This is a combined synopsis/solicitation for drydock repairs to USCGC SMILAX (WLIC-315). The Coast Guard seeks repairs including hull preservation, machinery inspection and maintenance, tank cleaning, and other work. The solicitation includes 48 work items describing the required services in detail. The period of performance is 120 days beginning in April 2023. The place of performance is the contractor's facility. The solicitation closes on February 15, 2023 and the government will award a fixed-price contract. Small businesses are encouraged to respond.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC SMILAX (WLIC 315)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2023
Developed By: CWO Pamela Arts-Smith
(REV-2 04 April 2023)
USCGC SMILAX (WLIC-100) DRYDOCK AVAILABILITY FY2021
ii (Rev-2)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property .................................................................................. x Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics - Tender .............................................................................................................. xii General Requirements WORK ITEM 1: Hull Plating (U/W Body), Ultrasonic Testing WORK ITEM 2: U/W Body, Preserve (100%) - Tender WORK ITEM 3: Hull Plating Freeboard, Preserve “100%” WORK ITEM 4: Hull and Structural Plating (General) -10.2-Pound Steel, Renew - Tender WORK ITEM 5: Hull and Structural Plating (General) - 12.75-Pound Steel Plate, Renew - Tender WORK ITEM 6: Hull and Structural Plating (General) - 15.3-Pound Steel Plate, Renew - Tender WORK ITEM 7: Hull and Structural Plating (General) - 7.65-Pound (3/16") Steel Plate, Renew - Tender26 WORK ITEM 8: Hull and Structural Plating (General) - 7.65- Pound Steel Plate, Renew - Tender WORK ITEM 9: Hull And Structural Plating (General) - Cracked Steel Welds, Repairs - Tender WORK ITEM 10: Appendages (U/W), Leak Test WORK ITEM 11: Propulsion Shaft Rope Guards, Inspect WORK ITEM 12: Appendages (U/W) - Internal, Preserve WORK ITEM 13: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 14: Tanks (Potable Water), Clean and Inspect WORK ITEM 15: Propulsion Shafting; Remove, Inspect, and Reinstall WORK ITEM 16: Propulsion Shafting, Straighten WORK ITEM 17: Propulsion Shaft Bearings (External), Check Clearances WORK ITEM 18: Propeller , Remove, Inspect, and Reinstall WORK ITEM 19: Propeller, Minor Repairs and Reconditioning, Perform WORK ITEM 20: Propulsion Stern Tube Bearings, Check Clearances WORK ITEM 21: Stern Tube Interior Surfaces, Preserve 100% WORK ITEM 22: Fathometer Transducer, Renew – Tender WORK ITEM 23: Sea Valves and Waster Pieces, Overhaul or Renew WORK ITEM 24: Sea Strainers - Duplex (All Sizes), Overhaul WORK ITEM 25: Rudder Assembly; Remove, Inspect And Reinstall WORK ITEM 26: Rudder(s), Preserve (“100%”) WORK ITEM 27: Spud Wells, Preserve - Tender WORK ITEM 28: Buoy and Cargo Crane, Inspect and Service WORK ITEM 29: Tanks (Potable Water), Preserve “100%” WORK ITEM 30: Tanks (Potable Water), Preserve, Partial, WORK ITEM 31: Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System) WORK ITEM 32: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 33: Cathodic Protection, Zinc Anodes, Renew, - Tender WORK ITEM 34: Drydock - Tender WORK ITEM 35: Temporary Services, Provide - Tender WORK ITEM 36: Sea Trial Performance, Support, Provide WORK ITEM 37: Potable Water Riser Piping, Renew WORK ITEM 38: Fuel Oil Tank Gooseneck Ventilation Pipes, Renew WORK ITEM 39: Visor Plating Upper Bridge, Repair WORK ITEM 40: Forward Bulkwark, Repair WORK ITEM 41: Lead-Based Paint, Perform Spot Abatement WORK ITEM 42: Deck Covering (Interior Wet/Dry), Renew iii (Rev-2)
WORK ITEM 43: Tank Fuel Valves, Renewal WORK ITEM 44: Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean WORK ITEM 45: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean WORK ITEM 46: Sewage Holding Tanks, Clean and Inspect WORK ITEM 47: Boat Boom, Inspect and Service - Tender WORK ITEM 48: Bilges, Preserve iv (Rev-2)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
