and stamped shoring designs for excavations exceeding 20 feet in depth, slope stability analysis for work within Riverton City Slope Easement on the 13200 South project, and multiple permits from UDOT, Riverton, Herriman, and County Survey. Construction staking, survey as-builts, pipe and manhole testing, and third-party CCTV inspection are contractor responsibilities, while compaction testing and CCTV inspection are provided by JBID. Traffic control plans must be approved by UDOT Region 2 and Herriman City. Bid Item 34 on the 13200 South project covers potential costs for securing temporary access through Suburban Land Reserve Property. Contractors are required to submit written questions via https://utah.bonfirehub.com with a deadline of 5:00 pm on October 8, 2026. The project engineers are Bowen Collins & Associates for the 13800 South project and J-U-B Engineers for the 13200 South project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-BID CONFERENCE AGENDA
Projects:
Coming Projects:
• 13800 South Mountain View Corridor Sewer Project
• 13200 South Mountain View Corridor Sewer Project
• 12600 South Mountain View Corridor Sewer Project
• 13400 South Mountain View Corridor Sewer Project
Owner: Jordan Basin Improvement District
Engineers: • Bowen Collins & Associates (13800 South)
• J-U-B Engineers (13200 South)
Date:
September 24, 2026
Time:
2:00 pm
Location: Jordan Basin Improvement District
1. Welcome
2. Attendees list
3. Introductions
a. Jordan Basin Improvement District
i) Joel Thompson – General Manager
ii) Matt Garn – District Engineer
b. Bowen Collins & Associates
i) Brent Packer – Project Manager
c. J-U-B Engineers
i) Jordan Pugmire – Project Manager
ii) Whitney Davidson – Project Engineer
iii) Alea Nielson – Project Engineer
iv) Tyler Jepsen – Construction Engineer
4. Only prequalified contractors (Newman Construction, Nix Construction, Red Pine
Construction, Silver Spur Construction, Spade Excavating, and Whitaker Construction) are eligible to submit bids on the Mountain View Corridor Sewer Projects.
PRE-BID CONFERENCE AGENDA (continued)
5. Project Overview:
• 13800 South Mountain View Corridor Sewer Project (BCA) o 500 lf 18-inch PVC Sewer o 434 lf trenchless construction guided bore (36-in steel casing) o 31 feet maximum sewer depth excavation o Critical Issues:
Permits: UDOT, Riverton, Herriman, County Survey Monument (if required)
Sewer Depth and Shoring – See Specification 31 75 00 for shoring design requirements provided by the Contractor
Sewer bypass pumping see Sanitary Sewer Project Note 12, Dwg No. G-
Optional intermediate bore pit (see Dwg No. C-02) Winter work allowed during Oct 15 to April 15 with temp asphalt placed in the winter and permanent asphalt placed in the spring (see UDOT Proj Note 4.A, Dwg No. G-05)
Traffic Control see UDOT Project Note 4.B Dwg No. G-05 and General Note 23, Dwg No. G-04
Surface Restoration see General Notes 19 and 20, Dwg No. G-04 Construction staking, survey as-builts, pipe and manhole testing provided by Contractor (third party).
Compaction testing and CCTV inspection will be provided by JBID
• 13200 South Mountain View Corridor Sewer Project (JUB) o 1328 lf 18-inch PVC Sewer o 121 lf 10-inch PVC sewer o 534 lf trenchless construction guided bore (36-in steel casing) o 28 ft maximum sewer depth excavation o Review Drawings o Main Points:
Slope Stability Analysis required for work within Riverton City Slope Easement (on Costco Property)
Permanent Easements have not been recorded, and executing the Agreement will be held until easements are secured.
It is the responsibility of the contractor to secure staging and access within the Suburban Land Reserve Property. Initial conversations have been initiated with Suburban Land Reserve, access will be allowable pending negotiations. Bid Item 34 was included to cover potential costs associated with securing temporary access.
GEI Technical Specs: 31 09 13, 31 71 00, 31 73 00, 31 74 23, 31 75 00
• Contractor will need to submit:
o Requirement of Engineered, Stamped Shoring for all excavations over 20-ft in depth o Slope Stability Analysis for Riverton City Monitoring Arrays: along MVC and 13200 S. See Spec 31 09 13 Traffic Control Plan will need to be reviewed and approved by UDOT
Region 2 and Herriman City. Shoulder closured along MVC are allowable at any time. See specification 01300 & 01500
PRE-BID CONFERENCE AGENDA (continued)
6. Construction Work Schedule – 7:00 am to 5:00 pm Monday through Friday
7. Contract times and liquidated damages (refer to the Agreement, Section 00500 of the
Contract Documents)
a. Substantial Completion for all Work: June 1, 2027
b. Final Completion: July 1, 2027
c. Liquidated damages: $600 per day
8. Sealed Bids are due on October 13, 2026 at 2:00 pm local time at JBID.
9. Tentative schedule for award: October 27, 2026 at JBID Board Meeting.
10. All questions about the Projects must be submitted in writing via https://utah.bonfirehub.com. Questions submitted after 5:00 pm on October 8, 2026 may not be answered.
Pre-Bid Conference Agenda
File details come from the government source that posted it. Updated .