2-Section 00260 - Information Required of Bidder.pdf
PDF 102 KB Posted
- Attached to
- 13800 South Mountain View Corridor Sewer Project
- Solicitation number
- JBID971
- Issued by
- Salt Lake County, Utah
About this file
This is an Information Required of Bidder document issued by the Jordan Basin Improvement District for the 13800 South Mountain View Corridor Sewer Project in Utah. The project scope includes installing approximately 500 linear feet of 18-inch sanitary sewer pipeline, 3 sanitary sewer manholes, a 434-foot-long guided bore with a 36-inch minimum casing crossing under Mountain View Corridor, and associated construction items. Only contractors that have been prequalified for the Multiple Mountain View Corridor Sewer Projects are eligible to submit bids. Bidders must provide comprehensive information including company name and contact details, Utah contractor license classification, years of experience, ownership and management structure, site inspection documentation, proposed project superintendent and manager with resumes, proposed site safety representative, surety bonding information, and current job listings with completion status.
Bidders are required to submit a detailed subcontractor list identifying any subcontractor performing more than five percent of the total bid price, including the type of work and percentage of bid value, with no changes or substitutions permitted after bid opening without written owner approval. Suppliers and manufacturers for specified items must be listed and identified as the basis for the bid, with the same restriction on post-opening changes. Contractors performing the trenchless guided bore work must submit additional qualification and experience information per Specification 31 71 00 Tunnel Excavation and Initial Support. All bidders must make a sworn statement before a notary public certifying that all provided information is true and complete, with failure to comply potentially rendering the bid non-responsive and subject to rejection.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JORDAN BASIN IMPROVEMENT DISTRICT INFORMATION REQUIRED OF BIDDER
13800 S MOUNTAIN VIEW CORRIDOR SEWER PROJECT PAGE 00260-1
SECTION 00260
INFORMATION REQUIRED OF BIDDER
The Bidder shall furnish all of the following information. The Bidder is required to make a sworn statement that the information provided is true and complete in the presence of a notary public, and that notary public must notarize the signature of the Bidder. Failure to comply with these requirements may render the Bid non-responsive and subject to rejection. Attach additional sheets as needed to provide the required information. Award of a contract will be based upon review and evaluation of this information.
1. Bidder’s name and address:
2. Bidder’s Telephone Number:
Bidder’s Fax Number:
Bidder’s Email Address:
3. Bidder’s Contractor License: Primary Classification
Utah License No.
Supplemental Classification, if any:
4. Number of years experience in work of this type:
5. Names and titles of owners, officers, managing members, general partners, joint venturers or other managing agents of Bidder:
Name Title
13800 S MOUNTAIN VIEW CORRIDOR SEWER PROJECT PAGE 00260-2
6. Name of person who inspected site of the work on behalf of Bidder.
Name: Date of Inspection:
Title:
7. Proposed Project superintendent (attach resume):
Name: Years experience:
8. Proposed Project Manager, if other than superintendent (attach resume):
9. Proposed Site safety representative, if other than superintendent (attach resume):
10. Name, address, and telephone number of surety company and agent who will provide the required performance and payment bonds for the contract:
11. List of current jobs:
Owner Telephone No. Contract Amount ($) Type of Job Completion Percentage
12. List of Subcontractors
The Bidder shall list below the name of each Subcontractor who will perform Work on this Project in excess of five percent (5%) of the total Bid Price; a description of the type of Work to be completed by the Subcontractor and the value of the Work as a percentage of the total Bid Price.
After the opening of Bids, no changes or substitutions will be allowed without the written approval of the Owner.
13800 S MOUNTAIN VIEW CORRIDOR SEWER PROJECT PAGE 00260-3
Subcontractor’s Name Type of Work Percent (%) of Total Bid Price
Note: Contractor or Subcontractor performing the trenchless construction guided bore Work under Mountain View Corridor shall submit qualification and experience information included with the Contractor’s Bid as defined in Specification 31 71 00 Tunnel Excavation and Initial Support.
13. List of Suppliers
The Bidder shall list below the name of the manufacturer and the name of the supplier it intends to use, and upon which its Bid was based, for each item listed below. After the opening of Bids, no changes or substitutions will be allowed without the written approval of the Owner.
Item Manufacturer Supplier
STATE OF )
: ss
COUNTY OF )
, being first duly sworn on oath, deposes and says that the foregoing answers to questions, and all statements and information contained herein, are true and complete.
Printed Name
Printed Title
SUBSCRIBED AND SWORN to before me this ____ day of _______________, 20___.
Notary Public Residing at:
My Commission Expires:
File details come from the government source that posted it. Updated .