3/24/2023 Rev 0 5,6,8 Entered NONE in “OTHER REFERENCES”
3/24/2023 Rev 0 11,15 thur 21, 23,24,33 Removed incorrect drawings and added correct drawings to
WI’s, updated Consolidated List of References
4/3/2023 Rev 1 41,44,45 Removed incorrect drawings and added correct drawings to
WI’s and updated Consolidated List of References
4/3/2023 Rev-1 38 Add additional drawing for reference of interferences and update Consolidated List of References
4/3/2023 Rev-1 19 Para 4.1 Removed incorrect propeller and added correct propeller (Manganese Bronze alloy, 4 blades, 46" diameter x
42" pitch)
4/3/2023 Rev-1 42 Para 3.2.1 changed to inspect and submit CFR in place of replace shower pans
4/3/2023 Rev-1 47 Added drawings and updated Consolidated List of References, added other requirements Table 1, Item 5
4/3/2023 Rev-1 46 Correct duplicate para 3.4, removed duplicate and added 3.4.1
4/3/2023 Rev-1 7 Changed WI title and para 1.1 to read 7.65 pound steel
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-2)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 180 TE 1205-1, Rev-, Installation of Hull Zinc Protectors (SMILAX 315)
Coast Guard Drawing 100 TE 4804-1, Rev A, Hot, Cold and Sanitary Water Piping
Coast Guard Drawing 180 TE 0103-007, Rev 2, Booklet Of General Plans
Coast Guard Drawing 180 TE 0103-007, Rev 3, Booklet Of General Plans
Coast Guard Drawing 180 TE 0500-001, Rev 1, Offsets
Coast Guard Drawing 180 TE 0500-002, Rev 1, Lines
Coast Guard Drawing 180 TE 0700-005, Rev B, Docking Plan (WLIC 315)
Coast Guard Drawing 180 TE 0700-005, Rev C, Docking Plan (WLIC 315)
Coast Guard Drawing 180 TE 103-007, Rev 2, Booklet of Plans (SMILAX (315)
Coast Guard Drawing 180 TE 103-7, Rev 3; Booklet of Plans (SMILAX) (315)
Coast Guard Drawing 180 TE 0103-009, Rev -, Booklet Of General Plans
Coast Guard Drawing 180-TE-0103-001 Rev 7, Deck Plan Arrangement (Smilax 315)
Coast Guard Drawing 180 TE 1101-003, Rev 2, Shell Expansion
Coast Guard Drawing 180 TE 1101-005, Rev -, Shell & Deck Framing Plqn Aft Section
Coast Guard Drawing 180 TE 1112-005, Rev -, Spud Winch Sheave Fdns & Guards (SMILAX) (315)
Coast Guard Drawing 180 TE 1701-14, Rev B, Derrick Swinging Gear Installation
Coast Guard Drawing 180 TE 2200-001, Rev -, Rudder, Rudder Stock and Bearings
Coast Guard Drawing 180 TE 2200-001, Rev C, Rudder, Rudder Stock & Bearings
Coast Guard Drawing 180 TE 4301-9, Rev B, Shaft Details
Coast Guard Drawing 180 TE 4302-010, Rev B, Stern Tube Seals & Struts
Coast Guard Drawing 180TE-4807-1, Sea Water Systems Mods
Coast Guard Drawing 180TE-4823-1, Sea Chest & Sea Water Dets
Coast Guard Drawing 180TE-4823-2, Sea Chest Modification
Coast Guard Drawing 180 TE 0500-001, Rev 1, Offsets
Coast Guard Drawing 180 TE 0500-002, Rev 1, Lines
Coast Guard Drawing 180-TE 4400-5, Rev -, Propeller (CGC SMILAX)
Coast Guard Drawing 180-TE 0103-007, Rev 2, Booklet of Plans (SMILAX) (315)
Coast Guard Drawing 180-TE 0103-007, Rev 3, Booklet of Plans (SMILAX) (315)
Coast Guard Drawing 180-TE 1106-001, Rev 1, Deck Plating vi (Rev-2)
Coast Guard Drawing 180-TE 1106-1, Rev 3, Deck Plating
Coast Guard Drawing 180-TE 4808-6, Rev -, Sanitary Drains Diagram SMILAX
Coast Guard Drawing 180-TE 2200-1, REV C, Rudder, Rudder Stock & Bearings
Coast Guard Drawing 180-TE 4804-002, Rev B, Hot, Cold, and Sanitary Water Piping
Coast Guard Drawing 180-TE 5501-001, Rev -, Fuel Oil Service System Diagram
Coast Guard Drawing 180-TE 8201-012, Rev -, Crane Assembly (AMD-2344)
Coast Guard Drawing FL 6713-201, Rev B, CRP-V850 Transducer (B-14) Adapter Assembly
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters
Coast Guard Drawing 180 TE 4000-001, Rev -, Machinery Arrangements
Coast Guard Drawing 180 TE 5200-2, Rev A, Main Engine/Generator Exhaust Mods
Coast Guard Drawing 180-TE 8201-10, Crane HPU and PIPING Installation
Coast Guard Drawing 75-WAGL-1103-2, Rev G, Boat Davit and Pedestal Assembly
