Attachement 1
COMMISSIONING SCOPE MATRIX
SECTION 01 91 13 ‐ GENERAL COMMISSIONING REQUIREMENTS
Roles & Responsibilities Matrix Roles and Responsibilities Matrix: Designers, CxA, RML CQM, Installing Contractors, Other 3rd Party Specialists
Review Leads Participates Funct. Witness Review Primary Secondary/ Manage/ Primary Testing & Record Perform. and & Record Oversight Additional Record Oversight
Deficiencies Testing Verify Deficiencies Oversight Documentation
Piping Pressure Testing X X X X
DW Supply Sanitization X X X X
Equipment/System Start‐up X X X X
Equipment/System Functional Performance Testing X X X X
Duct Leakage Testing X X X X X
Piping Pressure Testing X X X X
Hydronic Flush & Fill X X X X
Equipment Pre‐Startup Readiness Checklists X X X
Equipment Start‐up X X X X
Testing, Adjusting, & Balancing X TAB Sub X X X TAB Sub
Equipment/System Functional Perfance Testing X X X X
Electrical Power System Testing X X X X X X
Backup Power System Testing X X X X X X
Automated Lighting Controls Funct. Perf. Testing X X X X
Lightning Protection QC / Testing X X X X
Data/Comm Testing X X X X
Speaker System Testing X X X X
Access Control Testing X X X X
Fire Alarm System Testing X X X X
On‐site Construction Reviews X X
Air‐leakage Testing X X X X
Water‐leakage Testing X X X X
Installing Contractor CQM Contract
Building Envelope (Div. 07 & 08)
Commissiong Documenation 3rd Party Specialist
Div. 23 Mechanical
Div. 26 Electrical
Div. 22 Plumbing
Div. 27 Communication
Div. 28 Electronic Safety & Security
Design Firm of Record
(A&E, GPD, DCI,
etc)Commissioning Role/Execution by Discipline
Attachement 1
COMMISSIONING SCOPE MATRIX
SECTION 01 91 13 ‐ GENERAL COMMISSIONING REQUIREMENTS
Responsibilities per System Commissioning Role/Execution by Equipment/System Key: CxA will… C = Complete/Deliver/Provide W/V = Witness and/or Verify work/testing by others D = Direct and oversee testing by contractors N/A = Not Applicable
Div. 22 Plumbing Commissioning
Agent Commissioning
Agent Commissioning
Agent Commissioning
Agent Commissioning
Agent Division Equipment/System Submittal Periodic Equipment Controls Functional Testing Issues
Review* On‐site Start‐up Point‐to Performance Adjusting Reporting Construct. Point Testing Balancing Review Testing
General DHW (heaters, mixing valves, re‐circulation pumps) C C W/V W/V D W/V C Laboratory DHW (heaters, mixing valves, re‐circulation pumps) C C W/V W/V D W/V C Cage Wash DHW (heaters, mixing valves, re‐circulation pumps) C C W/V W/V D W/V C Tempered Water System C C N/A N/A N/A W/V C Domestic Water Supply System C C N/A N/A N/A N/A C Drain/Waste/Vent Plumbing C C N/A N/A N/A N/A C Laboratory Gases Piping System C C N/A N/A N/A N/A C Sewage Ejector Sump Pump Systems C C W/V W/V D N/A C Disinfection/Sterilization Steam Systems C C W/V W/V D N/A C R.O. Water System C C W/V W/V D N/A C Animal Watering System C C W/V W/V D W/V C Anesthesia Recovery Pumps C C W/V N/A W/V N/A C Compressed Air C C W/V W/V D N/A C Vacuum Pump System C C W/V W/V D N/A C
HVAC Systems including BAS (controls) ‐ all systems C C W/V W/V D W/V C
General Power Distribution (e.g. panels, switchgear) C C W/V N/A W/V N/A C Backup Power ‐ Automatic Transfer Systems C C W/V W/V W/V N/A C Uninterruptable Power Systems C C W/V N/A W/V N/A C Automated Lighting Controls C C W/V W/V D N/A C Lightning Protection System C C N/A N/A N/A N/A C
Speaker System C C W/V W/V W/V N/A C Data/Comm System C C W/V W/V W/V N/A C
Access Controls System C C W/V W/V W/V N/A C Fire Alarm System C C W/V W/V W/V N/A C
Air Barrier C C N/A N/A D N/A C Thermal Barrier C C N/A N/A D N/A C Water/Weather Barrier C C N/A N/A D N/A C
*CxA will review a select subset of all submittals in each division indicated, not ALL submittals under that division; e.g. would review hydronic pumps, but not piping insulation submittals under Div. 23
Design Firm of Record (A&E, GPD, DCI, etc)
Design Firm of Record (A&E, GPD, DCI, etc)
CQM Contract
Division 22 Plumbing
Division 23 Mechanical
Division 26 Electrical
Division 27 Communications
Division 28 Electronic Safety &
Security
Divisions 07, 08 Building Envelope