Coast Guard Drawing 180-TE-8201-009, Rev -, Single Point Boat Davit Installation and Details
(SMILAX)
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 5983, SWBS 589, Nov 2015, Buoy Crane Model SB70-28.5
Coast Guard Technical Publication (TP) 4958, Section A, Amendment 1; Mar 2011, Utility Air winch
Model HU-40 Series
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install New
Deck Covering Systems
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2020, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary
Services
OTHER REFERENCES
American Bureau of Shipping (ABS) 2, Rule Requirements for Survey After Construction, 2014, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities vii (Rev-2)
American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System
Components - Health Effects
American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System
Components - Health Effects
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2013, Recommended Practice for
Personal Qualification and Certification in Nondestructive Testing
American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and
Welding End
American Society of Mechanical Engineers (ASME) B16.34, 2013, Valves-Flanged, Threaded, and
Welding End
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D3359, 2009, Standard Test Methods for Measuring Adhesion by Tape
Test
ASTM International (ASTM) D3951, Reapproved 2010, Standard Practice for Commercial Packaging
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component
Adhesives (An)
ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component
Adhesives (AN)
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene
Glycol (For Caterpillar applications, use CAT Extended Life Pre-Mix coolant.)
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust-
Petrolatum
Commercial Item Description (CID) A-A-59316, Nov 2016, Abrasive Materials for Blasting
Commercial Item Description (CID) A-A-59316, 2003, Abrasive Materials for Blasting
Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Fernstrum Gridcooler Installation and Maintenance Manual, 2013, Form 175
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller -
Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller -
Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves viii (Rev-2)
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2011 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufactures Standardization Society, Standard Practice 61 (MSS SP-61), 2009, Pressure Testing of
Valves
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of
Reliability Is Required
MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application
MIL-PRF-24647, 2013, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited)
MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main
Propulsion Shafting
Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-
PRO-160, Jan 2006, Chapter 16, Cofferdams
Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-
PRO-160, Jan 2011, Chapter 16, Cofferdams
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and
Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning
The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements ix (Rev-2)
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 12/NACE No.5, 2007, Surface Preparation and Cleaning of Steel & Other Hard
Materials by High and Ultrahigh Pressure Water Jetting
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) 2006, Joint Surface Preparation
Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal x (Rev-2)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
15 Y **Propeller shaft NSN: 2010-01-F16-4712 2 ea.
18 Y **Propeller/RH NSN: 2010-01-F08-1386 1 ea. 5,500
18 Y **Propeller/LH NSN: 2010-01-F03-0148 1ea 5,500
22 N ***Fathometer
Transducer, Shallow
Water, 50-200 kHz
(Airmar Technology
SS505)
NSN: 5845-01-470-2500 1 ea. 343.63
22 Y *Transducer Cover
Plate
N/A 4 ea. 50.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C5IT Service Center.
xi (Rev-2)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
1 Hull Plating (U/W Body), Ultrasonic Testing
2 U/W Body, Preserve (100%) - Tender
10 Appendages (U/W), Leak Test
15 Propulsion Shafting; Remove, Inspect, and Reinstall
16 Propulsion Shaft Bearings (External), Check Clearances
20 Propulsion Stern Tube Bearings, Check Clearances
24 Sea Strainers - Duplex (All Sizes), Overhaul
25 Rudder Assembly; Remove, Inspect And Reinstall
28 Buoy and Cargo Crane, Inspect and Service
42 Deck Covering (Interior Wet/Dry), Renew
47 Boat Boom, Inspect and Service-Tender
48 Bilges, Preserve xii (Rev-2)
PRINCIPAL CHARACTERISTICS - TENDER
100' WLIC (CGC SMILAX) INLAND CONSTRUCTION TENDER
PHYSICAL
Length overall 100' 0"
Depth 5' 0"
Maximum beam 24' 0"
Frame spacing 1' 6"
Full load draft 4' 8 1/4" LCF Draft
Full load displacement 218.16 Long Tons SW
HULL
Hull material Steel
MACHINERY
Number of propellers 2
Number of blades 4
Diameter 46"
Pitch 42" fixed
Shaft RPM 480
TANK CAPACITIES
Fuel tanks
Fresh water tanks
Lube oil
1 (Rev-2)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-2)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-2) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. None.
3.7 SFLC Standard Specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:
None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
4 (Rev-2)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
5 (Rev-2)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
6 (Rev-2)
QA-3A - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
7 (Rev-2)
QA-3B - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading
(mils)
Mean Reading (mils) IAW ASTM DD4417).
8 (Rev-2)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
9 (Rev-2)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic
Pull-Off (Type I/Banana) Gauge Is
Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
10 (Rev-2)
11010_UT_0320_FLT
REC_11010_UT_FLT_100' WLIC (315 CGC SMILAX) (0911)
WORK ITEM 1: Hull Plating (U/W Body), Ultrasonic Testing
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing
(UT) of U/W hull plating.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 180 TE 700-005, Rev B, Docking Plan (BLUEBELL) (315)
Coast Guard Drawing 180 TE 1101-003, Rev 2, Shell Expansion
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:
• 3.2 (UT measurements).
3.1.2 Tech Rep.
Not applicable.
11 (Rev-2)
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 UT measurements. The Contractor shall perform a total of 500 UT measurements of U/W hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawings 180 TE 700-
005 and 180 TE 1101-003 for guidance, in accordance with SFLC Std Spec 0740, Appendix C. Mark up a copy of Coast Guard Drawing 180 TE 1101-003 to show all locations selected for measurement and record all measurements in Table I (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit A CIR, to also include the marked up drawing and completed Table I.
4. NOTES
4.1 UT Table. Table 1 provided below is for the recording of all UT measurements.
12 (Rev-2)
TABLE 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL
SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT
PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE
13 (Rev-2)
63130_0320_FLT
REC_63130_100Percent_FLT_100' WLIC (315 CGC SMILAX) (0413)
WORK ITEM 2: U/W Body, Preserve (100%) - Tender
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve U/W body surfaces.
NOTES
1. The purpose of the preservation tasks covered by this item is to completely remove all existing coatings and recoat the U/W body surfaces with a new coating system.
2. U/W body surfaces are as defined in 4.1 (Definitions) and exclude areas covered by docking blocks, unless the vessel is fleeted for the express purpose of preserving blocked areas.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 180 TE 103-007, Rev 2, Booklet of Plans (SMILAX (315)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
14 (Rev-2)
• 3.2.3 Post-surface preparation cleaning and inspection
3.1.2 Tech Rep. The Contractor shall refer to SFLC Std Spec 0000, paragraphs 3.2.4.2.1 (Painting contractor certification program requirement) and 3.2.4.2.2 (Coating Tech Rep), for applicable requirements.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness. Specific areas/equipment/components to be protected include, but are not limited to:
• All scuppers and overboard discharges.
• Waterline area where U/W body coating system interfaces with freeboard coating system
(unless freeboard surfaces are also being preserved).
• Fathometer transducer surfaces.
• Sea valve openings.
• Propeller shaft bearings and seals.
• Rudder bearings.
• Propellers.
• Zinc anodes (unless anodes are being renewed).
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
• Sea chest grating.
3.1.5 Initial inspection. Prior to removing the existing coating system, the Contractor shall inspect and verify whether all draft marks have permanent markings (weld beads or impressions), showing their location on the hull. Submit a CFR.
3.1.6 Water used in preparation and washing procedures. The Contractor shall ensure that water used in all surface preparation tasks, including pre-surface preparation wash and water jetting, is of sufficient purity and quality that it does not prevent the surface being cleaned from achieving the required degree of surface cleanliness or non-visible contamination criteria.
3.1.6.1 Ensure that surface preparation water does not contain sediments or other impurities that are destructive to the proper functioning of the cleaning equipment.
3.1.6.2 Ensure that all water used in any surface preparation or cleaning procedures is captured, contained, and all spent water disposed of in accordance with all Federal, state and local regulations.
15 (Rev-2)
3.1.7 Surface preparation optional methods. The Contractor has the option of using either high/ultrahigh pressure water jetting or abrasive blasting to achieve the required surface preparation, prior to application of the coating system specified in 3.2 (Preservation requirements). The Contractor may add abrasives to the water jet stream, for one or both of the following reasons:
• Achieving greater productivity.
• Achieving the required surface profile.
NOTES
1. Existing coating system on the U/W body surfaces may have a nominal thickness in excess of that which was originally installed, because of “patch-coats” applied during past drydock availabilities.
2. Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.
3.2 Preservation requirements. The Contractor shall accomplish the following tasks:
3.2.1 Pre-surface preparation wash. Accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Refer to SSPC-SP 1, for guidance.
3.2.2 Surface preparation and coating application.
The Contractor shall accomplish the following tasks:
3.2.2.1 Prepare and coat the U/W hull surfaces with the system specified for “Underwater (U/W) Body and Boot-Top (U/W Body and Boot-Top, Steel Hulls (Up to 7 Years), in Salt Water”, in SFLC Std Spec
6310, Appendix A (Cutter and Boat Exterior Painting Systems). Ensure that the anticorrosive (AC) is tacky prior to applying the first antifouling (AF) top-coat.
3.2.2.2 Ensure that the first AF coat is applied over the AC undercoating, while it is still tacky.
3.2.3 Post-surface preparation cleaning and inspection. After completion of surface preparation and prior to coating application, accomplish the following tasks and submit a CIR.
3.2.3.1 Perform a visual inspection of the prepared U/W body steel substrate.
3.2.3.2 Perform solvent cleaning of all prepared surfaces, in accordance with SSPC-SP 1. Capture, contain, and dispose of all wastes from solvent cleaning, in accordance with all Federal, state and local regulations..
NOTE
Lists of all authorized coating materials and suppliers are listed in SFLC Std
Spec 6310, Appendix C (Cutter and Boat Authorized Coatings).
3.2.3.2 .
3.3 Draft mark painting. The Contractor shall paint all draft marks with two coats of a “Polysiloxane” or
“Silicone Alkyd Enamel” coating, at 2.0-3.0 mils DFT, white (17925).
16 (Rev-2)
3.4 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces). Surfaces being preserved are considered “critical-coated surfaces”.
3.5 AF system protective measures – in the event of prolong atmospheric exposure. If the vessel will not be refloated within the immersion time as recommended by the coating system manufacturer, the
Contractor shall employ suitable measures - including but not limited to keeping the coating system wet and away from direct sun light, to avoid film damage that may reduce or impact the final performance of the AF coating system when placed into service.
4. NOTES
4.1 Definitions.
4.1.1 U/W Body. The underwater body is defined as the areas from the bottom of the keel to the upper edge of the boot-topping, as shown on Coast Guard Drawing 180 TE 103-7, including rudders, transducer hull rings, sea chests (including the sea chest inlet up to the final connection with the flange face at the sea chest isolation valve(s)), bilge keels, struts, skegs, gratings, rope guards, and all other appendages.
17 (Rev-2)
63140_0320_FLT
REC_63140_100Prcnt_FLT_100' WLIC (315 CGC SMILAX) (0617)
WORK ITEM 3: Hull Plating Freeboard, Preserve “100%”
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve 100% of the freeboard surfaces defined in 4.1 Definition of freeboard surfaces.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 180 TE 0103-007, Rev 3, Booklet Of General Plans
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
18 (Rev-2)
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and contamination during the performance of work. Upon completion of work, remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.3.1 Apply protective measures as specified in SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection) to the following components, spaces and equipment:
• Areas where underwater body coating system interfaces with freeboard coating system
(unless u/w body surfaces are also being preserved).
• Adjacent deck surfaces and deck fittings.
• Deck equipment.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
• Towing knees.
3.2 Initial inspection. Prior to removing the existing coating system, the Contractor shall inspect and verify whether or not all hull identification numbers and letters have permanent markings (weld beads or impressions), showing their location on the hull. Submit a CFR.
3.3 Surface preparation optional methods. The Contractor shall have the option of using either high/ultrahigh pressure water Jetting or abrasive blasting to achieve the required surface preparation, prior to application of the coating system specified in 3.6 (Preservation requirements). The Contractor may add abrasives to the waterjet stream, for one or both of the following reasons:
• Achieving greater productivity.
• Achieving the required surface profile.
NOTE
Waterjetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.
3.4 Substrate inspection. After completing surface preparation and before coating application, the
Contractor shall perform a visual inspection of the prepared substrate, and submit a CFR.
3.5 Pre-surface preparation wash. The Contractor shall accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants.
Capture, contain, and dispose of wash water for proper disposal in accordance with all Federal, state and local regulations.
3.6 Preservation requirements. The Contractor shall accomplish the following tasks:
3.6.1 System particulars. Prepare and coat 100% of the freeboard surfaces as designated in paragraph 1.1
(Intent) with the system specified for “Freeboard/Superstructure/Mast (Freeboard/Superstructure)” in
SFLC Std Spec 6310. Select the following:
• Select “Option I” system, for the applicable metal substrate.
19 (Rev-2)
• Black (17038), as the top/finish coat color..
3.6.2 Visual identification markings. The Contractor shall paint all distinctive visual safety and identification markings as follows:
3.6.2.1 Decals. Coast Guard Emblem decals may be substituted for painted emblems. Vinyl adhesive letters and numbers may also be substituted for painted letters and numbers - at the Contractor’s discretion.
3.6.2.2 Painted markings. Paint all distinctive visual identification markings, including the Coast Guard diagonal stripes, "U.S. COAST GUARD" legends, hull numbers, and draft marks in accordance with
SFLC Std Spec 6310, and Coast Guard Drawings FL 2804-12 and FL 2804-22 as applicable.
NOTES
Surfaces being preserved are considered “critical-coated surfaces”.
Although there may be several possible procurement sources for the Coast
Guard Emblem decals and vinyl adhesive letters and numbers, one known source is:
Brace Enterprises
10250 SE 138 Terrace
Dunnellon, FL 34431
352-489-4442 / Fax: 352-489-4476 www.braceenterprise.com
3.6.3 Tear drop. Not applicable.
3.7 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control…